Construction Schedule

190 KB Posted

Attached to
RFP – INSPECTIONS & MATERIAL TESTING - 020822
Solicitation number
Not on record
Issued by
Fulton County, Georgia

About this file

This file contains a construction schedule for the Rhodes Street project in Fulton County, Georgia, prepared for the City of College Park in conjunction with an inspections and material testing services solicitation. The project, with a Notice to Proceed issued on January 17, 2022, encompasses extensive infrastructure work including utility relocations, demolition, grading, comprehensive storm drain installation across multiple pipeline sizes and locations, roadway construction, bridge construction, and completion activities. The project is scheduled for completion on May 31, 2023, with a total original duration of 497.88 days. Major phases include preconstruction activities (January-March 2022), utility work (March-June 2022), project construction spanning from March 2022 through April 2023 with extensive storm drain work occurring from May through July 2022, bridge construction from June through November 2022, and final completion items from April through May 2023. The schedule identifies numerous storm drain segments ranging from 10 inches to 42 inches in diameter, with asphalt paving activities scheduled for November-December 2022 and sidewalk work planned for January-March 2023.

The construction schedule reflects a detailed sequencing of 97 discrete activities with minimal total float (ranging from 0.20 to 2.13 days), indicating a tightly managed project with limited schedule flexibility. Key activities include bridge footings and foundations (40 days), bridge deck and railing construction (64 days), and associated site work including grading, fill placement, base course preparation, and pavement installation. The schedule indicates that inspections and material testing services would be required throughout the project lifecycle to monitor compliance with construction specifications, particularly during the utility relocation phase, all storm drain installations, structural concrete work for the bridge and median, asphalt paving operations, and concrete sidewalk construction. The project's complexity, extended timeline, and numerous sequential and parallel activities demonstrate the critical need for comprehensive testing and inspection services to ensure quality assurance and regulatory compliance throughout construction.

Text of this file

Activity ID Activity Name Original Duration

Remaining Duration

Start Finish Total Float

2756 - Rhod2756 - Rhodes Street - Fulton Co. (Comp. 5/31 497.88d 497.88d 17-Jan-2022 29-May-2023 2.13d

ConstructConstruction Milestones 497.88d 497.88d 17-Jan-2022 29-May-2023 2.13d

A1000 Notice to Proceed 0.00d 0.00d 17-Jan-2022* 0.00d A1010 Project Completion May 31, 2023 0.00d 0.00d 29-May-2023* 2.13d

UtilitiesUtilities 75.00d 75.00d 10-Mar-2022 22-Jun-2022 0.20d

A1020 Water and Sewer Relocation 75.00d 75.00d 10-Mar-2022 22-Jun-2022 0.20d

PreconstrPreconstruction Activities 40.00d 40.00d 17-Jan-2022 03-Mar-2022 0.20d

A1030 CWM Survey Control 10.00d 10.00d 17-Jan-2022 27-Jan-2022 0.20d A1040 Clear Project 15.00d 15.00d 28-Jan-2022 14-Feb-2022 0.20d A1050 Grub Project 15.00d 15.00d 15-Feb-2022 03-Mar-2022 0.20d

Project CoProject Construction 412.88d 412.88d 04-Mar-2022 20-Apr-2023 1.00d

A1060 Demolition Existing Roadway 4.00d 4.00d 04-Mar-2022 09-Mar-2022 0.20d A1070 Rough Grade Onsite 40.00d 40.00d 21-Apr-2022 15-Jun-2022 0.20d A1080 Storm Drain 30" A0 to A1 0.25d 0.25d 19-May-2022 19-May-2022 0.20d A1110 Storm Drain 30" A1 to A3 0.25d 0.25d 19-May-2022 19-May-2022 0.20d A1120 Storm Drain 24" A3 to A2 0.75d 0.75d 19-May-2022 20-May-2022 0.20d A1130 Storm Drain 24" A3 to A11 0.75d 0.75d 20-May-2022 20-May-2022 0.20d A1140 Storm Drain 18" A11 to A10 0.25d 0.25d 23-May-2022 23-May-2022 0.20d A1150 Storm Drain 24" A3 to A3.2 0.75d 0.75d 23-May-2022 23-May-2022 0.20d A1160 Storm Drain 24" A3.2 to A3.1 0.75d 0.75d 24-May-2022 24-May-2022 0.20d A1170 Storm Drain 24" A3.1 to A4 0.75d 0.75d 24-May-2022 25-May-2022 0.20d A1180 Storm Drain 24" A4 to A5 0.75d 0.75d 25-May-2022 26-May-2022 0.20d A1190 Storm Drain 18" A5 to A8 0.25d 0.25d 26-May-2022 26-May-2022 0.20d A1200 Storm Drain 18" A8 to A8.2 0.25d 0.25d 26-May-2022 26-May-2022 0.20d A1210 Storm Drain 18" A8 to A8.1 0.25d 0.25d 26-May-2022 26-May-2022 0.20d A1220 Storm Drain 18" A5 to A5.1 0.25d 0.25d 27-May-2022 27-May-2022 0.20d A1230 Storm Drain 18" A5.1 to A6.1 0.25d 0.25d 27-May-2022 27-May-2022 0.20d A1240 Storm Drain 18" A6.1 to A6 0.25d 0.25d 27-May-2022 27-May-2022 0.20d A1250 Storm Drain 18" A6 to A7 0.25d 0.25d 27-May-2022 27-May-2022 0.20d A1260 Storm Drain 30" B0 to B0 0.25d 0.25d 30-May-2022 30-May-2022 0.20d A1270 Storm Drain 30" B0 to B2 0.25d 0.25d 30-May-2022 30-May-2022 0.20d A1280 Storm Drain 30" B2 to B3.1 0.50d 0.50d 30-May-2022 30-May-2022 0.20d A1290 Storm Drain 30" B3.1 to B3 0.25d 0.25d 31-May-2022 31-May-2022 0.20d A1300 Storm Drain 30" B3 to B4.1 0.25d 0.25d 31-May-2022 31-May-2022 0.20d A1310 Storm Drain 18" B4.1 to B23 0.25d 0.25d 31-May-2022 31-May-2022 0.20d A1320 Storm Drain 18" B23 to B28 0.25d 0.25d 31-May-2022 31-May-2022 0.20d A1330 Storm Drain 18" B28 to B28.1 0.25d 0.25d 01-Jun-2022 01-Jun-2022 0.20d A1340 Storm Drain 18" B28 to B27 0.25d 0.25d 01-Jun-2022 01-Jun-2022 0.20d A1350 Storm Drain 18" B27 to B26 0.25d 0.25d 01-Jun-2022 01-Jun-2022 0.20d A1360 Storm Drain 42" D1 to D2 2.50d 2.50d 01-Jun-2022 06-Jun-2022 0.20d A1370 Storm Drain 42" D2 to Existing 2.50d 2.50d 06-Jun-2022 08-Jun-2022 0.20d A1380 Storm Drain 18" B26 to B25 0.25d 0.25d 08-Jun-2022 08-Jun-2022 0.20d A1390 Storm Drain 10" PVC B25 to B25.1 0.10d 0.10d 09-Jun-2022 09-Jun-2022 0.20d A1400 Storm Drain 18" B25 to B25.2 0.25d 0.25d 09-Jun-2022 09-Jun-2022 0.20d

1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 J F M A M J J A S O N D J F M A M J

Co

Notice to Proceed Pro

Utilities

Water and Sewer Relocation Preconstruction Activities

CWM Survey Control Clear Project

Grub Project Project Construc

Demolition Existing Roadway Rough Grade Onsite

Storm Drain 30" A0 to A1 Storm Drain 30" A1 to A3 Storm Drain 24" A3 to A2 Storm Drain 24" A3 to A11 Storm Drain 18" A11 to A10 Storm Drain 24" A3 to A3.2 Storm Drain 24" A3.2 to A3.1 Storm Drain 24" A3.1 to A4 Storm Drain 24" A4 to A5 Storm Drain 18" A5 to A8 Storm Drain 18" A8 to A8.2 Storm Drain 18" A8 to A8.1 Storm Drain 18" A5 to A5.1 Storm Drain 18" A5.1 to A6.1 Storm Drain 18" A6.1 to A6 Storm Drain 18" A6 to A7 Storm Drain 30" B0 to B0 Storm Drain 30" B0 to B2 Storm Drain 30" B2 to B3.1 Storm Drain 30" B3.1 to B3 Storm Drain 30" B3 to B4.1 Storm Drain 18" B4.1 to B23 Storm Drain 18" B23 to B28 Storm Drain 18" B28 to B28.1 Storm Drain 18" B28 to B27 Storm Drain 18" B27 to B26

Storm Drain 42" D1 to D2 Storm Drain 42" D2 to Existing Storm Drain 18" B26 to B25 Storm Drain 10" PVC B25 to B25.1 Storm Drain 18" B25 to B25.2

2756 - Rhodes Street - Fulton Co. (Comp. 5/31/2023) Project Start Date 17-Jan-2022 Data Date - 17-Jan-2022 Byron Group by WBS

23-Nov-2021 09:23

Remaining Level of Effort Actual Level of Effort

Actual Work Remaining Work

Page 1 of 3 TASK filter: All Activities © Primavera Systems, Inc.

Hector Morales Text Box

EXHIBIT A

CONSTRUCTION SCHEDULE

Hector Morales Text Box

EXHIBIT A

CONSTRUCTION SCHEDULE

Remaining Duration

Start Finish Total Float

A1410 Storm Drain 18" B25.2 to B24.1 0.25d 0.25d 09-Jun-2022 09-Jun-2022 0.20d A1420 Storm Drain 18" B24.1 to B24 0.25d 0.25d 09-Jun-2022 09-Jun-2022 0.20d A1430 Storm Drain 30" B4.1 to B4 0.25d 0.25d 09-Jun-2022 10-Jun-2022 0.20d A1440 Storm Drain 30" B4 to B5.1 0.25d 0.25d 10-Jun-2022 10-Jun-2022 0.20d A1450 Storm Drain 24" B5.1 to B5 0.75d 0.75d 10-Jun-2022 13-Jun-2022 0.20d A1460 Storm Drain 24" B5 to 22 0.75d 0.75d 13-Jun-2022 13-Jun-2022 0.20d A1470 Storm Drain 18" B22 to B21 0.25d 0.25d 13-Jun-2022 14-Jun-2022 0.20d A1480 Storm Drain 18" B21 to B20 0.25d 0.25d 14-Jun-2022 14-Jun-2022 0.20d A1490 Storm Drain 24" B22 to B22.1 0.75d 0.75d 14-Jun-2022 15-Jun-2022 0.20d A1500 Storm Drain 24" B22.1 to B6.1 0.75d 0.75d 15-Jun-2022 15-Jun-2022 0.20d A1510 Storm Drain 24" B6.1 to B6 0.75d 0.75d 15-Jun-2022 16-Jun-2022 0.20d A1520 Storm Drain 24" B6 to B7 0.75d 0.75d 16-Jun-2022 17-Jun-2022 0.20d A1530 Storm Drain 24" B7 to B8.3 0.75d 0.75d 17-Jun-2022 20-Jun-2022 0.20d A1540 Storm Drain 24" B8.3 to B8.1 0.75d 0.75d 20-Jun-2022 20-Jun-2022 0.20d A1550 Storm Drain 18" B8.1 to B8.2 0.25d 0.25d 20-Jun-2022 21-Jun-2022 0.20d A1560 Storm Drain 24" B8.1 to B8 0.75d 0.75d 21-Jun-2022 21-Jun-2022 0.20d A1570 Storm Drain 24" B8 to B9 0.75d 0.75d 21-Jun-2022 22-Jun-2022 0.20d A1580 Storm Drain 18" B9 to B9.1 0.25d 0.25d 22-Jun-2022 22-Jun-2022 0.20d A1590 Storm Drain 18" B9.1 to B9.2 0.25d 0.25d 22-Jun-2022 23-Jun-2022 0.20d A1600 Storm Drain 18" B9.1 to B18.1 0.25d 0.25d 23-Jun-2022 23-Jun-2022 0.20d A1610 Storm Drain 18" B18.1 to B18 0.25d 0.25d 23-Jun-2022 23-Jun-2022 0.20d A1620 Storm Drain 18" B18 to B17 0.25d 0.25d 23-Jun-2022 23-Jun-2022 0.20d A1630 Storm Drain 18" B9 to B9.3 0.25d 0.25d 23-Jun-2022 24-Jun-2022 0.20d A1640 Storm Drain 18" B9.3 to B10 0.25d 0.25d 24-Jun-2022 24-Jun-2022 0.20d A1650 Storm Drain 18" B10 to B10.1 0.25d 0.25d 24-Jun-2022 24-Jun-2022 0.20d A1660 Storm Drain 18" B10 to B11 0.25d 0.25d 24-Jun-2022 24-Jun-2022 0.20d A1670 Storm Drain 18" B11 to B11.1 0.25d 0.25d 24-Jun-2022 27-Jun-2022 0.20d A1680 Storm Drain 18" B11.1 to B16.1 0.25d 0.25d 27-Jun-2022 27-Jun-2022 0.20d A1690 Storm Drain 18" B16.1 to B16 0.25d 0.25d 27-Jun-2022 27-Jun-2022 0.20d A1700 Storm Drain 18" B16 to B15 0.25d 0.25d 27-Jun-2022 27-Jun-2022 0.20d A1710 Storm Drain 18" B11 to B12 0.25d 0.25d 27-Jun-2022 28-Jun-2022 0.20d A1720 Storm Drain 18" B12 to B12.1 0.25d 0.25d 28-Jun-2022 28-Jun-2022 0.20d A1730 Storm Drain 18" B12 to B13.1 0.25d 0.25d 28-Jun-2022 28-Jun-2022 0.20d A1740 Storm Drain 18' B13.1 to B13 0.25d 0.25d 28-Jun-2022 28-Jun-2022 0.20d A1750 Storm Drain 18" B13 to B14 0.25d 0.25d 28-Jun-2022 29-Jun-2022 0.20d A1760 Storm Drain 10" PVC B14 to B14.1 0.10d 0.10d 29-Jun-2022 29-Jun-2022 0.20d A1770 Storm Drain 10" PVC C1.1 to C1 0.10d 0.10d 29-Jun-2022 29-Jun-2022 0.20d A1780 Storm Drain 18" C1 to C2 0.25d 0.25d 29-Jun-2022 29-Jun-2022 0.20d A1790 Storm Drain 18" C2 to C2.1 0.25d 0.25d 29-Jun-2022 29-Jun-2022 0.20d A1800 Storm Drain 18" C2.1 to C2.2 0.25d 0.25d 29-Jun-2022 30-Jun-2022 0.20d A1810 Storm Drain 18" C2.1 to C5 0.25d 0.25d 30-Jun-2022 30-Jun-2022 0.20d A1820 Storm Drain 10" PVC C5 to C5.1 0.25d 0.25d 30-Jun-2022 30-Jun-2022 0.20d A1830 Storm Drain 18" C5 to C4 0.25d 0.25d 30-Jun-2022 30-Jun-2022 0.20d A1840 Storm Drain 10" PVC C4 to C4.1 0.25d 0.25d 30-Jun-2022 01-Jul-2022 0.20d A1850 Storm Drain 18" C4 to C6.1 0.25d 0.25d 01-Jul-2022 01-Jul-2022 0.20d A1860 Storm Drain 18" C6.1 to C6 0.25d 0.25d 01-Jul-2022 01-Jul-2022 0.20d

1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 J F M A M J J A S O N D J F M A M J

Storm Drain 18" B25.2 to B24.1 Storm Drain 18" B24.1 to B24 Storm Drain 30" B4.1 to B4 Storm Drain 30" B4 to B5.1 Storm Drain 24" B5.1 to B5 Storm Drain 24" B5 to 22 Storm Drain 18" B22 to B21 Storm Drain 18" B21 to B20 Storm Drain 24" B22 to B22.1 Storm Drain 24" B22.1 to B6.1 Storm Drain 24" B6.1 to B6 Storm Drain 24" B6 to B7 Storm Drain 24" B7 to B8.3 Storm Drain 24" B8.3 to B8.1 Storm Drain 18" B8.1 to B8.2 Storm Drain 24" B8.1 to B8 Storm Drain 24" B8 to B9 Storm Drain 18" B9 to B9.1 Storm Drain 18" B9.1 to B9.2 Storm Drain 18" B9.1 to B18.1 Storm Drain 18" B18.1 to B18 Storm Drain 18" B18 to B17 Storm Drain 18" B9 to B9.3 Storm Drain 18" B9.3 to B10 Storm Drain 18" B10 to B10.1 Storm Drain 18" B10 to B11 Storm Drain 18" B11 to B11.1 Storm Drain 18" B11.1 to B16.1 Storm Drain 18" B16.1 to B16 Storm Drain 18" B16 to B15 Storm Drain 18" B11 to B12 Storm Drain 18" B12 to B12.1 Storm Drain 18" B12 to B13.1 Storm Drain 18' B13.1 to B13 Storm Drain 18" B13 to B14 Storm Drain 10" PVC B14 to B14.1 Storm Drain 10" PVC C1.1 to C1 Storm Drain 18" C1 to C2 Storm Drain 18" C2 to C2.1 Storm Drain 18" C2.1 to C2.2 Storm Drain 18" C2.1 to C5 Storm Drain 10" PVC C5 to C5.1 Storm Drain 18" C5 to C4 Storm Drain 10" PVC C4 to C4.1 Storm Drain 18" C4 to C6.1 Storm Drain 18" C6.1 to C6

2756 - Rhodes Street - Fulton Co. (Comp. 5/31/2023) Project Start Date 17-Jan-2022 Data Date - 17-Jan-2022 Byron Group by WBS

23-Nov-2021 09:23

Remaining Level of Effort Actual Level of Effort

Actual Work Remaining Work

Page 2 of 3 TASK filter: All Activities © Primavera Systems, Inc.

Remaining Duration

Start Finish Total Float

A1870 Storm Drain 18" C2 to C2.3 0.25d 0.25d 01-Jul-2022 01-Jul-2022 0.20d A1880 Storm Drain 18" C2.3 to C3 0.25d 0.25d 01-Jul-2022 04-Jul-2022 0.20d A1890 Storm Drain 18" C3 to C3.1 0.25d 0.25d 04-Jul-2022 04-Jul-2022 0.20d A1900 Borrow to Fill 10.00d 10.00d 04-Jul-2022 18-Jul-2022 0.20d A1910 Finegrade Subgrade 15.00d 15.00d 18-Jul-2022 08-Aug-2022 0.20d A1920 Place GAB 18.00d 18.00d 08-Aug-2022 01-Sep-2022 0.20d A1930 Build Curb Pad 15.00d 15.00d 01-Sep-2022 22-Sep-2022 0.20d A1940 Pour Curb & Gutter/Header Curb 22.00d 22.00d 22-Sep-2022 24-Oct-2022 0.20d A1950 Pour Header Curb @ Roundabout 4.00d 4.00d 24-Oct-2022 28-Oct-2022 0.20d A1960 Fine Grade GAB @ Roundabout for Truck Apron 0.50d 0.50d 28-Oct-2022 28-Oct-2022 0.20d A1970 Pour Truck Apron 5.00d 5.00d 28-Oct-2022 04-Nov-2022 0.20d A1980 Backfill Curb and Gutter 3.00d 3.00d 04-Nov-2022 09-Nov-2022 0.20d A1990 Fine Grade GAB 12.00d 12.00d 09-Nov-2022 25-Nov-2022 0.20d A2000 Asphalt Pave 25MM 10.00d 10.00d 25-Nov-2022 07-Dec-2022 0.33d A2010 Asphalt Pave 19MM 9.00d 9.00d 07-Dec-2022 17-Dec-2022 0.33d A2020 Grade Sidewalk Pad 30.00d 30.00d 19-Dec-2022 27-Jan-2023 0.00d A2030 Pour Sidewalk 27.00d 27.00d 30-Jan-2023 07-Mar-2023 0.00d A2040 Final Dress and Grass 10.00d 10.00d 08-Mar-2023 21-Mar-2023 0.00d A2050 Install Guardrail 3.00d 3.00d 22-Mar-2023 24-Mar-2023 0.00d A2060 Asphalt Mill & Inlay 1.00d 1.00d 24-Mar-2023 25-Mar-2023 1.13d A2070 Asphalt Top 12.5MM 3.00d 3.00d 25-Mar-2023 29-Mar-2023 1.13d A2080 Pour 5.5" Concrete Median 8.00d 8.00d 30-Mar-2023 10-Apr-2023 1.00d A2090 Pour 7.5" Concrete Median 8.00d 8.00d 11-Apr-2023 20-Apr-2023 1.00d

Bridge CoBridge Construction 104.00d 104.00d 16-Jun-2022 08-Nov-2022 99.00d

A1090 Construct Bridge Footings and Foundations 40.00d 40.00d 16-Jun-2022 10-Aug-2022 99.00d A1100 Construct Bridge Deck & Railing 64.00d 64.00d 11-Aug-2022 08-Nov-2022 99.00d

Project CoProject Completion Items 39.00d 39.00d 20-Apr-2023 29-May-2023 2.13d

A2100 Permanent Asphalt Markings 10.00d 10.00d 20-Apr-2023 02-May-2023 2.13d A2110 Install Permanent Signs 5.00d 5.00d 02-May-2023 08-May-2023 2.13d A2120 Punchlist 21.00d 21.00d 08-May-2023 29-May-2023 2.13d

1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 J F M A M J J A S O N D J F M A M J

Storm Drain 18" C2 to C2.3 Storm Drain 18" C2.3 to C3 Storm Drain 18" C3 to C3.1

Borrow to Fill Finegrade Subgrade

Place GAB Build Curb Pad

Pour Curb & Gutter/Header Curb Pour Header Curb @ Roundabout Fine Grade GAB @ Roundabout for Truck Apron

Pour Truck Apron Backfill Curb and Gutter

Fine Grade GAB Asphalt Pave 25MM

Asphalt Pave 19MM Grade Sidewalk Pad

Pour Sidewalk Final Dress and Grass Install Guardrail Asphalt Mill & Inlay Asphalt Top 12.5MM

Pour 5.5" Concrete Pour 7.5" Concre

Bridge Construction

Construct Bridge Footings and Foundations Construct Bridge Deck & Railing

Pro

Permanent A Install Per

Pu

2756 - Rhodes Street - Fulton Co. (Comp. 5/31/2023) Project Start Date 17-Jan-2022 Data Date - 17-Jan-2022 Byron Group by WBS

23-Nov-2021 09:23

Remaining Level of Effort Actual Level of Effort

Actual Work Remaining Work

Page 3 of 3 TASK filter: All Activities © Primavera Systems, Inc.

Hector Morales Text Box

EXHIBIT A

CONSTRUCTION SCHEDULE

Other files

File Type Posted
Inspections & Material Testing —
Drawings —
Addendum No. 1 —
Addendum No. 2 —
Award Information —
Exhibit B - Fee Proposal —
Bid Open Details —

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .