This is a Performance Work Statement (PWS) for industrial grade CO2 gas services and tank rental at Fort Jackson, South Carolina. The contractor must provide CO2 gas delivery and maintenance services for six tanks across three pool locations (Palmetto Falls Water Park, Knight Pool, and Legion Pool), including five 750-pound tanks and one 450-pound tank.

The contract requires maintaining CO2 gas levels through a Keep Full Program where tanks cannot drop below 20-30% capacity, implementing smart tank monitoring systems at each location, and providing monitoring access to FMWR staff. The period of performance is March 3, 2025 to March 2, 2026 for the base year, with four one-year options through March 2, 2030. The contractor must provide all personnel, equipment, supplies, transportation, tools, materials, and supervision necessary for service delivery. Historical usage data from 2020-2024 shows annual consumption ranging from approximately 75,000-80,000 pounds at Palmetto Falls, 3,000-6,000 pounds at Legion Pool, and 2,500-4,000 pounds at Knight Pool.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AUG 22

PERFORMANCE WORK STATEMENT (PWS)

CO2 Gas for AQUATIC POOLS

FORT JACKSON, SOUTH CAROLINA

Part 1 General Information

1. General: This is a non-personal service(s) contract under which the personnel rendering the service(s) are not subject, either by the contract’s terms or by the manner of its administration, to the supervision and control usually prevailing in relationships between the Government and its employees.

1.1 Description of Services/Introduction: This is a non-personal service(s) contract to provide Industrial grade CO2 gas for treating pools and the rental of five 750 lbs tanks and one 450 lbs tank.

1.2 Background: CO2 gas is needed for treating ph in pool waters. There three locations Palmetto Falls Water Park (Bldg. 6511), Knight Pool (Bldg. 3296), and Legion Pool (Bldg.

2763).

1.3 Scope: The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, other items and non-personal services necessary to perform operations for providing industrial grade CO2 gas for treating pool water on a Keep Full Program. The Contractor will provide a smart tank monitoring system at each location to monitor the CO2 levels. The contractor will monitor each location and provide FMWR a monitor as well. The contractor will ensure they do not let the tanks drop below 20-30 % full at each location. The Contractor will then arrange to come out and fill the tanks that are needed.

1.4 Objectives: The objective of this contract is to provide CO2 gas to stabilize pH levels and disinfects the water.

1.5 General Information:

1.5.1 Period of Performance: The period of performance shall be for one (1) Base Year of 12 months and four (4) 12-month option years. The Period of Performance reads as follows:

Base Year- 3 March 2025 to 2 March 2026 Option Year 1- 3 March 2026 to 2 March 2027 Option Year 2- 3 March 2027 to 2 March 2028

Option Year 3- 3 March 2028 to 2 March 2029 Option Year 4- 3 March 2029 to 2 March 2030

1.5.2 Quality Assurance: The Government will evaluate the Contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the acceptable quality levels (performance thresholds).

1.5.3 Recognized Holidays: The following provides information on recognized holidays for the purpose of the PWS. If submittal of any documentation (e.g. deliverables, submittals, etc.)

deadlines fall on a holiday, the closest workday prior to the holiday will apply as the deadline for submittal.

1.5.3.1 U.S. Holidays: Work shall not be performed on U.S. federally recognized holidays occurring during the normal workweek unless otherwise directed by the Contracting Officer.

When a U.S. holiday occurs on a Saturday or a Sunday, the holiday is observed on the preceding Friday or following Monday, respectively.

New Year’s Day January 1st M. L. King Memorial Day 3rd Monday in Jan Presidents Day 3rd Monday in February Memorial Day last Monday in May Juneteenth June 19th Independence Day July 4th

Labor Day 1st Monday in September Columbus Day 2nd Monday in October Veteran’s Day November 11th Thanksgiving Day 4th Thursday in November Christmas Day December 25th

1.5.4 Operating Hours: The Government facility office hours, facility operating hours, and the Contractor support hour requirements often coincide, however, they may differ. Please refer to the following.

1.5.4.1 Government Facility Office Hours: The Government facility office hours are 0700 t0 1630, Monday through Friday except U.S. Holidays identified in paragraph 1.5.3.1 above or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings.

1.5.4.2 Government Facility Operating Hours: The Government facility office hours are 0700 t0 1630, Monday through Sunday. The Government facility is open for operations during the recognized U.S. Holidays identified in paragraph 1.6.3.1 above. The Government facility may close due to local or national emergencies, administrative closings, or similar Government directed facility closings and will be communicated by the Contracting Officer to the Contractor.

1.5.4.3 Contractor Support Hours: The Contractor shall provide support between the hours of 0700 t0 1630, Monday through Sunday. The Government facility may close due to local or national emergencies, administrative closings, or similar Government directed facility closings.

The Contractor shall maintain an adequate workforce at all times, for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce is essential.

1.5.5 Place of Performance: The work to be performed under this contract will be performed Palmetto Falls Water Park (Bldg. 6511), Knight Pool (Bldg. 3296), and Legion Pool (Bldg.

2763).

1.6 Security Requirements: The following information is provided on security related matters.

1.6.1 Installation Access: Access to U.S. installations, buildings and controlled areas is limited to personnel who meet security criteria and are authorized. Failure to submit required information/data and obtain required documentation or clearances will be grounds for denying access to U.S. installations, buildings and controlled areas. The Contractor shall ensure that any subcontractors used in performance of this contract complies with these requirements and that all employees, of both the Contractor and any subcontractor utilized by the Contractor, are made aware of and comply with these requirements.

The Contractor shall be aware of and comply with the requirements associated with Installation Access Control. The Government is not liable for any costs associated with performance delays due solely to a firm’s failure to comply with Installation Access Control System (IACS) processing requirements.

The Contractor shall return installation passes to the issuing IACS office when the contract is completed or when a Contractor employee no longer requires access.

1.6.2 Background Checks: Contractor and all associated sub-contractors’ employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

1.6.3 Physical Security: The Contractor shall safeguard all Government equipment, information, and property provided for Contractor use.

1.6.4 Operations Security (OPSEC) Requirements: Contractor personnel shall adhere to facility security policies and restrictions. The Contractor shall immediately report suspicious activities to security personnel.

1.7 Post Award Conference/Periodic Progress Meetings: The Contractor shall attend any post award conference convened by the contracting activity or contract administration office in accordance with FAR Subpart 42.5. The Contracting Officer, COR, and other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance. At these meetings the Contracting Officer will apprise the Contractor of how the Government views the Contractor's performance and the Contractor shall apprise the

Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the Government.

1.7.1 The Contractor shall attend, participate in, and furnish input to scheduled and unscheduled meetings, conferences, and briefings that relate to the functions and services herein as required by the Government to provide effective communication and impart necessary information. The Contract Manager or designated representative shall attend meetings as requested by the Government. Meeting attendees shall at times include Contractor managerial, supervisory, and other personnel knowledgeable of the subject matter.

Meetings may start or end outside of regular duty hours.

1.8 Contracting Officer’s Representative (COR): Refer to Part 2 of this PWS for the definition of a COR. As determined by the Contracting Officer, a COR will be appointed and identified by letter of designation, a copy of which will be provided to the Contractor by the Contracting Officer. The designation letter states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates, or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order. The COR monitors all technical aspects of the contract and assists in contract administration. The COR is not authorized to obligate the Government. If the work is not written in the contract, the COR is not authorized to request new work. The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract, perform inspections necessary in connection with contract performance, maintain written and oral communications with the Contractor concerning technical aspects of the contract, issue written interpretations of technical requirements, including Government drawings, designs, specifications, monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies, coordinate availability of Government property, and coordinate site entry of Contractor personnel.

1.9 Key Personnel: The following personnel are considered key personnel by the Government: Program/Contract Manager. The Contractor shall provide a Program/Contract Manager who shall be responsible for the performance of the work. The name of this person and an Alternate Program/Contract Manager, who shall act for the Contractor when the Program/Contract Manager is absent, shall be provided in writing to the Contracting Officer no later than five (5) days or 5 days after a replacement is hired. (A.001)

Quality Control Manager: The Quality Control Manager must demonstrate a minimum of 5 years’ experience, within the past 10, working as a Quality Control Manager.

1.10 Identification of Contractor Employees: All Contractor personnel attending meetings, answering Government telephones, and working in other situations where their Contractor status is not obvious to third parties must identify themselves, to include proper marking of signature blocks in correspondence, to avoid creating an impression in the minds of members of the public that they are Government officials. The Contractor shall ensure that all documents or reports, produced by Contractors are suitably marked as Contractor products or that Contractor participation is appropriately disclosed.

1.11 Protection of Government and Contract Information: Per Public Use Notice of Limitations stated by Defense imagery Management operations Center and contained at www.dimoc.mil/resources/limitations/ , the Contractor shall not cite any information (e.g., contract information, pictures, locations, etc.) obtained through this contract on any hard copy or digital marketing tools to include its company website.

1.12 Phase In /Phase Out Period: To minimize decreases in productivity and to prevent possible negative impacts on additional services, the Contractor shall have personnel on board, during the 15 days phase in/ phase out periods. During the phase in period, the Contractor shall become familiar with performance requirements in order to commence full performance of services on the contract start date.

1.13 Safety: The following provides information pertaining to Safety and Accident Prevention:

1.13.1 Safety Laws and Regulations: The Contractor shall comply with FAR 52.236-13, Accident Prevention (November 1991), the references contained therein (e.g. U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1).

The requirements under FAR 52.236-13 and specifically of the EM 385-1-1 include, but are not limited to the following:

(a) Safety Plan: The Contractor shall develop and implement a safety plan for its employees. The Contractor shall submit the safety plan to the KO/COR for review and acceptance within 30 business days after contract award. Revisions shall be submitted to the KO/COR five (5) business days prior to the effective date of change. The plan shall include an analysis of the significant hazards to life, limb, and property inherent in contract work performance and a plan for controlling these hazards. Plan shall comply with pertinent provisions of U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385- 1-1 requirements and FAR 52-236-13. The SSP shall be forwarded to the Contracting Office for review/approval by the Safety Office. The Contractor shall provide and maintain work environments and procedures which will comply with the standards issued by the Secretary of Labor at 29 CFR Part 1926 and 29 CFR Part 1910. The Contractor shall also comply with all applicable portions of the latest version of U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, in effect on the date of the solicitation. Safeguard the public and Government personnel, property, materials, supplies, and equipment exposed to Contractor operations and activities. The Contractor shall submit the Safety Plan with a Job Hazard Analysis (JHA) to the KO/COR for review and acceptance within thirty (30) days of commencement of work. Revisions shall be submitted five (5) calendar days prior to the effective date of change. (A.002)

1.14 Environmental Compliance: The following provides information on Environmental Compliance.

1.14.1 Environmental Compliance Objectives:

The contractor shall implement the following environmental objectives in accordance http://www.dimoc.mil/resources/limitations/ with FAR 23.4; FAR 23.7; FAR 52.223-1 through 52.223-5; and based on EPA-issued guidance):

• Maximize the utilization of environmentally preferable products.

• Maximize the utilization of bio-based products. See USDA-designated items at http://www.biopreferred.gov or 7 CFR part 3201.

• Maximize the reutilization of nonhazardous and recovered materials.

• Promote recycling and other cost-effective waste reduction.

• Eliminate or reduce the generation of hazardous waste and the need for special material processing (including special handling, storage, treatment, and disposal).

• Promote energy-efficiency and water conservation.

1.15 Required Training: The following provides information on training requirements.

1.15.1 Anti-Terrorism (AT) Level I Training: All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, and controlled-access areas shall complete AT Level I awareness training within calendar days after the contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within (5) calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website: http://jko.jten.mil

If training cannot be conducted on the website, the Contractor shall coordinate with the COR who will contact the local AT Officer at their assigned location for classroom training.

Contractor personnel completing training in the classroom will receive a certificate or the training attendance roster signed by the AT Officer. Verification of the training shall be provided to the COR within five (5) calendar days after completion of the training (A.003).

1.15.2 OPSEC Training: Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC Awareness training. Joint Knowledge Online (jten.mil). This training shall be completed within fifteen (15) calendar days of contract award and within fifteen (15) calendar days of new employees commencing performance with the results reported to the COR NLT five (5) calendar days after contract award. (A.004).

1.15.3 iWATCH Training: The Contractor and all associated Sub-Contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within fifteen (15) calendar days of contract award and within fifteen (15) calendar days of new employees commencing performance with the results reported to the COR NLT five (5) calendar days after contract award.

(A.005). Training slides can be found on the Army OneSource we site:

http://www.myarmyonesource.com/familyprogramsandservices/iwatchprogram/default.aspx http://www.biopreferred.gov/ http://jko.jten.mil/ https://jkodirect.jten.mil/Atlas2/page/coi/externalCourseAccess.jsf?v=1729102054291&course_prefix=JS&course_number=-US009-14 http://www.myarmyonesource.com/familyprogramsandservices/iwatchprogram/default.aspx

PART 2

DEFINITIONS & ACRONYMS

2. Definitions and Acronyms

2.1 Definitions: Although not inclusive of every term used within this PWS, the following provides a list of definitions used throughout this PWS and commonly used in the acquisition field.

Contracting Officer – means a person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings on behalf of the Government. Note: The only individual who can legally bind the Government.

Contracting Officer's Representative (COR) – As defined in DFARS 202.101, means an individual designated and authorized in writing by the Contracting Officer to perform specific technical or administrative functions. DoD Instruction (DoDI) 5000.72, Part II Definitions states the following when defining a COR: “Defined in subpart 202.101 of Reference (f). Any individual delegated responsibilities pursuant to subpart 1.602-2 of Reference (e), regardless of local terminology, must be certified in accordance with this instruction. For example, local terminology can be COR, Contracting Officer’s technical representative, technical point of contact, technical representative, alternate COR, administrative COR, assistant COR, line item manager, task order manager, quality assurance personnel, quality assurance evaluator, or COR management.” In addition, Army Regulation 70-13, Chapter 2, paragraph 2-2g, states, in part, the following when providing other surveillance support personnel to assist the COR when needed, “…These other surveillance support personnel may serve as on-site representatives of the COR in performance of actual contract surveillance if they meet all COR requirements and have been appointed by the Contracting Officer as alternate CORs.”

Contractor – means a supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.

Contractor-acquired Property - means property acquired, fabricated, or otherwise provided by the Contractor for performing a contract and to which the Government has title.

Day – means, unless otherwise specified, a calendar day.

Defective Service – means a service output that does not meet the standard of performance associated with the Performance Work Statement.

Deliverable – means anything that can be physically delivered but may include non-manufactured things such as meeting minutes or reports.

Government-furnished Property – As reflected in FAR 52.245-1, Government-furnished Property “means property in the possession of, or directly acquired by, the Government and subsequently furnished to the Contractor for performance of a contract. Government-furnished property includes, but is not limited to, spares and property furnished for repair, maintenance, overhaul, or modification. Government-furnished property also includes contractor-acquired property if the contractor-acquired property is a deliverable under a cost contract when accepted by the Government for continued use under the contract

Government Property - means all property owned or leased by the Government. Government property includes both Government-furnished and Contractor-acquired property. Government property includes material, equipment, special tooling, special test equipment, and real property. Government property does not include intellectual property and software.

Property Administrator - means an authorized representative of the Contracting Officer appointed in accordance with agency procedures, responsible for administering the contract requirements and obligations relating to Government property in the possession of a Contractor.

High Level Objective (HLO) – means a key overarching result-based objective for a project necessary to achieve the project’s vision. HLOs are similar to Level 2 in a Work Breakdown Structure. Each HLO may contain several statements to flesh out the areas necessary to meet the objective.

Physical Security – means that part of security concerned with physical measures designed to safeguard personnel; to prevent unauthorized access to equipment, installations, material, and documents; and to safeguard against espionage, sabotage, damage, and theft.

Quality Assurance – (or Government contract quality assurance) means the various functions, including, inspection, performed by the Government to determine whether a Contractor has fulfilled the contract obligations pertaining to quality and quantity.

Quality Assurance Surveillance Plan (QASP) – means the key Government-developed surveillance process document and is applied to Performance-Based Service Contracting (PBSC). The QASP is used for managing Contractor performance assessment by ensuring that systematic quality assurance methods validate that Contractor quality control efforts are timely, effective, and are delivering the results specified in the contract or task order. The QASP directly corresponds to the performance objectives and standards (i.e., quality, quantity, timeliness) specified in the Performance Work Statement (PWS). It provides specific details on how the Government will survey, observe, test, sample, evaluate, and document Contractor performance results to determine if the Contractor has met the required standards for each objective in the PWS. The QASP, with very few if any exceptions, is an internal to Government document.

Quality Control – means all necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

Statement – means the specific results-based activities required to satisfy HLOs. A statement contains a result, the context of the statement, and the required action(s). Statements focus on “what” is to be accomplished; however, they are not prescriptive in describing “how” the outcome is to be achieved. Each HLO may have several statements to flesh out the areas necessary to meet the objective. Statements are similar to Level 3 in a Work Breakdown Structure.

Subcontractor – means one that enters into a contract with a prime Contractor. The Government does not have privity of contract with the subcontractor.

Work Day - The number of hours per day the Contractor provides services in accordance with the contract.

Work Week - Monday through Friday, unless otherwise specified.

2.2 Acronyms: Although not inclusive of every term used within this PWS, or that may be included in an acquisition, the following provides a list of acronyms commonly used in the acquisition field.

ACOR Alternate Contracting Officer's Representative AE Army in Europe AFARS Army Federal Acquisition Regulation Supplement AHA Activity Hazard Analysis AOR Area of Responsibility AR Army Regulation AT Anti-terrorism ATCTS Army Training Certification Tracking System CAC Common Access Card CCE Contracting Center of Excellence CFE Conventional Forces Europe CFR Code of Federal Regulations CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer’s Representative COTS Commercial-Off-the-Shelf DA Department of the Army DD250 Department of Defense Form 250 (Receiving Report) DD254 Department of Defense Contract Security Requirement List DFARS Defense Federal Acquisition Regulation Supplement DMDC Defense Manpower Data Center DoD Department of Defense FAR Federal Acquisition Regulation FRG Federal Republic of Germany GFP Government Furnished Property HLO High Level Objective HIPAA Health Insurance Portability and Accountability Act of 1996 IA Information Awareness IAC Installation Access Control IACO Installation Access Control Office ID Identification

IGCE Independent Government Cost Estimate IT Information Technology JTR Joint Travel Regulation JPAS Joint Personnel Adjudication System KO Contracting Officer OCI Organizational Conflict of Interest OCONUS Outside Continental United States (includes Alaska and Hawaii) ODC Other Direct Costs OPSEC Operations Security PA Property Administrator PII Personally Identifiable Information PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program RA Requiring Activity RCO Regional Contracting Office SIGE Safety and Health Protection Plan TE Technical Exhibit USAG United States Army Garrison USAREUR United States Army Europe UOM Unit of Measure

PART 3

GOVERNMENT PROPERTY (GP) AND SERVICES

3. Government Property and Services- N/A

PART 4

CONTRACTOR FURNISHED ITEMS AND SERVICES

4. Contractor Furnished Property and Services

4.1 General: The Contractor shall furnish all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items necessary to perform services as described in the PWS and associated contract documents, except for those items specified in Part 3 Government Property and Services.

4.2 Secret Facility Clearance: RESERVED

4.3 Materials: The Contractor shall furnish all materials and supplies required to perform work under this contract except that which is furnished by the Government (see Part 3). The Contractor shall provide all supplies, tools, and clothing (including personal protective clothing and equipment for Contractor employees when required by OSHA regulations, 29 CFR 1910, SUBPART I) required to meet the terms of the contract.

4.4 Vehicles and Equipment: The Contractor shall provide all necessary vehicles and equipment to perform the work described in this PWS. All Contractor provided vehicles, and equipment shall have the company name prominently displayed on both sides of the vehicle or equipment and present a neat, professional appearance. Contractor's vehicles and equipment used in the performance of this contract shall meet all local safety, and environmental requirements. Vehicles and equipment found to be unsafe shall be removed from the installation and replaced. The Contractor shall not use any Government-owned tools, materials, or parts to maintain Contractor vehicles and equipment without prior written approval of the Contracting Officer. The COR may inspect the Contractor’s vehicles and equipment at any time.

4.5 Background Checks): The Contractor shall provide Background Checks in accordance with this PWS and as determined by the Government.

PART 5

SPECIFIC TASKS

5.1 Basic Services: The Contractor shall provide all personnel, management, direct oversight, and any other items and services (not government furnished) necessary for maintaining CO2 gas levels of the six (6) rented CO2 tanks located at three (3) pools (Palmetto Falls Water Park (Bldg. 6511), Knight Pool (Bldg. 3296), and Legion Pool (Bldg. 2763)) on Fort Jackson.

5.2 Tasks: Tasks consist of the following:

5.2.1 Provide CO2 Gas: The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, other items and non-personal services necessary to perform operations for providing industrial grade CO2 gas for treating pool water on a Keep Full Program. The Contractor will provide a smart tank monitoring system at each location to monitor the CO2 levels. The contractor will monitor each location and provide FMWR a monitor as well. The contractor will ensure they do not let the tanks drop below 20- 30 % full at each location. The Contractor will then arrange to come out and fill the tanks that are needed. Contractor will provide a FMWR employee with a ticket from each location with amount filled and the date it was filled.

5.2.2 Tank Rental: The Contractor shall provide five (5) 750 lbs. tanks at the following location. Four (4) at Palmetto Falls Water Park, bldg. 6511 and one (1) tank at Knight Pool, bldg. 3296. Contractor shall provide one (1) 450 lbs. tank at Legion Pool, bldg. 2763.

Contractor is responsible for all maintenance, services and inspection of tanks.

PART 6

APPLICABLE PUBLICATIONS

6. Applicable Publications (Current Editions): The following publications, manuals, regulations, etc. are mentioned in this PWS and are listed below.

6.1.1 Department Of Defense Contract Security Classification Specification (DD Form 254)

6.1.2 Department of Defense Security Agreement (DD Form 441)

6.1.3 National Industrial Security Program Operating Manual (DoD 5220.22-M)

6.1.4 Installation Access Control (AE Reg 190-16)

6.1.5 The Army Physical Security Program (AR 190-13)

6.1.6 Contractor Identification (AE Reg 27-715)

6.1.7 U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1)

6.1.8 Information Assurance Workforce Improvement Program (DoD 8570-M)

6.1.9 Information Assurance Training Certification and Workforce Management Directive (DoDD 8570.01)

6.1.10 Information Assurance (AR 25-2)

6.1.11 Electromagnetic Compatibility Directive (2004/108/EC)

6.1.12 Policies and Procedures for Property Accountability (AR 735-5)

PART 7

ATTACHMENT AND TECHNICAL EXHIBIT LISTING

7. Attachment and Technical Exhibit List

7.1 Technical Exhibit A – Performance Requirements Summary

7.2 Technical Exhibit B – Deliverables Schedule

7.3 Attachment 1 – Historical Workload Data

TECHNICAL EXHIBIT A

Performance Requirements Summary (PRS)

PERFORMANCE

OBJECTIVE

STANDARD PERFORMANCE

THRESHOLD

ACCEPTABLE

QUALITY

LEVELS (AQLs)

METHOD OF

SURVEILLANCE

PRS#1 - PWS para (5.2.1)

Contractor will provide industrial grade CO2 gas for treating pool water on a Keep Full Program.

The contractor will ensure they do not let the tanks drop below 20-30 % full at each location.

No more than 1 tank dropping below 10% full in a year.

Periodic Inspection

PRS#2 - PWS para (5.2.1) Contractor will provide a FMWR employee with a ticket from each location with amount filled and the date it was filled.

The contractor ensure they give a FMWR employee ticket.

No more that 2 times forgetting to drop the ticket a year.

100% Inspection

TECHNICAL EXHIBIT B

DELIVERABLES SCHEDULE

Deliverable Frequency # of Copies Medium/Format Submit To A.001 Key Personnel:

(paragraph 1.9)

Within 5 days after contract award or 5 days after a replacement is hired.

One each to the Contracting Officer and

COR

Electronic delivery via email using Microsoft Office Word or Power Point 2013

To the Contracting Officer through the Contracting Officer’s Representati ve (COR)

A.002 Safety Plan:

(paragraph 1.13.1)

Within 30 business days after contract award.

One each to the Contracting Officer and

COR

Electronic delivery via email using Microsoft Office Word or Power Point 2013

To the Contracting Officer through the Contracting Officer’s Representati ve (COR)

A.003 Anti- Terrorism (AT) Level I Training:

(paragraph 1.15.1)

Within (5) calendar days after completion of training by all employees and subcontractor personnel

One each to the Contracting Officer and

COR

Electronic delivery via email using Microsoft Office Word or Power Point 2013

To the Contracting Officer through the Contracting Officer’s Representati ve (COR)

A.004 OPSEC

Training:

(paragraph 1.15.2)

NLT then five (5) calendar days after contract award.

One each to the COR

Electronic delivery via email using Microsoft Office Word or Power Point 2013

To the Contracting Officer through the Contracting Officer’s Representati ve (COR)

A.005 iWATCH Training:

(paragraph 1.15.3)

NLT then five (5) calendar days after contract award.

One each to the COR

Electronic delivery via email using Microsoft Office Word or Power Point 2013

To Contracting Officer’s Representati ve (COR)

ATTACHMENT 1

HISTORICAL WORKLOAD DATA

Year Palmetto Falls Legion Pool Knight Pool 2020 74,427 lbs. 6,428 lbs. 3,889 lbs.

2021 80,926 lbs. 3,861 lbs. 3,659 lbs.

2022 68,627 lbs. 2,733 lbs. 2,510 lbs.

2023 75,051 lbs. 5,475 lbs. 4,048 lbs.

2024 (9 months) 54,084 lbs. 3,761 lbs. 2,974 lbs.

PERFORMANCE WORK STATEMENT (PWS)
Part 1 General Information
1.5 General Information:
1.14.1 Environmental Compliance Objectives:
PART 2 DEFINITIONS & ACRONYMS
2. Definitions and Acronyms
PART 3
PART 4
4. Contractor Furnished Property and Services
PART 5 SPECIFIC TASKS
PART 6 APPLICABLE PUBLICATIONS
PART 7
7. Attachment and Technical Exhibit List

TECHNICAL EXHIBIT A