County_LD_Schedule_(for_purchasing_only).xlsx

XLSX spreadsheet 22 KB Posted

Attached to
ARPA Stormwater Starkey Facility M10 Modification (PID 003900A) (Rebid)
Solicitation number
24-0692-ITB-C
Issued by
Pinellas County, Clewiston City, Florida

About this file

The document is a Liquidated Damages Calculator spreadsheet from a county government in Florida, specifically related to the APRA Stormwater Starkey Facility M10 Modification (Rebid) project with PID No. 003900A. The project involves retrofitting and enhancing an existing stormwater management facility by constructing a weir and two upstream stormwater ponds to improve water quality treatment and maintain existing flood prevention capabilities within the Starkey Watershed. The total project duration is 548 calendar days, with an Engineer's estimated construction cost of $7,044,066.00.

The liquidated damages for this project are calculated at $1,387.19 per day of delay, which includes components such as design consultant fees ($76.30 per day), construction administration/inspection costs ($1,236.00 per day), and project management rates. The calculation methodology considers various potential damages, including design consultant fees, construction administration expenses, and hourly rates for project managers. The document provides detailed guidelines for determining liquidated damages, emphasizing the importance of reasonable and documentable cost calculations that reflect actual potential project delays and associated expenses.

View the file

Other files

File Type Posted
ARPA_Stormwater_Starkey_Facility_M10_Modification_(PID_003900A)_(Rebid).pdf PDF
Appendix_1_-_Permits.pdf PDF
Appendix_6-Tierra_Geotechnical_Engineering_Services_Report-4-7-2022.pdf PDF
Appendix_4_-_Special_Notices.pdf PDF
Appendix_6-Geosyntec_Geotechnical_Evaluation-4-17-2020.pdf PDF
SBE_Compliance_Form.pdf PDF
Sample_Agreement-24-0692.pdf PDF
Appendix_6-Geosyntec_Soil_Characterization_Testing_Results_Summary-3-24-2020.pdf PDF
Appendix_6-Geosyntec_Supplemental_Soil_Sampling_Results_Summary-3-18-2024.pdf PDF
FINAL_PLANS_2024-02.pdf PDF
Final_Plan_Sheet_32_REVISED_.pdf PDF
Pricing_Proposal-24-0692(reference_only).pdf PDF
Supplemental_Specifications.pdf PDF
Appendix_6-Intertek_PSI_Geotechnical_Engineering_Services_Report-3-29-2019.pdf PDF
Performance_and_Payment_Bonds.pdf PDF
Affdavit_of_Release_and_Guarantee24-0692.pdf PDF
QUALIFICATION_SUBMITTAL_FORM.pdf PDF
Project_Location_Map_(For_Legistar_Only).pdf PDF
Sample_Application_for_Payment.pdf PDF
Bid_Submittal_Form-JOC.pdf PDF
Florida_Trench_Safety_Form.pdf PDF
OpenGov_Fillable-_Final.pdf PDF
PFO_(for_Purchasing_Only).pdf PDF
Sample_Change_Order.pdf PDF
Airport_Security_Program.pdf PDF
E-Verify_Affidavit.pdf PDF
EOR_SBE_Letter_(for_Purchasing_only).pdf PDF
Engineer_Estimate-Final-20240410.xls XLS spreadsheet
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table

LIQUIDATED DAMAGES CALCULATOR
Project: APRA Stormwater Starkey Facility M10 Modification (Rebid)
PID No.: 003900A
Enter Design Consultant's total post design fee$ 40,000.00
Enter Construction Administrator's total FeeN/A
Duration of Construction (calendar days)548
Enter Total Project Enclosed Square Footage (if applicable)N/A
Enter Total Daily Department PM/APM Full time EquivalentsN/A
Engineer's Estimate of probable construction cost$ 7,044,066.00
Elements for Liquidated Damages Determination:
Design Consultant Fees$ 76.30Total post design fee divided by construction duration *3%
Construction Administration/Inspection$ 1,236.00Daily combined burdened rate for CA staff + Consultant CEI
Project Manager/Assistant Project Manager$ 74.89(1 hour/day burdened rate)
Department Project Overhead$ - 0
Agency Administrative Costs$ - 0
Temporary Heat/Cooling/Electric$ - 0
Temporary Storage of Owner Provided FFE$ - 0
Rental/Lease of Facilites for Staff, and/or Clients$ - 0
Lost revenues$ - 0
Lost grant revenues$ - 0
Interest$ - 0
Rental / moving expenses$ - 0
Cost for Insurance
Other
Total Liquidated Damages Amount per day$ 1,387.19
Prepared by:
Edit Highlighted Areas

Definitions

A. LIQUIDATED DAMAGES:
Liquidated damages are a specific sum (or a sum readily determinable) of money, stipulated by the contracting parties, as the amount to be recovered for each day of delay in delivery of the product.
Typically, the actual damage amount is unknown or difficult to estimate and is liquidated by the mutual agreement to the rate. Liquidated damages must be based on a reference to a definite standard, such as market value, established experience, or direct inference from known circumstances.
Liquidated damages can not be speculative or a penalty.
B. RATE DETERMINATION:
The amount of liquidated damages must be reasonable to ensure that the damages will not be held to be unenforceable. Therefore, the rate of liquidated damages, also, must be reasonable and is figured on a project-by-project basis.
On the other hand, you do not want to set the liquidated damages at too low an amount. Once liquidated damages are included in a contract, you will be unable to recover actual damages in excess of the specified amount.
C. HOW TO DETERMINE THE AMOUNT OF ANTICIPATED ACTUAL DAMAGES IN ORDER TO ESTABLISH AN APPROPRIATE AMOUNT FOR LIQUIDATED DAMAGES:
Examples of Elements of Rate Determination are listed below (All rates to be based on daily cost). The following list of criteria should be considered when determining anticipated damages that may be caused by a delay in the completion of a project.
Some of these are hard costs; others are based upon nonquantifiable factors.

*Design Consultant Fees – calculated as the construction administration portion of the consultant fee divided by the construction duration multiplied by 3% per year based on duration. If not known, use estimate.

*Construction Administration Fee - Generally calculated by the Construction Division; however, if Construction Division is not inspecting, cost can be based on the total cost for CA divided by the construction duration (multiplied by 3%/year).
FDOT grant funded projects will use the FDOT LD Schedule.
*Project Manager/Assistant Project Manager Time – Hourly burdened rate of PM or APM.
*DPW Project Overhead - based upon daily rate for DPW administrative overhead costs not recovered in PM billing rate.
*Agency Administrative Costs – based upon daily rate for agency personnel assigned to work on project or agency personnel required to spend a portion of their time should be included at that percentage of the daily rate.
*Temporary Heat/Cooling/Electric, Owner provided – Per S.F. of project area/day.
*Temporary Storage of Owner provided FFE – Costs for storage of Furniture, Fixtures, and Equipment, or other storage of products or materials caused by the delayed turn over of the facility.
*Rental/Lease of Facilities for Staff, and/or Clients – calculated in coordination with the agency representative based upon specific needs and available alternatives.
*Loss of revenue - Loss of potential revenue from a facility not opening as scheduled.
*Loss of grant - Loss of grant funding should the project not be completed on time.
*Interest (on borrowed funds) during unexcused delays in completion or periods of non-use.
*Rental/moving or other expenses for alternate space.
*Costs for insurance, utilities, or equipment.
D. HOW TO DOCUMENT THE MEANS BY WHICH LIQUIDATED DAMAGES ARE ESTABLISHED:
1. Determine your anticipated actual per diem damages using criteria such as those listed above.
2. Determine the appropriateness of the figure arrived at in Step 1. The anticipated figure may be used, or a percentage of that figure may be determined to be more appropriate for liquidated damages.
3. Create a typewritten document of the criteria, calculations, and judgments used above.
4. Place the documentation with the Contracts Unit project file for future reference. It is essential to keep all of the records used to determine the per diem liquidated damages amount.
This documentation is important to resolve possible future claims, for audit purposes, and for reference in developing future liquidated damages clauses.