Cottonwood Submittal Reg.xlsx
XLSX spreadsheet 28 KB Posted
- Attached to
- UNITED STATES FOREST SERVICE, ROCKY MOUNTAIN REGION 2, ROAD AND BRIDGE CONSTRUCTION SERVICES MATOC
- Solicitation number
- 1240LU24R0013
- Issued by
-
Department of Agriculture Forest Service
About this file
This file is a submittal register template for road and bridge construction services under a USFS Region 2 MATOC contract. The register details required contractor submissions for two example projects, including various plans, certifications, documentation, and drawings that must be submitted for government review and approval.
Key required submittals include: Quality Control Plan, Hazardous Spill Plan, Fire Prevention Plan, Erosion Control Plan, Construction Schedule, Traffic Control Plan, Bridge Removal Plan, concrete mix designs, structural steel certifications, shop drawings for bridge components, and as-built drawings. The template includes columns for tracking submission dates, review status, and government acceptance. For the first example project, several items were submitted around September 2023 with work continuing through early 2024. The register serves as a tracking tool for contractors to manage and document all required submissions throughout the project lifecycle.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Past Performance Questionnaire.docx | DOCX document | |
| Cottonwood Plans 2.pdf | ||
| Cottonwood Plans 1.pdf | ||
| Berry Creek Plans.pdf | ||
| Washakie Plans.pdf | ||
| Washakie Food Storage Order.pdf | ||
| Washakie TOPR.pdf | ||
| Berry Creek TOPR.pdf | ||
| Cottonwood TOPR.pdf | ||
| 1240LU24R0013 Region 2 Road and Bridge MATOC.pdf | ||
| Washakie FSSS.pdf | ||
| Washakie SOI.xlsx | XLSX spreadsheet | |
| Cottonwood SOI.xlsx | XLSX spreadsheet | |
| Berry Creek Submittal Reg.xlsx | XLSX spreadsheet | |
| Berry Creek FSSS.pdf | ||
| Berry Creek SOI.xlsx | XLSX spreadsheet | |
| Equipment Cleaning Form_Fillable_20241203.pdf | ||
| Cottonwood Map.pdf | ||
| Cottonwood FSSS.pdf | ||
| R2 Fire Plan.pdf |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittals Reqd All ITOPs
| EXAMPLE ITOP SUBMITTAL REGISTER | Project Title: EXAMPLE ITOP | Contract Number: | ||||||
| Project Location: FOREST NAME, DISTRICT, AND/OR NFSR | Contractor: EXAMPLE Contractor | |||||||
| TO BE COMPLETED BY CONTRACTOR QUALITY CONTROL MANAGER OR PROJECT SUPERINTENDANT | ||||||||
| Item Number | Specification Section | |||||||
| and Pargraph Number / Table Number | DESCRIPTION OF ITEM SUBMITTED | |||||||
| (include if it is shop drawings, plans, product data, manufacturer's instructions, samples, test reports, certifications, etc.) | CLASSIFICATION | Contractor Submission | Government Review | REVIEW REMARKS | ||||
| Government Approval | Government Acceptance | Date Submitted to Government (QC Review of Submittal Performed Prior to Submission) | Date Submittal Returned to Contractor | Submittal Review Code |
Approved/Disapproved Accepted/Not Accepted
| 1 | Section H | Hazardous Conditions Safety Plan | X | 9/9/23 | 9/15/23 | Accepted | ||
| 2 | Section H | Progress Schedule | X | 9/9/23 | 9/16/23 | Approved | ||
| 3 | Section H | Designation of Represetnatives | X | 9/9/23 | 9/16/23 | Approved | ||
| 4 | FAR 52.222-11 | SF1413 - ABC Co.C24, XKJ Interprises, TSI Labs | X | 9/9/23 | 9/16/23 | Accepted | ||
| 5 | Section H or C??? | Fire Prevention and Control Plan | X | 9/9/23 | 9/16/23 | Accepted | ||
| 6 | Section H | Temporary Traffic Control Plan | X | 9/9/23 | 9/16/23 | Approved | ||
| OSHA 1926.65 (4) | Site Specific Safety and Healthy Plan | X | Due prior to start of work on site | |||||
| 8 | Section H | Erosion Control Plan | X | 9/9/23 | 9/16/23 | Approved | ||
| FP 109.01 | Measurement Notes and Records | X | Due within 24 hours of completeing work that is in-place and complete according to contract. | |||||
| 9 | FP 157.14 | Erosion Control Inspection Reports | X | 9/9/23 | 9/16/23 | Accepted | ||
| 10 | FP 107.10 / Section H | Spill Prevention and Control Countermeasures Plan (SPCCP) | 9/9/23 | 9/16/23 | Accepted | Due 2 days before beginning work | ||
| FP 107.10 | Hazardous Spill Plan | X | Required when SPCCP is not required by contract. Due 2 days before beginning work. | |||||
| 11 | FP 153.03 | Quality Control Plan | X | 9/9/23 | 9/16/23 | Approved | ||
| 12 | FP 153.07 (b) | Testing Control Charts, November 2023 | X | 12/5/23 | 12/7/23 | Accepted | ||
| 13 | FP 153.07 (b) | Testing Control Charts, December 2023 | X | 1/5/24 | 1/8/24 | Accepted | ||
| 14 | FP 153.07 (b) | Testing Control Charts, January 2024 | X | 2/5/24 | 2/9/24 | Accepted | ||
| 15 | FP 204-1 | Select Borrow Material, Source Classification, Gradation, Liquid Limit | X | 10/1/23 | 10/14/23 | Accepted | ||
| 16 | FP 204-1 | Select Borrow Material, Production, Classification, Gradation, Liquid Limit, Moisture-density | X | 10/1/23 | Accepted | |||
| 17 | FP 204-1 | Select Borrow Material, Production, Density, In Place, Sta. 1+50- 2+50, Layer 1-5 | X | 10/21/23 | Accepted | |||
| 18 | FP 204-1 | Select Borrow Material, Production, Density, In Place, Sta. 1+50- 2+50, Layer 6-10 | X | 11/15/23 | Accepted | |||
| 18.1 | FP 204-1 | Topping Material, Source, Classification | X | 10/25/23 | Not Accepted | Soil classification shall be A-1 or A-2-4. | ||
| 19 | FP 204-1 | Resubmit: Topping Material, Source, Classification | X | 10/25/23 | Accepted | |||
| 20 | FP 201-1 | Topping Material, Production, Moisture-Density, Processed | X | 11/21/23 | Accepted | |||
| 21 | FP 201-1 | Topping Material,Production, Density, In-place | X | 11/30/23 | Accepted | |||
| 22 | FP 251-1 | Riprap Material, Class 1, Source | X | 10/1/23 | Accepted | |||
| 23 | FP 251-1 | Riprap Material, Class 1, Production | X | 12/5/23 | Accepted | |||
| 24 | FP 251-1 | Riprap Material, Class 2, Source | X | 10/1/23 | Accepted | |||
| 25 | FP 251-1 | Riprap Material, Class 2, Production | X | 1/15/24 | Accepted | |||
| 26 | FP 301-1 | Surface Course Aggregate, Commercial Source, LA Abbrasion, Soundness, Fractured Faces, LL | X | 10/1/23 | Accepted | |||
| 27 | FP 301-1 | Surface Course Aggregate, Commercial Source, Plasticity Index | X | 10/1/23 | Accepted | |||
| 28 | FP 301-1 | Surface Course Aggregate, Production, Gradation | X | 12/15/23 | Accepted | |||
| 29 | FP 301-1 | Surface Course Aggregate, Production, Moisture-density, Density, Moisture Content, Fractured Faces | X | 12/15/23 | Accepted | |||
| 30 | FP 602.06 | Plastic Pipe, Corrugated Polyethelene, 12", Manufacturer's Instructions | X | 10/1/23 | Accepted | |||
| 30.1 | FP 708 | Plastic Pipe, Corrugated Polyethelene, 12", Product Data | X | 10/1/23 | Accepted | |||
| 32 | FP 208 | Cofferdams Drawings | X | 10/15/23 | 10/25/23 | Approved | ||
| 33 | FP 104.03 (b) | As-built Drawings, Final | X | 1/31/24 | 2/10/24 | Approved |
NOTES: The contractor is ultimately responsible for identifying and providing all submittals required by the Individual Project Task Orders. The contractor shall submit the initial submittal register to the CO within 14 days of Notice to Proceed and shall update the submittal register through the project.
Page &P of &N
Submittal EXAMPLE ITO
| EXAMPLE ITOP SUBMITTAL REGISTER | Project Title: South Cottonwood Bridge Replacement | Contract Number: | ||||||
| Project Location: PSICC - Salida RD - NFSR 344 | Contractor: | |||||||
| TO BE COMPLETED BY CONTRACTOR QUALITY CONTROL MANAGER OR PROJECT SUPERINTENDANT | ||||||||
| Item Number | Specification Section | |||||||
| and Paragraph Number / Table Number | Plan Sheet Reference | Specifications Reference | DESCRIPTION OF ITEM SUBMITTED | |||||
| (include if it is shop drawings, plans, product data, manufacturer's instructions, samples, test reports, certifications, etc.) | CLASSIFICATION | Contractor Submission | Government Review | REVIEW REMARKS | ||||
| Government Approval | Government Acceptance | Date Submitted to Government | ||||||
| (QC Review of Submittal Performed Prior to Submission) | Date Submittal Returned to Contractor | Submittal Review Code |
Approved/Disapproved Accepted/Not Accepted
| 1 | Equipment Inspection | N/A | Special Contract Requirement 107 | Equipment Inspection |
| 2 | Written Plan | N/A | Std. Specification Section 153 and Special Contract Requirement 153 | Quality Control Plan |
| 3 | Written Plan | N/A | Special Contract Requirement 153 | Proposal for Alternate Test Methods (if applicable) |
| 4 | Written Plan | N/A | Special Contract Requirement 107 | Hazardous Spill Plan |
| 5 | Written Plan | N/A | Special Contract Requirement 107 | Fire Prevention and Suppression Plan |
| 6 | Written Plan | N/A | Special Contract Requirement 157 | Erosion Control Plan |
| 7 | Written Plan | N/A | Standard Specification Section 157 | Inspection Reports |
| 8 | Written Plan | N/A | Special Contract Requirement 203 | Bridge Removal Plan |
| 9 | Written Plan | N/A | Special Contract Requirement 155 | Written Plan for Construction Schedule |
| 10 | Written Plan | N/A | Special Contract Requirement 156 | Written Plan for Alternate Traffic Control Plan |
| 11 | Written Plan | N/A | Special Contract Requirement 156 | Written Plan for Emergency Access Plan |
| 12 | Written Plan | N/A | Standard Specification Section 563 | Painting Plan |
| 13 | Written Notice | N/A | Standard Specification Section 555 | Notice of Beginning Shop Work for Structural Steel Fabrication |
| 14 | Certification/Documentation | N/A | Special Contract Requirement 107 | Noxious Weed Certification (Vehicles) |
| 15 | Certification/Documentation | N/A | Standard Specification Section 153 | Certification of Quality Control Personnel |
| 16 | Certification/Documentation | N/A | Special Contract Requirement 153 | Documentation of Testing Equipment |
| 17 | Certification/Documentation | N/A | Standard Specification Section 552 | Admixture Compatibility |
| 18 | Certification/Documentation | N/A | Standard Specification Section 552 | Concrete Mix Design |
| 19 | Certification/Documentation | N/A | Standard Specification 554.10 | Rebar Production Certification |
| 20 | Certification/Documentation | N/A | Standard Specification Section 153 | Material Certifications |
| 21 | Certification/Documentation | N/A | Standard Specification Section 157 | Certification of Erosion Control and Sediment Control Personnel |
| 22 | Certification/Documentation | Sheet 12 | NA | Pipe Connector Pull-out Capacity |
| 23 | Certification/Documentation | Sheet 16 | NA | Timber posts species/grade |
| 24 | Certification/Documentation | N/A | Standard Specification Section 555 | AISC Quality Certification |
| 25 | Certification/Documentation | N/A | Standard Specification Section 555 | Structural Steel Mill Test Reports and Production Certifications |
| 26 | Certification/Documentation | N/A | Special Contract Requirement 611 | Certification of Water Line Installer |
| 27 | Documentation | N/A | Standard Specification 109.01 | Measurement Notes |
| 28 | Documentation | N/A | Standard Specification Section 153 | QCP and Construction Operation Report |
| 29 | Documentation | N/A | Standard Specification 203.05 (a) and (d) | Disposal Agreements, Statements, and Permits |
| 30 | Documentation | N/A | Special Contract Requirement 208.06 | Cofferdam fill source, construction and restoration method (if applicable) |
| 31 | Documentation | N/A | Standard Specification 552, Table 552-9 | Concrete Test Results/ Report |
| 32 | Documentation | N/A | Standard Specification 301.03 | Target Values for Aggregate |
| 33 | Documentation | Sheet 16 | NA | Preservative ASSAY retention report |
| 34 | Sample | N/A | Special Contract Requirement 552 | Water Repellent Concrete Sealer |
| 35 | Drawings | N/A | Standard Specification 208 | Working Drawings & Construction Details of Excavation Support Systems (if applicable) |
| 36 | Drawings | N/A | Special Contract Requirement 552 | Stay-In-Place Forms/Erection Shop Drawings & Calculations |
| 37 | Drawings | N/A | Standard Specification Section 555 | Structural Steel Shop Drawings & Camber Diagrams |
| 38 | Drawings | N/A | Special Contract Requirement 554 | Rebar Shop Drawings |
| 39 | Drawings | Sheet 14 | N/A | Bridge Rail Shop Drawings |
| 40 | Drawings | Sheet 16 | N/A | Approach Rail Shop Drawings |
| 41 | Drawings | N/A | Special Contract Requirement 104 | As-Built Drawings |
| NOTES: | The contractor is ultimately responsible for identifying and providing all submittals required by the Individual Project Task Orders. The contractor shall submit their proposed revisions to the initial submittal register to the CO within 14 days of Notice to Proceed and shall update the submittal register through the project. |