Cragfont_Dry_Stone_Wall_Reconstruction_Scope_of_Work.pdf
PDF 224 KB Posted
- Solicitation number
- Event 32701-13863
- Issued by
- Sumner County, Tennessee
About this file
This is a Scope of Work document issued by the Tennessee Historical Commission for the Cragfont Dry Stack Stone Wall Repair and Restoration Project at Cragfont State Historic Site in Castalian Springs, Tennessee. The project involves the repair and restoration of approximately 2,200 square feet of dry stack stone wall spanning approximately 600 feet in length, with the goal of restoring the structure to an average height of 3.5 feet including copestones. The work will be performed in fifty-foot sections and includes initial assessment and documentation with photography, careful disassembly with removal of modern repair materials, reconstruction using salvageable stones prioritized from the original wall, and quality assurance checkpoints after every three restored sections. Site Director Tonya Staggs and Project Coordinator Bobby Cooley serve as primary contacts for oversight and approval of design modifications, new stone sourcing, and quality assurance reviews.
All contractors must be licensed and insured professionals maintaining safety and professional standards throughout the project. A Licensed Masonry Contractor with LMC classification is required to bid, though General Contractors with BC, BC-B, or BC-B(sm) classifications may bid if they subcontract masonry work for projects valued over $100,000. Additionally, the contractor must hold a level three craft certification with the Dry Stone Walling Association or Master Craftsman level 3 certification with the Dry Stone Conservancy. The contractor is responsible for sourcing all additional stone required beyond salvageable materials from the original wall, with pricing included in the bid and subject to approval by the site director and program coordinator. The contractor must also manage all debris removal from the site, with truck trailers or dumpsters as the preferred removal method.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Site Location:
Cragfont State Historic Site
200 Cragfont Rd, Castalian Springs, TN 37031
Site Director(s):
Tonya Staggs director@historiccastaliansprings.org
(615)-452-7070
Project Coordinator:
Bobby Cooley
State Historic Site Program Coordinator
Bobby.cooley@tn.gov
629-395-8012
Project Name:
Tennessee Historical Commission: Cragfont Dry Stack Stone Wall Repair and
Restoration Project mailto:director@historiccastaliansprings.org mailto:Bobby.cooley@tn.gov
Scope of Work:
Evaluation
To determine the needs of the dry-stack stone wall at Cragfont State Historic Site, Contractor must follow guidelines of the Secretary of the Interior’s Standards for
Rehabilitation and Guidelines for Rehabilitating Historic Buildings, specifically noting the
Building Exterior, Masonry: Brick, Stone, Terra-Cotta, Concrete, Adobe, Stucco, and
Mortar.
Basic Requirements
1. All contractors and work must be done by licensed and insured professionals.
Any crew on site will maintain all safety requirements during the construction process and act in a professional manner as expected in an area where the public may be allowed access.
2. A Licensed Masonry Contractor (LMC classification) is required to bid on this project. A General Contractor with a BC, BC-B, or BC-B(sm) classifications may also bid on the project, but shall subcontract masonry work to a licensed masonry contractor if the work is valued over $100,000.00.
3. Contractor shall have a level three craft certification with the Dry Stone Walling
Association or a Master Craftsman (level 3) certification with the Dry Stone
Conservancy.
4. Contractor shall clean up all related debris during the job. Contractor is responsible for removing all debris from the site. Truck trailers and/or dumpsters preferred method of removal.
Scope
This scope of work will focus on repairing and restoring approximately two thousand two hundred (2,200) square feet (six hundred (600) feet in length) dry stack stone wall at
Cragfont State Historic Site. The goal is to restore, repair, and reconstruct the wall across the entire length of the structure to an average height of three and one half (3.5) feet, including the copestones.
Contractor shall do all the following without exception:
1. Initial Assessment and Documentation:
• Perform a thorough evaluation of the dry stack stone wall to determine and document all existing conditions, necessary repairs, and specific restoration requirements for the sashes, frames, and associated millwork.
• Photograph the stone wall in a manner to assist with reconstruction.
2. Careful Disassembly:
• In fifty (50) foot sections at a time, dismantle the stonework of the wall.
• After dismantling each section, remove all Portland cement or other modern materials used to temporarily repair sections of the wall in the past.
• Evaluate available stone to reuse and document where additional will be needed to replace cracked and unusable stones.
3. Reconstructing the dry stack stone wall
• Using the photographic evidence required in the documentation phase, reconstruct the dry stack stone wall in fifty (50) foot sections based on the design and layout of how it was previously constructed, including the copestones.
• The reconstruction process shall use all salvageable stones from the original wall first.
- Contractor is responsible for sourcing all additional stone required to reconstruct the wall. This price shall be included in the quote and an approval by site director and program coordinator is required before agreeing on new stone being suggested.
- Slight changes to the original design are permitted based on stones available, trees surrounding the wall, gates, and the new request to adhere to a three and one half (3.5) foot height across the length of the wall. Significant changes are required to be brought to program coordinator and site director for approval.
4. Quality Check:
• When at least three (3) sections of fifty (50) foot wall are restored, a check in with the site director and program coordinator is required for quality assurance and design approval.