Corrugated Metal Culvert Pipe 0622 0747
Solicitation number
CRFQ 0803 DOT2200000170 1
Issued by
Webster County, West Virginia

About this file

This is a pricing exhibit for CRFQ DOT2200000170, a corrugated metal culvert pipe procurement. The contract involves the supply of corrugated steel culvert arch pipe in various sizes and configurations. The required items include five different pipe sizes ranging from 17" x 13" to 83" x 57", with quantities varying by size: five sections of 17" x 13" pipe, twelve sections of 21" x 15" pipe, ten sections of 42" x 29" pipe, thirteen sections of 57" x 38" pipe, and nine sections of 83" x 57" pipe. Additional band components are required for each pipe size, with quantities ranging from five to eight bands per size. All pipe shall be supplied in 20-foot sections and shall be zinc-coated (galvanized) corrugated steel constructed in accordance with Section 713.2 of the Standard Specifications.

Vendors are required to submit unit costs per 20-foot pipe section and per band in the designated pricing format. The extended line cost column is to be calculated by multiplying the unit cost by the estimated quantity for each line item. Vendors must provide a total cost for each pipe and band combination, allowing the procurement authority to evaluate the overall cost of the complete corrugated metal culvert pipe package across all specified sizes and quantities.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Item2

CORRUGATED METAL CULVERT PIPE - SUPPLEMENTAL

ATTACHMENT A - PRICING PAGE

Vendor Name:

ITEM 1
Part 1p =Pipe - Zinc coated (galvanized) corrugated steel culvert arch pipe
(type II), reference section 713.2 of the Standard Specs.
Pipe shall be in 20 foot sections. Unit Cost shall be per 20 foot
sections.
Part 1b =Bands - Shall be the bands for the previous Pipe. Unit Cost shall
be Each.
Part 1t =Total - Shall be the total cost for Part "p" and Part "b".
ITEM 2EstimatedExtended
Line #Item #Span x RiseUnit CostQuantityCost
11-1713/12p17" x 13" - 12 gauge5
21-1713/12bBand6
31-2115/12p21" x 15" - 12 gauge12
41-2115/12bBand6
51-4229/10p42" x 29" - 10 gauge10
61-4229/10bBand5
71-5738/10p57" x 38" - 10 gauge13
81-5738/10bBand8
91-8357/10p83" x 57" - 10 gauge9
101-8357/10bBand5