Cost Breakdown.docx

DOCX document 15 KB Posted

Attached to
Demolish Building 100 Jones Hall Mountain View CA
Solicitation number
36C26125R0092
Issued by

About this file

The document is a Cost Breakdown template for a demolition project at Jones Hall in Mountain View, California. The template provides a structured format for presenting project costs by division, with sections for general requirements, other expenses, subtotals, bonds and insurance, overhead, and profit, culminating in a total project bid amount.

This cost breakdown is associated with a Veterans Affairs solicitation (36C26125R0092) for demolishing Building 100 at the Palo Alto Health Care System campus. The procurement is 100% set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) under VISN 21 MACC Group 2. Key dates include a site visit on October 23, 2025, at 10:00 AM PST, RFIs due by October 28th at 8:00 AM PST, and offers due by November 17th, 2025, at 8:00 AM PST. The contract will be awarded based on price, with the contractor expected to minimize construction impact on daily VA operations.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DIVISIONAL COST BREAK-OUT

CLIN 0001

Demolish Building One-hundred Jones Hall, Mountain View, California

Provide complete Divisional Cost Break-Out for complete project. If necessary, add additional lines for each Division applicable to this project.

REF
DESCRIPTION
TOTAL

010000

DIVISION 1 - GENERAL REQUIREMENTS

OTHER

OTHER
$
OTHER
OTHER
$

SUB TOTAL:

BONDS & INSURANCE

OVERHEAD

PROFIT

TOTAL PROJECT BID AMOUNT: