This is Addendum No. 5 to a Connecticut Resources Recovery Authority (CRDA) contract for Project 26-010, which concerns the abandonment and removal of dike penetrations and encroachments at the former MIRA Waste to Energy Facility. The addendum modifies the original bidding documents and must be acknowledged and submitted with all bids; failure to do so may result in disqualification. The bid deadline has been extended to December 4, 2025, at 1:00 PM, with additional addenda to follow along with the draft contract.
No pricing terms, set-asides, funding sources, or other financial details are specified in this addendum. The document serves primarily as a procedural notice confirming the project scope, extending the bidding timeline, and establishing receipt acknowledgment requirements for prospective bidders.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
November 14, 2025
Addendum #5
Abandonment/Removal of Dike Penetrations and Encroachments at the former MIRA Waste to Energy Facility
CRDA Project No. 26-010
This addendum dated November 14, 2025, forms a part of the Contract Documents and modifies the original bidding documents. Please acknowledge receipt of this Addendum below and submit with your bid. Failure to do so may subject the submitter to disqualification.
Bid Date will be extended to December 4, 2025 at 1:00 PM, additional addenda to follow with draft contract.
Submitter:
Signature:
End of Addendum #5