Cooling Tower Replacement Specs.pdf
PDF 2 MB Posted
- Solicitation number
- PE-67800-NONST-2024-000000012
- Issued by
- Jefferson County, Georgia
About this file
This is a set of construction specifications for the Jackson County Courthouse Cooling Tower Replacement project in Jefferson, Georgia. The specifications outline the scope of the project, which involves demolishing and replacing the existing 500-ton, two-cell, counterflow cooling tower with a new cooling tower of equal capacity. The work is to be performed during a 4-calendar day period, and includes modifications to the electrical system and building automation system. The specifications provide detailed requirements for the demolition, installation, testing, and documentation of the new cooling tower system. The project is to be procured through a lump-sum contract with the Owner. No pricing terms, set asides, or funding information is provided in the specifications.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Construction Documents for
Jackson County Courthouse Cooling Tower Replacement
5000 Jackson Parkway Jefferson, GA 30549
For Construction Documents
PRIME CONSULTANT / MECHANICAL ENGINEER
Johnson, Spellman & Associates, Inc.
350 Research Court, Suite 130 Peachtree Corners, GA 30092
(770) 447-4555 www.jsace.com
JSA PROJECT NUMBER 24JS63
August 30, 2024
Jackson County Courthouse Cooling Tower Replacement CONTENTS
1 8/30/2024
CONTENTS
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
006519 Release and Waiver of Claim 006536 Contractor Warranty 009400 Modification Procedures
DIVISION 01 - GENERAL REQUIREMENTS
011100 Summary of Work 011400 Work Restrictions 012500 Substitution Procedures 012976 Applications for Payment 013113 Project Coordination 013216 Progress Schedules 013323 Shop Drawings and Submittals 015000 Temporary Facilities and Controls 017123 Field Engineering 017329 Cutting and Patching 017416 Cleaning 017600 Protective Measures 017719 Project Closeout
DIVISION 09 - FINISHES
099000 Painting and Coating
DIVISION 23 - HEATING, VENTILATION, AND AIR CONDITIONING (HVAC)
230010 General Provisions – HVAC 230100 Operation and Maintenance of HVAC Systems 230500 Common Work Results for HVAC 230514 Variable Frequency Drives 230523 HVAC Valves and Strainers 230553 Identification for HVAC Piping and Equipment 230593 Testing Balancing and Adjusting 230700 HVAC Insulation 230923 Building Automation and Temperature Controls System 232000 Pipe, Fittings, and Accessories – HVAC 232113 Hydronic Piping 232500 Water Treatment Systems 236500 Cooling Tower 238237 Miscellaneous Electric Heaters
DIVISION 26 - ELECTRICAL
260010 Supplemental Requirements for Electrical 260505 Selective Demolition for Electrical 260519 Low-Voltage Electrical Power Conductors and Cables 260526 Grounding and Bonding for Electrical Systems 260529 Hangers and Supports for Electrical Systems
260533.13 Conduit for Electrical Systems
260533.16 Boxes for Electrical Systems
260553 Identification for Electrical Systems 260583 Wiring Connections
Jackson County Courthouse Cooling Tower Replacement CONTENTS
2 8/30/2024
262406 New Overcurrent Devices in Existing System 262726 Wiring devices
262816.16 Enclosed Switches
Jackson County Courthouse Cooling Tower Replacement RELEASE AND WAIVER OF CLAIM Section 006519
1 8/30/2024
SECTION 006519
RELEASE AND WAIVER OF CLAIM
PRIME CONTRACTOR
On ____________, 20 there personally appeared before me the undersigned authority in and for said
County of _______________ State of ________________ (Name)
________________________________, the _____________________ of (Company)
_________________________________________, who being duly sworn by me, states that all payrolls, materials bills, sales tax, privilege tax or license, old age benefits tax, state and federal unemployment insurance and other liabilities have been paid in full, incurred for use in the performance of the contract for
_______________________________________ and waives any claims and releases
____________________________________________, from any rights or claims for debts due and owing by virtue of the furnishing of any material or supplies of any lien thereon.
Sworn to and subscribed before me this __________ day of _________, 20____.
By: (Signature)
Title:
Date:
SEAL:
(Notary Public)
Date:
END OF SECTION 006519
Jackson County Courthouse Cooling Tower Replacement CONTRACTOR WARRANTY FORM Section 006536
1 8/30/2024
SECTION 006536
CONTRACTOR WARRANTY FORM
(To be typed on Contractor's letterhead)
PROJECT: ____________________________________________
LOCATION: ____________________________________________
OWNER: ____________________________________________
We,____________________________________________ contractor for (Company Name)
The above referenced project, do hereby warrant that all labor and materials furnished and work performed are in accord with the Contract Documents and authorized modifications thereto, and will be free from defects due to defective materials or workmanship for a period of one (1) year from Date of Final Completion.
This warranty commences on (Date of Final Completion affixed by Architect), and expires on (Expiration Date). Should any defect develop during warranty period due to improper materials, workmanship or arrangement, the same shall, upon written notice by the Owner, be made good by the undersigned at no expense to the Owner.
Nothing in the above shall be deemed to apply to work which has been abused or neglected by the Owner.
DATE:_________________ FOR:
(Company Name)
BY:
TITLE:
END OF SECTION 006536
Jackson County Courthouse Cooling Tower Replacement MODIFICATION PROCEDURES Section 009400
1 8/30/2024
SECTION 009400
MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section specifies administrative and procedural requirements for handling and processing contract modifications.
B. Related Sections: The following Sections contain requirements that relate to this Section:
1. Division I Section "Shop Drawings and Submittals" for requirements for the Contractors Construction Schedule.
2. Division I Section "Applications for Payment" for administrative procedures governing Applications for Payment.
3. Division 1 Section "Substitution Procedures" for administrative procedures for handling requests for substitutions made after award of the Contract.
1.3 CHANGE ORDER PROPOSAL REQUESTS
A. Owner-Initiated Proposal Requests: The Engineer will issue a detailed description of proposed changes in the Work that will require adjustment to the Contract Sum or Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.
1. Proposal requests issued by the Architect are for information only. Do not consider them as an instruction either to stop work in progress or to execute the proposed change.
2. Within 10 days of receipt of a proposal request, submit an estimate of cost necessary to execute the change to the Engineer for the Owner's review.
a. Include a list of quantities of products required and unit costs, with the total amount of purchases to be made. Where requested, furnish survey data to substantiate quantities.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include a statement indicating the effect the proposed change in the Work will have on the Contract Time.
B. Contractor-Initiated Proposals: When latent or unforeseen conditions require modifications to the Contract, the Contractor may propose changes by submitting a request for a change to the Engineer.
1. Include a statement outlining the reasons for the change and the effect of the change on the Work.
Jackson County Courthouse Cooling Tower Replacement MODIFICATION PROCEDURES Section 009400
2 8/30/2024
2. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and Contract Time.
3. Include a list of quantities of products required and unit costs, with the total amount of purchases to be made. Where requested, furnish survey data to substantiate quantities.
4. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
5. Comply with requirements in Section “Substitution Procedures" if the proposed change requires substitution of one product or system for a product or system specified.
1.4 CHANGE ORDER PROCEDURES
A. Upon the Owner's approval of a Proposal Request, the Engineer will issue a Change Order for signatures of the Owner and the Contractor on AlA Form G701.
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION 009400
Jackson County Courthouse Cooling Tower Replacement SUMMARY OF WORK
Section 011100
1 8/30/2024
SECTION 011100
SUMMARY OF WORK
PART 1 - GENERAL
1.1 THE WORK IS GENERALLY DESCRIBED AS THE COOLING TOWER REPLACEMENT AT THE
JACKSON COUNTY COURTHOUSE, JEFFERSON GEORGIA.
A. Construction shall take place in a single phase:
1. The scope of work shall be performed during a 4 calendar day period, beginning at an approximate time that the longest lead item (Cooling Tower) is available to the job site and which coincides with the Owner’s schedule.
B. Scope of work shall be as follows:
1. The intent of the project is to demolish and replace the existing nominal 500 ton, two cell, counterflow Cooling Tower (CT-1). The new Cooling Tower shall be of equal capacity as the existing. The new Cooling Tower is to be fabricated to be a direct replacement of the existing Cooling Tower with accessory upgrades.
2. Demolition work shall include the removal of the existing Cooling Tower and portions of the associated above-ground condenser piping.
3. The electrical scope shall include the modification of the power supply for connection to the replacement Cooling Tower, associated basin heaters and heat trace.
4. The BAS controls sequence of operations and points shall remain the same as currently programmed by Convergint. Convergint shall provide the same sequence of operations and points for all new and existing equipment.
C. The Contractor shall also provide as-built drawings to the Owner and Engineer at the end of each Phase of construction. As-built drawings shall be to scale and dimensioned.
1.2 GENERAL DESCRIPTION OF WORK
A. Contractor shall furnish all material, labor, tools, plant, supplies, equipment, transportation, superintendence, temporary construction of every nature, insurance, taxes, contributions and all services and facilities, unless specifically excepted, and install all materials, items and equipment required to complete the construction of the project, as set forth in the contract documents.
B. Contract: Construct the Work under the Owner's General Conditions and Agreement between Owner and Contractor where the basis of payment is a Lump Sum.
C. Contractor's Responsibilities:
1. Secure and pay for, as necessary, execution of the Work and as applicable, all building permits, fees, and licenses. The Owner will pay for land disturbance and utility impact fees (if applicable).
2. Pay all required sales, consumer and use taxes.
3. Give all notices required by the Contract Documents or by governing regulations.
2 8/30/2024
4. Comply with codes, ordinances, rules, regulations, orders and other legal requirements of public authorities, which pertain to proper performance of the Work, and promptly submit written notice to the Architect of any observed variance of the Contract Documents from legal requirements.
5. The Contractor will maintain in good condition an up-to-date set of as-built field drawings reflecting all changes made to the Contract Documents at the jobsite.
One set of new prints, reflecting all changes, will be made from these drawings and presented to the Owner prior to issuance of final payment to the Contractor.
D. Survey of Existing Conditions:
1. By executing the Form of Agreement, the Contractor has acknowledged that:
a. He has visited and inspected the Project site and building area, in which the work is to be performed,
b. He has satisfied himself as to the nature and location of the work, including any obstructions, amount of work, actual levels, the equipment and facilities needed preliminary to and during the prosecution of the Work.
2. Contractor shall locate drainage or sewer lines, water, gas and other utility and electrical service lines, piping and conduits in the way of this work.
3. Failure by Contractor to have acquainted himself with available information concerning Site conditions, including factors affecting costs and liabilities, shall not relieve Contractor of responsibility for performance of work in accordance with requirements of Contract Documents, and for amount of consideration named or other determined.
E. Ten percent (10%) retainer shall be withheld from the Contractor's Application for Payment until the following have been achieved or provided by the Contractor.
1. Final Change Orders agreed to and executed by all parties.
2. Original and notarized lien waivers.
3. Engineer’s certification that punchlist has been completed.
4. As-built drawings and O&E manuals.
1.3 CONTRACTOR USE OF THE PREMISES
A. General: The Contractor shall limit his use of the premises to the work indicated, so as to allow for Owner occupancy.
B. Use of the site: Confine operations at the site to the back of house, Mechanical Room, Electrical Room, or other areas of the building where work is shown to take place on the contract documents. Portions of the site beyond areas on which work is indicated are not to be disturbed.
C. Contractor shall be provided with an escort within the building and secured areas as needed.
No keys or access cards shall be provided to the contractor.
D. Keep driveways and entrances clear and available at all times. Do not use for parking or storage of materials.
E. Do not encumber the site with materials and equipment. Confine stockpiling of materials and location of storage sheds to areas approved by the owner.
F. Lock automotive type vehicles and other mechanized and motorized construction equipment, when parked and unattended. Do not leave vehicles or equipment unattended with motor running or ignition key in place.
3 8/30/2024
1.4 OWNER OCCUPANCY
A. The Owner will continuously occupy the buildings and areas immediately adjacent to the site and premises during the entire stage of project construction.
B. Cooperate with Owner to minimize conflict, and to facilitate Owner's operations.
C. Schedule the Work to accommodate owner occupancy and utility system shutdown restrictions.
D. The Contractor shall make accommodations as noted to minimize the down time of all mechanical and electrical systems in the building as noted in the construction documents.
END OF SECTION 011100
Jackson County Courthouse Cooling Tower Replacement WORK RESTRICTIONS Section 011400
1 8/30/2024
SECTION 011400
WORK RESTRICTIONS
PART 1 - GENERAL
1.1 WORK RESTRICTIONS
A. Contractor shall schedule and control all work persons employed on the Project. Contractor shall instruct all workers to prevent tracking dirt and debris into existing buildings. Profanity, inappropriate dress, or inappropriate conduct shall not be permitted on any Project. Owner reserves the right to have the Contractor remove from the Project anyone who, in the sole opinion of the Owner, exhibits such behavior.
PART 2 - NOT USED
PART 3 - NOT USED
END OF SECTION 011400
Jackson County Courthouse Cooling Tower Replacement SUBSTITUTION PROCEDURES Section 012500
1 8/30/2024
SECTION 012500
SUBSTITUTION PROCEDURES
PART 1 - GENERAL
1.1 RELATED SECTIONS
A. Section 013323 Shop Drawings and Submittals
1.2 REQUEST FOR SUBSTITUTION
A. If the Contractor desires to use materials or products of manufacturers different from those indicated in the Contract Documents, the contractor shall make written application as described herein. The burden of proving the equality of the proposed substitution rests on the Contractor. To be acceptable, the proposed substitution shall meet or exceed all expressed requirements of the Contract Documents and shall be submitted upon the Contractor's letterhead.
1. Submit to the Engineer at the earliest date possible in order to afford him ample time to process the request.
2. Submit copies of shop drawings, product data or samples as required in Section 013323. The Engineer will consider reports from reputable independent testing laboratories, verified experience records from previous users and other written information valid in the circumstances.
3. Completely and clearly indicate in what respects the materials or products differ from those indicated in the Contract Documents.
4. Include the manufacturers printed recommendations clearly describing the installation use and care, as applicable, of the proposed substitutions.
5. Include a complete schedule of changes in the Contract Documents, if any, which must be made to permit the use of the proposed substitutions.
PART 2 - PRODUCTS (NOT APPLICABLE)
END OF SECTION 012500
Jackson County Courthouse Cooling Tower Replacement APPLICATION FOR PAYMENT Section 010276
1 8/30/2024
SECTION 012976
APPLICATIONS FOR PAYMENT
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division I Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section specifies administrative and procedural requirements governing the Contractors Applications for Payment.
1. Coordinate the Schedule of Values and Applications for Payment with the Contractors Construction Schedule, Submittal Schedule, and List of Subcontracts.
B. Related Sections: The following Sections contain requirements that relate to this Section.
1. Schedules: The Contractors Construction Schedule and Submittal Schedule are specified in Division I Section "Shop Drawings and Submittals."
1.3 SCHEDULE OF VALUES
A. Coordination: Coordinate preparation of the Schedule of Values with preparation of the Contractors Construction Schedule.
1. Correlate line items in the Schedule of Values with other required administrative schedules and forms, including:
a. Contractor's Construction Schedule.
b. Application for Payment forms, including Continuation Sheets.
c. List of subcontractors.
d. Schedule of allowances.
e. Schedule of alternates.
f. List of products.
g. List of principal suppliers and fabricators.
h. Schedule of submittals.
2. Submit the Schedule of Values to the Engineer at the earliest possible date but no later than 7 days before the date scheduled for submittal of the initial Applications for Payment.
B. Format and Content: Use the Project Manual table of contents as a guide to establish the format for the Schedule of Values. Provide at least one line item for each Specification Section.
1. Identification: Include the following Project Identification on the Schedule-of Values:
2 8/30/2024
a. Project name and location.
b. Name of the Engineer.
c. Project number.
d. Contractor’s name and address.
e. Date of submittal.
2. Arrange the Schedule of Values in tabular form with separate columns to indicate the following for each item listed:
a. Related Specification Section or Division.
b. Description of Work.
c. Name of subcontractor.
d. Name of manufacturer or fabricator.
e. Name of supplier.
f. Change Orders (numbers) that affect value.
g. Dollar value: Percentage of Contract Sum to nearest one hundredth percent, adjusted to total 100 percent.
3. Provide a breakdown of the Contract Sum in sufficient detail to-facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with the Project Manual table of contents. Break principal subcontract amounts down into several line items.
4. Round amounts to nearest whole dollar; the total shall equal the Contract Sum.
Provide a separate line item in the Schedule of Values for each part of the Work where Applications for Payment may include materials or equipment, purchased or fabricated and stored, but not yet installed.
a. Differentiate between items stored on-site and items stored off-site.
Include requirements for insurance and bonded warehousing, if required.
5. Provide separate line items on the Schedule of Values for initial cost of the materials, for each subsequent stage of completion, and for total installed value of that part of the Work.
1.4 APPLICATIONS FOR PAYMENT
A. Each Application for Payment shall be consistent with previous applications and payments as Certified by the Engineer and paid for by the Owner.
1. The initial Application for Payment, the Application for Payment at time of Substantial Completion, and the final Application for Payment involve additional requirements.
B. Payment-Application Times: Each progress payment date is indicated in the Agreement.
The period of construction Work covered by each Application for Payment is the period indicated in the Agreement. The Application for Payment is due on the 1st of each month and will be paid by the 30th of each month.
C. Payment-Application Forms: Use AlA Document G702 and Continuation Sheets G703 as the form for Applications for Payment.
3 8/30/2024
D. Application Preparation: Complete every entry on the form. Include notarization and execution by a person authorized to sign legal documents on behalf of the Contractor. The Engineer will return incomplete applications without action.
1. Entries shall match data on the Schedule of Values and the Contractor's Construction Schedule. Use updated schedules if revisions were made.
2. Include amounts of Change Orders and Construction Change Directives issued prior to the last day of the construction period covered by the application.
E. Transmittal: Submit 4 signed and notarized original copies of each Application for Payment to the Engineer by a method ensuring receipt within 24 hours. One copy shall be complete, including waivers of lien and similar attachments, when required.
1. Transmit each copy with a transmittal form listing attachments and recording appropriate information related to the application, in a manner acceptable to the Engineer.
F. Waivers of Mechanics Lien: With each Application for Payment, submit waivers of mechanics lien from every entity who is lawfully entitled to file a mechanics lien arising out of the Contract and related to the Work covered by the payment.
1. Submit partial waivers on each item for the amount requested, prior to deduction for retainage, on each item.
2. When an application shows completion of an item, submit final or full waivers.
3. The Owner reserves the right to designate which entities involved in the Work must submit waivers.
4. Waiver Delays: Submit each Application for Payment with the Contractor's waiver of mechanics lien for the period of construction covered by the application.
a. Submit final Applications for Payment with or preceded by final waivers from every entity involved with performance of the Work covered by the application who is lawfully entitled to a lien.
5. Waiver Forms: Submit waivers of lien on forms, and executed in a manner, acceptable to the Owner.
G. Initial Application for Payment: Administrative actions and submittals, that must precede or coincide with submittal of the first Application for Payment, include the following:
1. List of subcontractors.
2. List of principal suppliers and fabricators.
3. Schedule of Values.
4. Contractor's Construction Schedule (preliminary if not final).
5. List of Contractor's staff assignments.
6. Copies of building permits.
H. Application for Payment at Substantial Completion: Following issuance of the Certificate of Substantial Completion, submit an Application for Payment.
1. This application shall reflect Certificates of Partial Substantial Completion issued previously for Owner occupancy of designated portions of the Work.
2. Administrative actions and submittals that shall precede or coincide with this application include:
a. Occupancy permits and similar approvals.
4 8/30/2024
b. Warranties (guarantees) and maintenance agreements.
c. Test and Balance records.
d. Maintenance instructions.
e. Meter readings.
f. Startup performance reports.
g. Changeover information related to Owner's occupancy, use, operation, and maintenance.
h. Final cleaning.
i. Application for reduction of retainage and consent of surety.
j. List of incomplete Work, recognized as exceptions to Engineer’s
Certificate of Substantial Completion.
I. Final Payment Application: Administrative actions and submittals that must precede or coincide with submittal of the final Application for Payment include the following:
1. Completion of Project closeout requirements.
2. Completion of items specified for completion after Substantial Completion.
3. Ensure that unsettled claims will be settled.
4. Transmittal of required Project construction records to the Owner.
5. Removal of temporary facilities and services.
PART 2 - PRODUCTS (NOT APPLICABLE)
END OF SECTION 012976
Jackson County Courthouse Cooling Tower Replacement PROJECT COORDINATION Section 013113
1 8/30/2024
SECTION 013113
PROJECT COORDINATION
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies the requirements for the coordination of work and trades during construction phase services.
1.2 RELATED SECTIONS
A. Section 007200 General Conditions
B. Section 007320 Special Conditions
C. Section 011400 Work Restrictions
D. Section 013513 Special Project Procedures
E. Section 017416 Cleaning
1.3 ADMINISTRATION AND SUPERVISION
A. Coordination: Coordinate various elements of the work and entities engaged to perform the work; and coordinate the work with existing facilities/conditions, and with work by separate contractors (if any) and the Owner.
1.4 SURVEY/RECORDING
A. General: Working from established lines and levels at or near the project site, establish and maintain dependable markers for lines and levels of the work. Calculate dimensions and measure for layout of the work; do not scale the drawings. Record deviations (if any) from drawing information on existing conditions and review with Engineer at time of discovery.
B. Installer Inspections: Require installer of each major unit of work to inspect substrate and conditions of installation, and to report (in writing) unsatisfactory conditions.
C. Correct unsatisfactory conditions before proceeding. Inspect each product immediately before installation. Do not install damaged or defective products, materials or equipment.
1.5 INSTALLATION, GENERAL
A. Comply with manufacturer's instructions and recommendations to extent that printed information is more stringent than requirements contained directly in the contract documents.
Jackson County Courthouse Cooling Tower Replacement PROJECT COORDINATION Section 013113
2 8/30/2024
B. Timing: Install work during time and under conditions which will assure best possible results, coordinated with required inspections and testing.
C. Anchor work securely in place, properly located by line and level, organized for best possible uniformity, visual effect, operational efficiency, durability, and similar benefit to Owner's use. Isolate non-compatible materials from contact, sufficiently to prevent deterioration.
D. Mount individual units of work at industry recognized heights, if not otherwise indicated;
refer uncertainties to Engineer before proceeding.
END OF SECTION 013113
Jackson County Courthouse Cooling Tower Replacement PROGRESS SCHEDULES Section 013216
1 8/30/2024
SECTION 013216
PROGRESS SCHEDULES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. General provisions of the Contract, including General and Supplementary Conditions and General Requirements, Division 1, apply to all work specified in this Section.
1.2 PROGRESS SCHEDULE
A. General: Prior to the start of construction, prepare and submit to the Owner for approval a progress schedule outlining the major sequences of construction from start to final completion of the project. The work shall be carried on at such locations and in such sequence as indicated in the progress schedule.
B. Line-item breakdown:
1. The breakdown of the schedule must correspond to the line items referenced in the Schedule of Values AIA Document G703.
2. The progress schedule will include all major trades and activities, the time required for each construction category and a final completion date for the entire project.
3. The progress schedule shall define the latest possible start date for the relieve finishing of individual shop spaces as shown on the drawings.
4. The absence of references in said schedule to specific location, details or construction sequence for any portion of the work shall not relieve the Contractor from his obligation to complete the work according to said schedule and the completion date.
1.3 SCHEDULE OF SUBCONTRACTORS
A. Provide the Engineer with a list of subcontractors 10 business days after the award of the contract.
END OF SECTION 013216
Jackson County Courthouse Cooling Tower Replacement SHOP DRAWINGS AND SUBMITTALS Section 013323
1 8/30/2024
SECTION 013323
SHOP DRAWINGS AND SUBMITTALS
PART 1 - GENERAL
1.1 GENERAL REQUIREMENTS
A. Submit shop drawings, product information and samples to the Engineer for review as required in each section of the Specifications. All submittals shall be made promptly, allowing a minimum of 10 business days for Engineer’s review. The Contractor shall schedule submittals in accordance with the Construction Schedule so as to prevent delay in the work.
1.2 SPECIFIC SUBMITTAL REQUIREMENTS
A. Submittals shall be provided in Portable Document Format (PDF) and in the following minimum quantities:
1. One (1) set of drawings submitted; One (1) copy returned.
2. Product Information: One (1) copy submitted; One (1) returned.
3. Samples: Two (2) submitted; one (1) returned.
1.3 SHOP DRAWINGS
A. Shop drawings shall be made to conform, with the design drawings. Contract Drawings shall take precedence over shop drawings unless otherwise authorized in writing. Review of the shop drawings by the Engineer does not constitute a change to the Contract.
B. In case the Contractor is in doubt regarding certain dimensions shown on the Contract Drawings, or if there is a discrepancy on the Contract Drawings, the Contractor shall clearly mark the dimensions in question to be especially checked or verified.
C. All drawings for review must be submitted in quantities listed above. A minimum of two sets will be returned to the Contractor marked with one of the following:
1. "No Exceptions Taken" – Indicates the shop drawings have been reviewed for conformance with the Contract Documents and that no exceptions have been taken. Proceed with the work.
2. "Approved as Noted" – Indicates the shop drawings have been reviewed for conformance with the Contract Documents and that minor exceptions have been taken. Contractor may proceed with the work provided he corrects the work as noted. Resubmittal will not be required.
3. "Revise and Resubmit" – Indicates the shop drawings have been reviewed for conformance with the Contract Documents and that work may not proceed. After items to which exceptions have been taken are corrected, the Contractor shall again submit copies for review.
Jackson County Courthouse Cooling Tower Replacement SHOP DRAWINGS AND SUBMITTALS Section 013323
2 8/30/2024
4. “Rejected” – Indicates the shop drawings have been reviewed for conformance with the Contract Documents and major exceptions have been taken. Work shall not proceed. After items to which exceptions have been taken are corrected, the Contractor shall again submit copies for review.
(In case exceptions are noted on one sheet, which affect details on other sheets, the exception is to be taken as applying to such other details.)
D. All drawings and details must be checked by the Contractor and show the initial of the Contractor's checker before they are submitted for review.
E. Review of shop drawings by the Engineer shall not constitute an authorization or approval of a change to the contract. Changes to the Contract Documents shall be made only by Change Order.
F. All shop drawing submittals must be complete for that category of work required before the Engineer will review the submittal. No partial submittals will be accepted.
1.4 PRODUCT DATA
A. Submittal requirements and approval process for product information shall be as listed above for shop drawings except as follows:
1. A minimum of one of the required copies must be an original of the manufacturer's printed literature.
2. When more than one product or type of item is shown, the specific item submitted shall be clearly marked in every instance where it occurs in the literature, and unrelated items shall be struck out so that consideration of only the item submitted is possible.
3. The name of the manufacturer and supplier of each item is required on each copy of each submittal.
1.5 SAMPLES
A. Submit actual samples of products or materials in a finished state in quantities as listed above. Minimum requirements for sample submittals shall be as follows:
1. Size of each sample shall be large enough to show repeated patterns, joints or ranges of color and texture.
2. Samples of coatings or other products dependent on substrate for texture or other prominent characteristics shall be submitted as applied over that substrate.
3. The name of the manufacturer and supplier of each item shall be permanently affixed to each sample.
END OF SECTION 013323
Jackson County Courthouse Cooling Tower Replacement TEMPORARY FACILITIES AND CONTROLS
Section 015000
1 4/1/2022
SECTION 015000
TEMPORARY FACILITIES AND CONTROLS
PART 1 - GENERAL
1.1 RELATED SECTIONS
A. Section 017416 Cleaning
1.2 RELATED DOCUMENTS
A. Drawings and General provisions of the Contract, including General and Supplementary Conditions and General Requirements, Division 1, apply to all work specified in this Section.
PART 2 - PRODUCTS – NOT APPLICABLE
PART 3 - EXECUTION
3.1 SAFETY
A. Comply with applicable provisions and standards of the Occupational Safety and Health Act of 1980 and any other applicable statute, standard, regulation or code.
3.2 SCAFFOLDING AND HOISTING
A. Provide all ladders and furnish and install all materials required for all scaffolding, staging, platforms, temporary floorings and railings, in compliance with all local and state laws governing same. The Contractor shall be held responsible for the maintenance, cleaning and removal of all scaffolding and equipment erected.
3.3 ELECTRICAL SERVICE
A. The existing electrical service shall be allowed for contractor(s) use, including extensions and connections necessary for construction work. If supplemental temporary electrical service is required by the contractor(s), the contractor(s) shall pay costs of installing and maintaining service for duration of project. Pay costs associated with use of permanent electrical system until Date of Final Completion, except as otherwise indicated below.
2 4/1/2022
3.4 TEMPORARY LIGHTING
A. Provide the following minimum light levels for construction purposes:
1. General construction and safety lighting: 5 footcandles.
2. Finishing work and testing: 25 footcandles.
3.5 TEMPORARY HEAT AND VENTILATION
A. Provide temporary heat in enclosed spaces to provide minimum temperatures of 40° Fahrenheit until finishing work begins; then maintain temperatures at levels indicated in specification sections.
B. Provide ventilation to prevent accumulation of dust, fumes, or gases, to properly cure materials and disperse humidity.
3.6 SANITARY TOILET FACILITIES
A. Provide and maintain temporary toilet facilities for construction personnel. Permanent facilities may not be used by personnel.
3.7 FIRE PROTECTION
A. Provide one 20 pound, ABC type fire extinguisher for each 5,000 SF of area during the entire construction period.
3.8 TRASH REMOVAL
A. Keep the premises clean at all times and remove all rubbish and debris in containers at the end of each working day in accordance with Section 017416.
3.9 TEMPORARY ENCLOSURES AND PROTECTION
A. The contractor may elect to furnish and maintain temporary stairs, ramps, barricades, enclosures, railings, shoring, bracing and staging in conformance with O.S.H.A.
requirements for the areas of construction. Contractor shall coordinate location and accessibility of all the above with the Owner during the Pre-Construction meeting.
3.10 COMPLETION OF WORK
A. At completion of work, or at time of permanent utility connections, as applicable, remove temporary facilities, including connections and debris resulting from temporary installation.
3 4/1/2022
3.11 CONSTRUCTION OFFICE
A. The Contractor may elect to staff and maintain a temporary construction office area with temporary tables, chairs, etc. on the site and in the Chiller Room throughout the entire duration of the Contract.
END OF SECTION 015000
Jackson County Courthouse Cooling Tower Replacement FIELD ENGINEERING Section 017123
1 8/30/2024
SECTION 017123
FIELD ENGINEERING
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and General provisions of the Contract, including General and Supplementary Conditions and General Requirements, Division 1, apply to all work specified in this Section.
PART 2 - PRODUCTS
2.1 MATERIALS
A. The Contractor shall provide all instruments, tools and appurtenances to accurately execute the work of this Section.
PART 3 - EXECUTION
3.1 FIELD ENGINEERING
A. Lay out work from the established base lines, elevations and benchmarks referenced on the Drawings.
B. Furnish templates, stakes and materials required.
C. Preserve all monuments, stakes and markers.
D. Coordinate and supervise layout of utility service lines and rough in requirements.
E. Verify all dimensions and conditions shown on the Drawings, Specifications and Addenda shall be verified before work is begun, and further verify at the site.
F. Where installed work interferes with other work, the Architect will designate what work is to be removed and replaced.
END OF SECTION 017123
Jackson County Courthouse Cooling Tower Replacement CUTTING AND PATCHING Section 017329
1 8/30/2024
SECTION 017329
CUTTING AND PATCHING
PART 1 - GENERAL
1.1 GENERAL
A. Definition: "Cutting and patching" includes cutting into existing construction to provide for the installation of or performance of other work and subsequent fitting and patching required to restore surfaces to their original condition or patching and repair of surfaces where equipment is removed or relocated.
B. Refer to other sections of these specifications for specific cutting and patching requirements and limitations applicable to individual units of work.
C. Structural work: Do not cut and patch structural work in a manner resulting in a reduction of the load carrying capacity or load/deflection ratio. Submit proposal and request and obtain Engineer's approval before proceeding with cut and patch of structural work.
D. Operational/Safety Limitations: Do not cut and patch operational elements and safety components in a manner resulting in decreased performance, shortened useful life, or increased maintenance. Submit proposals and requests and obtain Engineer's approvals before proceeding with cut and patches.
E. Visual/Quality Limitations: Do not cut and patch work exposed to view (interior or exterior) in a manner resulting in a noticeable reduction in the esthetic qualities and similar qualities, as judged by the Engineer.
F. Limitations on approvals: Engineer's approval to proceed with cutting and patching does not waive the right to later require removal/replacement of work found to be cut and patched in an unsatisfactory manner as judged by the Architect/Engineer.
1.2 MATERIALS
A. General: Use material for cutting and patching that is identical to existing materials. If identical materials are not available, use materials that match existing adjacent surfaces to the greatest extent possible with regard to visual effect. Use materials for cutting and patching that will result in equal-or-better performance characteristics.
1.3 EXECUTION
A. Inspection: Before cutting, examine surfaces to be cut and patched and conditions under which work is to be performed. If unsafe or otherwise unsatisfactory conditions are encountered, take corrective action before proceeding with the work.
B. Temporary Support: To prevent failure, provide temporary support of work to be cut.
C. Protection: Protect other work during cutting and patching to prevent damage. Provide protection from adverse weather conditions for that part of the project that may be exposed during cutting and patching operations.
Jackson County Courthouse Cooling Tower Replacement CUTTING AND PATCHING Section 017329
2 8/30/2024
D. Take precautions not to cut piping, conduits or ducts serving the building and scheduled to be relocated until provisions have been made to bypass them.
E. Cutting: Cut the work using methods that are least likely to damage work to be retained or adjoining work.
F. Where cutting is required use hand or small power tools designed for sawing and grinding, not hammering or chopping. Cut through concrete and masonry with equipment such as a carborundum saw or core drill. Cut holes and slots neatly to size required with minimum disturbance of adjacent work. To avoid marring existing finished surfaces, cut and drill from the exposed or finished side into concealed surfaces. Temporarily cover openings when work is not being performed.
G. Patching: Patch with seams which are durable and as invisible as possible. Comply with specified tolerances for the work.
H. Restore exposed finishes of patched area and where necessary extend finish restoration into adjoining work in a manner which will eliminate evidence of cutting or patching and refinishing.
I. Where existing panels, devices, structural supports or equipment is removed, the area exposed shall be patched to match existing and painted as specified.
END OF SECTION 017329
Jackson County Courthouse Cooling Tower Replacement CLEANING Section 017416
1 8/30/2024
SECTION 017416
CLEANING
PART 1 - GENERAL
1.1 RELATED SECTIONS
A. Section 015000 Temporary Facilities and Controls
B. Section 017719 Project Closeout
1.2 RELATED DOCUMENTS
A. Drawings and General provisions of the Contract, including General and Supplementary Conditions and General Requirements, Division 1, apply to all work specified in this Section.
1.3 GENERAL REQUIREMENTS
A. Contractor shall keep the Project site free from accumulation of waste materials and rubbish at all times during the construction period. At completion of the Work, he shall remove all waste materials and rubbish from and about the Project, as well as his tools, construction equipment, machinery and surplus materials, except those specifically required by the Contract Documents to be left for the Owner's use.
B. If Contractor fails to keep project clean or to clean up prior to Date of Substantial Completion, the Owner may do so as provided in Paragraph 3.4 of the General Conditions and the cost thereof will be charged to the Contractor.
1.4 SAFETY REQUIREMENTS
A. Store volatile waste in covered metal containers. Remove from project site daily.
1. Allow no volatile wastes to accumulate on volatile substances.
2. Provide adequate ventilation during use of volatile substances.
B. Comply with local anti-pollution laws. Do not burn waste materials and rubbish on project site.
C. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinner on project site.
D. Dispose of no waste or cleaning materials, which contain materials harmful to plant growth on project site. Clean up materials, which are accidentally spilled as quickly as possible.
E. Clean disturbed areas of project site of debris.
1. Broom clean paved surfaces. Remove oil and similar deleterious substances.
2. Remove debris from grassed and landscaped areas, if contaminated, in most expeditious manner.
Jackson County Courthouse Cooling Tower Replacement CLEANING Section 017416
2 8/30/2024
F. Contractor shall make all accommodations required to leave the job site impacted by the replacement of the cooling tower in a manner similar to pre-construction state.
END OF SECTION 017416
Jackson County Courthouse Cooling Tower Replacement PROTECTIVE MEASURES DURING CONSTRUCTION Section 017600
1 8/30/2024
SECTION 017600
PROTECTIVE MEASURES DURING CONSTRUCTION
PART 1 - GENERAL
1.1 WORK INCLUDED
A. Provide and maintain suitable barriers to prevent access of unauthorized personnel into designated work areas.
B. Provide fire protection and prevention measures in work areas.
C. Institute accident prevention procedures.
1. Assume full responsibility for complying with and enforcing of all rules and regulations of all Federal, State and Municipal authorities having jurisdiction including those of the U.S. Environmental Protection Agency (P.L. 98-616), Occupational Safety and Health Act, the Office of the State Fire Marshall, and the local fire Marshall. OSHA requires a "Confined Space Program" which requires a written entry procedure, monitor procedure, and extraction procedure.
2. The requirements outlined hereinafter are to be considered as minimal, and where the requirements of any of the above authorities having jurisdiction conflict with the requirements of this section, the maximum condition shall prevail.
3. Any items damaged due to failure to comply with these requirements shall be corrected or replaced, to the satisfaction of the Owner without cost to the Owner.
4. Assume full responsibility for enforcing compliance with any protective measures indicated in specific sections of the Work.
1.2 FIRE PROTECTION
A. Contractor shall take all precautions to eliminate possible fire or explosion hazards at the site, including, but not limited to, enforcing the following requirements:
1. Any fuels, sludges, etc. removed from the fuel storage tanks shall be stored, handled, and maintained in accordance with the most recent edition of the Uniform Fire Code and publications developed by the American Petroleum Institute and the National Fire Protection Association, and local, state, or federal regulations, whichever supersedes.
2. All combustible material shall be removed from the site storage areas on a daily basis; including oil rags, empty solvent or paint containers, etc.
3. All tarpaulin or other covers for stored materials, shall be flameproof.
4. Solvents, paints, thinners, coatings, or other highly flammable materials, shall be stored only in well-ventilated areas, and all mixing and preparation shall be restricted to such areas. All such materials shall be handled in accordance with safe practice and the requirements of the authorities having jurisdiction.
5. Containers containing flammable or combustible materials shall remain capped or closed at all times, unless in immediate use.
6. No open fires on the site. Smoking is prohibited on site, except in areas designated by the Owner.
7. Avoid storage of large quantities of flammable or combustible materials at the site.
8. Gasoline may not be stored in any quantity on the site during any stage of construction.
Jackson County Courthouse Cooling Tower Replacement PROTECTIVE MEASURES DURING CONSTRUCTION Section 017600
2 8/30/2024
B. Provide and maintain at least one fire extinguisher station on the site, in a designated location within the Contract Limits. Additional fire extinguishers shall be furnished in each enclosed area used as a storeroom. Each fire extinguisher station shall be located so as to be easily accessible while providing minimum interferences with operations, and shall contain one standard UL listed, 10 pound: ABC rated carbon-dioxide unit. Contractor shall check units frequently to maintain in operable condition.
C. Welding and flame cutting will be allowed only upon authority of the Owner. All such equipment when used shall be kept in a safe and functional condition and be of a type which will minimize hazards. Great care must be exercised in the use of the tools near adjacent properties.
1.3 ACCIDENT PREVENTION AND PROCEDURES
A. Site safety will be the Contractor's responsibility.
1. Safety responsibility will include the supply and use of approved and personal protection equipment, fire extinguishers, combustible gas/oxygen indicators, storage of hazardous materials, and other safety equipment required to complete the Work.
2. All safety equipment will be stored in a designated storage area, and will be maintained in proper working order.
B. Promptly report in writing to the Owner and the Engineer all accidents which cause death, personal injury, or property damages, arising out of or in connection with the performance of the work whether on or adjacent to the site. Where death or serious injuries or serious damages are caused, the accident shall be reported immediately by telephone or messenger to the Owner.
C. If any claim is made by anyone against the Contractor or any subcontractor on account of any accident, promptly report the facts in writing to the Owner giving full details of the claim.
END OF SECTION 017600
Jackson County Courthouse Cooling Tower Replacement PROJECT CLOSEOUT Section 017719
1 8/30/2024
SECTION 017719
PROJECT CLOSEOUT
PART 1 - GENERAL
1.1 RELATED SECTIONS
A. Section 006536 Contractor Warranty Form
B. Section 017416 Cleaning
1.2 RELATED DOCUMENTS
A. General provisions of the Contract, including General and Supplementary Conditions and General Requirements, Division 1, apply to all work specified in this Section.
PART 2 - PRODUCTS
2.1 AS REFERENCED HEREIN
PART 3 - EXECUTION
3.1 CLEAN UP
A. Clean entire project at the end of the job in accordance with Section 017416 to accomplish the following:
1. Remove stains from glass and metal, clean and polish same.
2. Clean and polish all hardware and fixtures.
3. Clean and polish all tile work and finishes.
4. Clean and touch-up all paint, trim and floors.
5. Clean exterior of all debris and refuse.
3.2 OPERATING INSTRUCTIONS/MAINTENANCE MANUALS
A. The Contractor shall provide to the Owner three (3) bound copies of Operating Instructions, line diagrams, color code, etc. for all equipment. These instructions shall include a complete description of all equipment, diagrams indicating the connections, oiling requirements, type of oil and grease to be used, and the method to be used in the operation of equipment. Maintenance instructions and warranties shall also be included.
B. Final acceptance of the project shall be contingent upon receipt by the Owner from the Contractor of the following information not later than 30 days after Date of Substantial Completion.
1. Cuts and brochures of all installed equipment including manufacturer's operation and maintenance manuals.
2 8/30/2024
2. List of all suppliers and subcontractors including addresses and telephone numbers and who is to be contacted in case of malfunction while equipment is under warranty or guarantee.
C. Operating, Maintenance Instructions: Arrange for each installer of product/services requiring continuing maintenance (by Owner) or operation to meet with Owner’s personnel at project site to provide basic instructions needed for proper operation and maintenance of entire work. Include instructions by manufacturer’s representatives where installer are not expert in required procedures.
D. Review maintenance manuals, record documents, tools, spare parts and…