This document is a Task Assignment Notification Change Order Form for Florida Department of Environmental Protection (FDEP) Contract HW560, issued by the Waste Cleanup Programs division. The primary contractor is Tetra Tech, Inc., with Gerald Walker, P.G. serving as the contractor representative and Carrie L. Kruchell, P.G. as the DEP Contract Manager. The work is being performed at the Avalon Inn Property located at 443 4th Avenue North in St. Petersburg, Pinellas County, Florida, identified by Site ID ERIC_5563, COM_347598.

The change order reduces the total task cost from $25,727.60 to $25,496.60, representing a net decrease of $231.00. This reduction resulted from the elimination of a planned 35-foot deep monitoring well during the well installation and groundwater sampling project. During drilling operations on November 15, 2017, the subcontractor encountered difficult drilling conditions at 17 feet below land surface and was only able to reach 22 feet; the FDEP program manager subsequently approved cancellation of the deep well due to site lithology and petroleum hydrocarbon contamination assessment requirements. The subcontractor drilling cost was reduced from $2,714.00 to $2,504.00 by reducing well construction materials from 69 feet to 34 feet. Deliverables include MW Construction logs and field notes (due 11/30/2017), Laboratory COC and field notes (due 12/15/2017), and a Final Groundwater Assessment Report (due 02/01/2018). The task completion date was extended by 46 days from 01/14/2018 to 02/28/2018.

View the file

Other files

File Type Posted
CN-370000-HW560-A 11.pdf PDF
CN-370000-HW560-A10.pdf PDF
CN-370000-HW560-A3.pdf PDF
CN-370000-HW560-A4.pdf PDF
CN-370000-HW560-A5.pdf PDF
CN-370000-HW560-BF005C.pdf.crdownload CRDOWNLOAD file
CN-370000-HW560-BF006.pdf PDF
CN-370000-HW560-BF007A.pdf PDF
CN-370000-HW560-BF02BCO1.pdf PDF
CN-370000-HW560-BF05ACO2.pdf PDF
CN-370000-HW560-BF07ACO1.pdf PDF
CN-370000-HW560-BF602B.pdf PDF
CN-370000-HW560-BF602C.pdf PDF
CN-370000-HW560-BF61B.pdf PDF
CN-370000-HW560-CMC.pdf PDF
CN-370000-HW560-CO1.pdf PDF
CN-370000-HW560-CS16ACO1.pdf PDF
CN-370000-HW560-CS23ACO1.pdf PDF
CN-370000-HW560-CS25ACO1.pdf PDF
CN-370000-HW560-CS26ACO1.pdf PDF
CN-370000-HW560-CSS26A-2.pdf PDF
CN-370000-HW560-CSS30AC3.pdf PDF
CN-370000-HW560-DC005I.pdf PDF
CN-370000-HW560-DC007V.pdf PDF
CN-370000-HW560-DC007W.pdf PDF
CN-370000-HW560-DC008T.pdf PDF
CN-370000-HW560-DC009O.pdf PDF
CN-370000-HW560-DC011A.pdf PDF
CN-370000-HW560-DC011M.pdf PDF
CN-370000-HW560-DC018D.pdf PDF
CN-370000-HW560-DC01A.pdf PDF
CN-370000-HW560-DC01ACO4.pdf PDF
CN-370000-HW560-DC01ACO8.pdf PDF
CN-370000-HW560-DC023A.pdf PDF
CN-370000-HW560-DC025C.pdf PDF
CN-370000-HW560-DC027L.pdf PDF
CN-370000-HW560-DC028A.pdf PDF
CN-370000-HW560-DC028E.pdf PDF
CN-370000-HW560-DC028L.pdf PDF
CN-370000-HW560-DC02DCO1.pdf PDF
CN-370000-HW560-DC031A.pdf PDF
CN-370000-HW560-DC036A.pdf PDF
CN-370000-HW560-DC03D.pdf PDF
CN-370000-HW560-DC03G.pdf PDF
CN-370000-HW560-DC041A.pdf PDF
CN-370000-HW560-DC04C.pdf PDF
CN-370000-HW560-DC04F.pdf PDF
CN-370000-HW560-DC04FCO1.pdf PDF
CN-370000-HW560-DC06C.pdf PDF
CN-370000-HW560-DC06CCO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tetra Tech, Inc.

1558 Village Square Blvd., Ste. 2, Tallahassee, FL 32309-2478

Tel 850.385.9899 Fax 850.385.9860 www.tetratech.com

December 7, 2017

Department of Environmental Protection Waste Cleanup Programs ATTN: Ms. Carrie Kruchell MS #4535 Bob Martinez Center 2600 Blair Stone Road Tallahassee, Florida 32399-2400

Reference: Florida Department of Environmental Protection (FDEP) Waste

Cleanup Programs Consolidated Contract HW560

Subject: Request for Change Order – Monitoring Well Installation and

Groundwater Sampling at the Avalon Inn Property located at 443 4th Avenue North St Petersburg, Pinellas County, Florida

Dear Ms. Kruchell:

On November 15, 2017, Tetra Tech initiated monitoring well installation drilling operations at the Avalon Inn Property located at 443 4th Avenue North St Petersburg, Pinellas County, Florida. The drilling program included the installation of two shallow monitoring wells to 17 feet below land surface (bls) and one deep monitoring well to 35 feet bls. The subcontract drillers, using a 7720DT series Geoprobe rig, encountered difficult drilling and refusal due to a tight sand unit at 17 feet bls. The drillers were able to proceed using hollow stem augers, and reached 22 feet bls, and then proceeded to split spoon sample to 33 feet bls where the rods got stuck. The drillers were planning to mobilize a larger rig to the site to complete the deep monitoring well, when the FDEP program manager emailed Tetra Tech and indicated “we don’t need to install a deep well given the lithology and the fact that we are only dealing with petroleum hydrocarbons, and if that silt is acting as a semi-confining unit, we should be fine.” The two shallow monitoring wells were installed as proposed.

Based on the elimination of the deep monitoring well, a change order is required due to the reduced drilling costs. Because the drilling subcontract was set up with a daily unit rate for the DPT rig, a reduction in that unit rate is not available and the only reduction was for well construction materials. The well construction materials are reduced for the proposed 69 feet to 34 feet with a revised subcontractor cost of $2,504.00. The subcontract driller invoice is attached (Attachment A).

Attachment B provides the original Contract HW560 Cost Estimate Spreadsheet and the revised Change Order Cost Estimate Spreadsheet that contains the revised cost details for the reduced subcontractor costs. As indicated by the two HW560 Cost Estimate

Tetra Tech, Inc.

1558 Village Square Blvd., Ste. 2, Tallahassee, FL 32309-2478

Tel 850.385.9899 Fax 850.385.9860 www.tetratech.com

Spreadsheets, the drilling cost has been reduced resulting in a revised net cost of $25,496.50.

If you have any questions, please call myself or Frank Lesesne at (850) 385-9899.

Sincerely yours, Gerald Walker, P.G.

Program Manager

GAW/gaw Attachments c: Justin Cross, FDEP

Yanisa Angulo, FDEP Jay McGovern, Tetra Tech

Frank Lesesne, Tetra Tech Tallahassee File FDEP Contract HW 560

Attachment A

Contract HW560 Subcontract Driller Invoice

Attachment B

Contract HW560 Original Cost Spreadsheet and Revised Cost Spread Sheet

FDEP COST ESTIMATE

Contractor: Tetra Tech, Inc.

Date: October 27, 2017

Task #: HW560 SubTask 1 Project Management

Site: Avalon Inn SubTask 2 Well Installation & Groundwater Sampling

Activity/Phase: Well Installation and Groundwater Sampling SubTask 3 Groundwater Monitoring Report

Project Manager: Carrie Kruchell SubTask 4

SubTask 5

Totals 1 2 3 4 5

Labor Rate Category

$57.80 Project Manager (GW) 9 9.1

$51.73 Scientist V (FL) 8 4 4 0 0

$53.56 Engineer V (MJ) 8 0 8 0 0

$39.71 Scientist IV (BO) 59 55 4 0 0

$23.65 Engineer I (MQ) 50 0 50 0 0

$34.22 Staff GIS Specialist (JM) 4 0 4 0 0

$28.02 Project Assistant (JJ) 4 0 4 0 0

Total Hours 142 9 59 74 0 0

Direct Labor $4,711.71 $523.52 $2,390.97 $1,797.22 $0.00 $0.00

Overhead 143.00% $6,737.74 $748.63 $3,419.09 $2,570.02 $0.00 $0.00

Gen & Admin 12.20% $1,396.83 $155.20 $708.83 $532.80 $0.00 $0.00

Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Labor $12,846.28 $1,427.35 $6,518.89 $4,900.04 $0.00 $0.00

Other Direct Costs $235.59 $26.18 $119.55 $89.86 $0.00 $0.00

Travel

Vehicle Rental $485.00 $485.00 $0.00 $0.00 $0.00

Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00

Air Fare $0.00 $0.00 $0.00 $0.00 $0.00

Per diem + Hotel $660.00 $660.00 $0.00 $0.00 $0.00

Total Travel $1,145.00 $1,145.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement)

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00

Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00

Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement)

Transportation & Disposal $2,714.00 $2,714.00 $0.00 $0.00 $0.00

Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00

Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00

Surveying $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $2,714.00 $2,714.00 $0.00 $0.00 $0.00

Handling Fee $271.40 $271.40 $0.00 $0.00 $0.00

Total Subcontractor Cost $2,985.40 $2,985.40 $0.00 $0.00 $0.00

Laboratory

Analytical Costs $5,726.50 $5,726.50 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

Sample Shipping $416.00 $416.00 $0.00 $0.00 $0.00

Total Laboratory $6,142.50 $6,142.50 $0.00 $0.00 $0.00

Field Expenses

Hand Auger $0.00 $0.00 $0.00 $0.00 $0.00

Monitoring Well Installation Kit $368.60 $368.60 $0.00 $0.00 $0.00

Groundwater Sampling Kit $417.10 $417.10 $0.00 $0.00 $0.00

Expendables $162.50 $162.50 $0.00 $0.00 $0.00

Personal Protection (Level D) $140.00 $140.00 $0.00 $0.00 $0.00

Encore Sampler $0.00 $0.00 $0.00 $0.00 $0.00

Total Field Expenses $1,088.20 $1,088.20 $0.00 $0.00 $0.00

Subtotal $24,442.97 $1,453.53 $17,999.54 $4,989.90 $0.00 $0.00

Completion Fee $1,284.63 $142.74 $651.89 $490.00 $0.00 $0.00

Total Estimated Cost $25,727.60 $1,596.27 $18,651.43 $5,479.90 $0.00 $0.00

REV: 03/23/17 Page 1

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE :

SUBTASK 2: Well Installation & Groundwater Sampling

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Scientist V (FL) Tallahassee Office; Fieldwork coordination, communication & oversight 4

Engineer V (MJ)

Scientist IV (BO) 55

Engineer I (MQ) 0

Staff GIS Specialist (JM) 0

Project Assistant (JJ) 0

TOTAL LABOR 59

FIELD EXPENSES ITEM RATE COSTING UNIT USAGE TOTALS

Equipment

Hand Auger $8.25 Each 0 $0.00

Monitoring Well Installation Kit $184.30 Day 2 $368.60

Shallow Groundwater Sampling Kit $208.55 Day 2 $417.10

Expendables $32.50 Day 5 $162.50

Personal Protection (Level D) $28.00 Day 5 $140.00

Encore Sampler $8.75 Each 0 $0.00

TOTAL EQUIPMENT $1,088.20

VEHICLE TYPE RATE UNIT USAGE

Van/Truck $97.00 day 5 $485.00

Car $68.00 day 0 $0.00

Subtotal $485.00

Mileage Miles 0

TOTAL VEHICLE $485.00

PER DIEM STAFF RATE UNIT USAGE

MEALS

Scientist III (WO) $36.00 Day 5 $180.00

Engineer I (MQ) $36.00 Day 0 $0.00

HOTEL

Scientist III (WO) $120.00 Day 4 $480.00

Engineer I (MQ) $120.00 Day 0 $0.00

TOTAL PER DIEM $660.00

LABORATORY COSTS

PARAMETER Media Method RATE # SAMPLES #QAQC Expidated Analysis

Volatiles Liquid 8260 $135.00 9 2 Three Day Turn Around x 50% $2,227.50

Semivolatiles Liquid 8270 $100.00 9 1 Three Day Turn Around x 50% $1,500.00

Pesticides Liquid 8081 $90.00 0 0 $0.00

Herbicides Liquid 8151 $150.00 0 0 $0.00

TRPH Liquid Florida PRO $84.00 9 1 Three Day Turn Around x 50% $1,260.00

Lead Liquid 6010 $11.50 9 1 Three Day Turn Around x 50% $172.50

Total Dissolved Fe and Mn Liquid 6010 $23.00 2 0 Three Day Turn Around x 50% $69.00

COD Liquid SM5220 $25.00 2 0 Three Day Turn Around x 50% $75.00

BOD (5 day) Liquid SM5210 $25.00 2 0 Seven Day Turn Around x15% $57.50

Methane/CO2/02 Liquid 3810 $110.00 2 0 Three Day Turn Around x 50% $330.00

In-line Filter (0.45 Micron) $17.50 2 0 $35.00

Subtotal $5,726.50

Cost Containers

Sample Shipping $104.00 4 $416.00

Subtotal $416.00

TOTAL LAB $6,142.50

SUBCONTRACTOR COSTS

NAME PURPOSE COST Units

DrillPro LLC Monitoring Well Installation $2,714.00 $2,714.00

$0.00 $0.00

TOTAL $2,714.00

Avalon Inn

Tallahassee Office; Monitoring well installation oversight; surveying monitoring well top of well casings, groundwater sampling; and submittal of groundwater samples for laboratory analysis

REV: 03/23/17 Page 2

SUBTASK 3: Groundwater Monitoring Report

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Scientist V (FL) Tallahassee Office; Document review by a PG 4

Engineer V (MJ) Austin Office; Evaluate potential in-situ remeidal alternatives for groundwater 8

Scientist IV (BO) 4

Engineer I (MQ) 50

Staff GIS Specialist (JM) Jacksonville Office; Figure preparation 4

Project Assistant (JJ) Jacksonville Office; Document editing & publication 4

TOTAL LABOR 74

FIELD EXPENSES ITEM RATE COSTING UNIT USAGE TOTALS

Equipment

$0.00

Expendables $32.50 Day 0 $0.00

Personal Protection (Level D) $28.00 Day 0 $0.00

OVA (Ambient air monitoring & soil sample screening) $426.00 Week 0 $0.00

$0.00

TOTAL EQUIPMENT $0.00

VEHICLE TYPE RATE UNIT USAGE

Van/Truck $97.00 day 0 $0.00

Car $68.00 day 0 $0.00

Subtotal $0.00

Mileage Miles 0

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USAGE

MEALS

Scientist III (WO) $36.00 Day 0 $0.00

Engineer I (MQ) $36.00 Day 0 $0.00

HOTEL

Scientist III (WO) $120.00 Day 0 $0.00

Engineer I (MQ) $120.00 Day 0 $0.00

TOTAL PER DIEM $0.00

LABORATORY COSTS

PARAMETER Media Method RATE # SAMPLES #QAQC

Volatiles Solid 8260 $135.00 0 0 $0.00

Semivolatiles Solid 8270 $100.00 0 0 $0.00

Pesticides Solid 8081 $90.00 0 0 $0.00

Herbicides Solid 8151 $150.00 0 0 $0.00

PCBS Solid 8082 $66.00 0 0 $0.00

Metals (Ar, Cd, Cr, and Pb) Solid 6010 $50.00 0 0 $0.00 RCRA 8 Metals (Ar, Ba, Cd, Cr, Pb, Se, Ag) Solid 6010 $87.50 0 0 $0.00

Mercury Solid 7470/7471 $25.00 0 0 $0.00

TRPH Solid Florida PRO $84.00 0 0 $0.00

Subtotal $0.00

Cost Containers

Sample Shipping $104.00 0 $0.00

TOTAL LAB $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST Units

$0.00

TOTAL $0.00

Avalon Inn

Tallahassee Office; Document preparation; description of field activities including monitoring well installation, groundwater sampling, and laboratory analysis; and text, tables and figures

Tallahassee Office; doucment field activities for report

REV: 03/23/17 Page 3

FDEP COST ESTIMATE

Contractor: Tetra Tech, Inc.

Date: December 7, 2017

Task #: HW560 SubTask 1 Project Management

Site: Avalon Inn SubTask 2 Well Installation & Groundwater Sampling

Activity/Phase: CO reduction of MW installation SubTask 3 Groundwater Monitoring Report

Project Manager: Carrie Kruchell SubTask 4

SubTask 5

Totals 1 2 3 4 5

Labor Rate Category

$57.80 Project Manager (GW) 9 9.1

$51.73 Scientist V (FL) 8 4 4 0 0

$53.56 Engineer V (MJ) 8 0 8 0 0

$39.71 Scientist IV (BO) 59 55 4 0 0

$23.65 Engineer I (MQ) 50 0 50 0 0

$34.22 Staff GIS Specialist (JM) 4 0 4 0 0

$28.02 Project Assistant (JJ) 4 0 4 0 0

Total Hours 142 9 59 74 0 0

Direct Labor $4,711.71 $523.52 $2,390.97 $1,797.22 $0.00 $0.00

Overhead 143.00% $6,737.74 $748.63 $3,419.09 $2,570.02 $0.00 $0.00

Gen & Admin 12.20% $1,396.83 $155.20 $708.83 $532.80 $0.00 $0.00

Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Labor $12,846.28 $1,427.35 $6,518.89 $4,900.04 $0.00 $0.00

Other Direct Costs $235.59 $26.18 $119.55 $89.86 $0.00 $0.00

Travel

Vehicle Rental $485.00 $485.00 $0.00 $0.00 $0.00

Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00

Air Fare $0.00 $0.00 $0.00 $0.00 $0.00

Per diem + Hotel $660.00 $660.00 $0.00 $0.00 $0.00

Total Travel $1,145.00 $1,145.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement)

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00

Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00

Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement)

Drilling (Non-conventional) $2,504.00 $2,504.00 $0.00 $0.00 $0.00

Transport and disposal $0.00 $0.00 $0.00 $0.00 $0.00

Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00

Surveying $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $2,504.00 $2,504.00 $0.00 $0.00 $0.00

Handling Fee $250.40 $250.40 $0.00 $0.00 $0.00

Total Subcontractor Cost $2,754.40 $2,754.40 $0.00 $0.00 $0.00

Laboratory

Analytical Costs $5,726.50 $5,726.50 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

Sample Shipping $416.00 $416.00 $0.00 $0.00 $0.00

Total Laboratory $6,142.50 $6,142.50 $0.00 $0.00 $0.00

Field Expenses

Hand Auger $0.00 $0.00 $0.00 $0.00 $0.00

Monitoring Well Installation Kit $368.60 $368.60 $0.00 $0.00 $0.00

Groundwater Sampling Kit $417.10 $417.10 $0.00 $0.00 $0.00

Expendables $162.50 $162.50 $0.00 $0.00 $0.00

Personal Protection (Level D) $140.00 $140.00 $0.00 $0.00 $0.00

Encore Sampler $0.00 $0.00 $0.00 $0.00 $0.00

Total Field Expenses $1,088.20 $1,088.20 $0.00 $0.00 $0.00

Subtotal $24,211.97 $1,453.53 $17,768.54 $4,989.90 $0.00 $0.00

Completion Fee $1,284.63 $142.74 $651.89 $490.00 $0.00 $0.00

Total Estimated Cost $25,496.60 $1,596.27 $18,420.43 $5,479.90 $0.00 $0.00

REV: 03/23/17 Page 1

SUBTASK 2: Well Installation & Groundwater Sampling

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Scientist V (FL) Tallahassee Office; Fieldwork coordination, communication & oversight 4

Engineer V (MJ)

Scientist IV (BO) 55

Engineer I (MQ) 0

Staff GIS Specialist (JM) 0

Project Assistant (JJ) 0

TOTAL LABOR 59

FIELD EXPENSES ITEM RATE COSTING UNIT USAGE TOTALS

Equipment

Hand Auger $8.25 Each 0 $0.00

Monitoring Well Installation Kit $184.30 Day 2 $368.60

Shallow Groundwater Sampling Kit $208.55 Day 2 $417.10

Expendables $32.50 Day 5 $162.50

Personal Protection (Level D) $28.00 Day 5 $140.00

Encore Sampler $8.75 Each 0 $0.00

TOTAL EQUIPMENT $1,088.20

VEHICLE TYPE RATE UNIT USAGE

Van/Truck $97.00 day 5 $485.00

Car $68.00 day 0 $0.00

Subtotal $485.00

Mileage Miles 0

TOTAL VEHICLE $485.00

PER DIEM STAFF RATE UNIT USAGE

MEALS

Scientist III (WO) $36.00 Day 5 $180.00

Engineer I (MQ) $36.00 Day 0 $0.00

HOTEL

Scientist III (WO) $120.00 Day 4 $480.00

Engineer I (MQ) $120.00 Day 0 $0.00

TOTAL PER DIEM $660.00

LABORATORY COSTS

PARAMETER Media Method RATE # SAMPLES #QAQC Expidated Analysis

Volatiles Liquid 8260 $135.00 9 2 Three Day Turn Around x 50% $2,227.50

Semivolatiles Liquid 8270 $100.00 9 1 Three Day Turn Around x 50% $1,500.00

Pesticides Liquid 8081 $90.00 0 0 $0.00

Herbicides Liquid 8151 $150.00 0 0 $0.00

TRPH Liquid Florida PRO $84.00 9 1 Three Day Turn Around x 50% $1,260.00

Lead Liquid 6010 $11.50 9 1 Three Day Turn Around x 50% $172.50

Total Dissolved Fe and Mn Liquid 6010 $23.00 2 0 Three Day Turn Around x 50% $69.00

COD Liquid SM5220 $25.00 2 0 Three Day Turn Around x 50% $75.00

BOD (5 day) Liquid SM5210 $25.00 2 0 Seven Day Turn Around x15% $57.50

Methane/CO2/02 Liquid 3810 $110.00 2 0 Three Day Turn Around x 50% $330.00

In-line Filter (0.45 Micron) $17.50 2 0 $35.00

Subtotal $5,726.50

Cost Containers

Sample Shipping $104.00 4 $416.00

Subtotal $416.00

TOTAL LAB $6,142.50

SUBCONTRACTOR COSTS

NAME PURPOSE COST Units

DrillPro LLC Monitoring Well Installation $2,504.00 $2,504.00

$0.00 $0.00

TOTAL $2,504.00

Avalon Inn

Tallahassee Office; Monitoring well installation oversight; surveying monitoring well top of well casings, groundwater sampling; and submittal of groundwater samples for laboratory analysis

REV: 03/23/17 Page 2

SUBTASK 3: Groundwater Monitoring Report

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Scientist V (FL) Tallahassee Office; Document review by a PG 4

Engineer V (MJ) Austin Office; Evaluate potential in-situ remeidal alternatives for groundwater 8

Scientist IV (BO) 4

Engineer I (MQ) 50

Staff GIS Specialist (JM) Jacksonville Office; Figure preparation 4

Project Assistant (JJ) Jacksonville Office; Document editing & publication 4

TOTAL LABOR 74

FIELD EXPENSES ITEM RATE COSTING UNIT USAGE TOTALS

Equipment

$0.00

Expendables $32.50 Day 0 $0.00

Personal Protection (Level D) $28.00 Day 0 $0.00

OVA (Ambient air monitoring & soil sample screening) $426.00 Week 0 $0.00

$0.00

TOTAL EQUIPMENT $0.00

VEHICLE TYPE RATE UNIT USAGE

Van/Truck $97.00 day 0 $0.00

Car $68.00 day 0 $0.00

Subtotal $0.00

Mileage Miles 0

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USAGE

MEALS

Scientist III (WO) $36.00 Day 0 $0.00

Engineer I (MQ) $36.00 Day 0 $0.00

HOTEL

Scientist III (WO) $120.00 Day 0 $0.00

Engineer I (MQ) $120.00 Day 0 $0.00

TOTAL PER DIEM $0.00

LABORATORY COSTS

PARAMETER Media Method RATE # SAMPLES #QAQC

Volatiles Solid 8260 $135.00 0 0 $0.00

Semivolatiles Solid 8270 $100.00 0 0 $0.00

Pesticides Solid 8081 $90.00 0 0 $0.00

Herbicides Solid 8151 $150.00 0 0 $0.00

PCBS Solid 8082 $66.00 0 0 $0.00

Metals (Ar, Cd, Cr, and Pb) Solid 6010 $50.00 0 0 $0.00 RCRA 8 Metals (Ar, Ba, Cd, Cr, Pb, Se, Ag) Solid 6010 $87.50 0 0 $0.00

Mercury Solid 7470/7471 $25.00 0 0 $0.00

TRPH Solid Florida PRO $84.00 0 0 $0.00

Subtotal $0.00

Cost Containers

Sample Shipping $104.00 0 $0.00

TOTAL LAB $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST Units

$0.00

TOTAL $0.00

Avalon Inn

Tallahassee Office; Document preparation; description of field activities including monitoring well installation, groundwater sampling, and laboratory analysis; and text, tables and figures

Tallahassee Office; doucment field activities for report

REV: 03/23/17 Page 3