COT_Joaquin_Murrieta_Park_Splash_Pad_Bid_Schedule_-_Addendum_1.xlsx

XLSX spreadsheet 15 KB Posted

Attached to
Joaquin Murrieta Park Splash Pad
Solicitation number
250041
Issued by
Pima County, Tucson City, Arizona

About this file

This document is an Invitation for Bid (IFB) Addendum 1 for the Joaquin Murrieta Park Splash Pad project issued by the City of Tucson, Arizona. The bid schedule details a comprehensive construction project encompassing multiple work categories including general conditions, wet utilities, grading, landscaping, electrical connections, splash pad construction, ramadas, and restroom building construction. The project is located at 1400 N. Silverbell Road in Tucson and involves creating a new splash pad facility with associated infrastructure, featuring specific quantities such as 22 linear feet of 3" water line, 28 linear feet of 2" water line, 4 light poles, 3 picnic tables, 15 fifteen-gallon trees, and 5,294 square feet of splash pad area.

The bid schedule indicates a detailed breakdown of work items, with all line items currently showing $0 pricing, suggesting this is a preliminary bidding document awaiting contractor pricing. The project includes comprehensive elements like dust control, stormwater pollution prevention (SWPPP), irrigation systems, concrete work, landscaping, electrical connections, safety fencing, and 90-day establishment period. While specific funding sources and budget are not explicitly detailed in this document, the project appears to be a municipal infrastructure improvement initiative aimed at enhancing recreational facilities in the Tucson community.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

JMP Splash Pad

IFB 250041 - Joaquin Murrieta Park Splash Pad
Joaquin Murrieta Park Splash Pad -- Bid Schedule
Project Location :Tucson, Arizona
Bid Advertisement :TBD
Addendum 1
Item DescriptionQuantityUnitUnit PriceAmount
General Conditions and Infrastructure Work
General Conditions1LS$0
Surveying
Survey & Layout1AC$0
Dust & Erosion Control
Dust control1AC$0
SWPPP1AC$0
New Wet Utilities
3" Sch 80 Water Line22LF$0
2" Sch 80 Water Line28LF$0
1" Sch 80 Water Line76EA$0
1" Quick Coupler2EA$0
6" Sewer Line61LF$0
Sanitary Sewer Cleanout2EA$0
Fine Grading and Preparation for Construction
Fine Grading43,560SF$0
Over excavate 24" under Building Foundations95CY$0
Grading for Paving/Sidewalks2,935SF$0
Sidewalks
4" Concrete Sidewalks2,935SF$0
Landscaping
Irrigation - Lawns (New & Restored)1LS$0
Turf - Sod - New Lawns7,730SF$0
15 Gallon Tree15EA$0
1/4" Rock Mulch2,005SF$0
Concrete Mow Strip60LF$0
Drip Irrigation1LS$0
Irrigation - Mains & Controls1LS$0
90 Day Establishment3MO$0
Light poles and Electrical Connections
Conduit & Electrical Connections1LS$0
Concrete Light Pole Bases4EA$0
Light Poles4EA$0
Concrete Benches & Picnic Tables
CIP Concrete Benches40LF$0
Picnic Tables3EA$0
Splash Pad Construction
Site prep5,294SF$0
Splash Pad Equipment5,294SF$0
Splash Pad Wet Area Construction5,294SF$0
Splash Pad Play Features5,294SF$0
Splash Pad Electrical1LS$0
Splash Pad Safety Fencing250LF$0
Ramadas Construction
Small Metal Ramada3EA$0
Trash Cans and Dog Waste Stations
Trash Cans3EA$0
Restroom Building Construction
Restroom Building Construction1,278SF$0

CONSTRUCTION TOTAL $0