CN-370000-HW560-DC027L.pdf

PDF 521 KB Posted

Attached to
Master Agreement FL|HW560|10644db8faa9279934cd6b08f1138598
Contract number
HW560
Issued by
Florida

About this file

This is a Task Assignment Notification Form for the Florida Department of Environmental Protection (FDEP) under DEP Contract No. HW560. The contractor is Tetra Tech, Inc., with Shawn Ouellette serving as the contractor representative and Dean Cox as the DEP Contract Manager. The task assignment pertains to operation and maintenance services at the Palace Cleaners site located at 733 S. Orange Blossom Trail, Apopka, Orange County, Florida (ERIC_5049).

The task assignment requires Tetra Tech to conduct three months of operation and maintenance (O&M) of the Soil Vapor Extraction (SVE) system in accordance with the December 2021 scope of work. The assignment consists of three subtasks: Subtask 1 (Project Management calculated at 12.5 percent of direct labor); Subtask 2 (SVE O&M activities including monthly site visits, vapor sampling, and a Quarterly O&M Summary deliverable); and Subtask 3 (utility services for three months from Duke Energy at $350 per month with a $20 monthly handling fee). The total task assignment value is $7,248.79, comprised of a fixed price of $6,198.79, a cost reimbursement of $1,050.00 for utilities, and a fixed fee of $0.00. The only cost-plus fixed fee component is utility payment reimbursement. The final deliverable, a Quarterly O&M Summary, is due May 31, 2022, with task assignment execution through August 31, 2022. Payment of $6,138.79 is contingent upon completion of O&M activities and FDEP approval of the Quarterly O&M Summary, with an additional $1,110.00 for utility costs and handling fees upon FDEP receipt of utility invoices.

View the file

Other files

File Type Posted
CN-370000-HW560-A12.pdf PDF
CN-370000-HW560-A2.pdf PDF
CN-370000-HW560-A7.pdf PDF
CN-370000-HW560-A8.pdf PDF
CN-370000-HW560-BF02B.pdf PDF
CN-370000-HW560-BF03B.pdf PDF
CN-370000-HW560-BF04A.pdf PDF
CN-370000-HW560-BF04ACO1.pdf PDF
CN-370000-HW560-BF04D.pdf PDF
CN-370000-HW560-BF05.pdf PDF
CN-370000-HW560-BF05ACO4.pdf PDF
CN-370000-HW560-BF06.pdf PDF
CN-370000-HW560-BF06CO1.pdf PDF
CN-370000-HW560-BF07BCO1.pdf PDF
CN-370000-HW560-BF602A.pdf PDF
CN-370000-HW560-BF62BCO1.pdf PDF
CN-370000-HW560-BF62CCO1.pdf PDF
CN-370000-HW560-BF62CCO2.pdf PDF
CN-370000-HW560-CO4.pdf PDF
CN-370000-HW560-CO5.pdf PDF
CN-370000-HW560-CS19ACO1.pdf PDF
CN-370000-HW560-CSS-19A.pdf PDF
CN-370000-HW560-CSS-31A.pdf PDF
CN-370000-HW560-CSS-32A.pdf PDF
CN-370000-HW560-CSS3ACO1.pdf PDF
CN-370000-HW560-DC006I.pdf PDF
CN-370000-HW560-DC007P.pdf PDF
CN-370000-HW560-DC008R.pdf PDF
CN-370000-HW560-DC009A.pdf PDF
CN-370000-HW560-DC010O.pdf PDF
CN-370000-HW560-DC01ACO1.pdf PDF
CN-370000-HW560-DC01ACO5.pdf PDF
CN-370000-HW560-DC01ACO6.pdf PDF
CN-370000-HW560-DC01ACO9.pdf PDF
CN-370000-HW560-DC021C.pdf PDF
CN-370000-HW560-DC025A.pdf PDF
CN-370000-HW560-DC025D.pdf PDF
CN-370000-HW560-DC027J.pdf PDF
CN-370000-HW560-DC030K.pdf PDF
CN-370000-HW560-DC031B.pdf PDF
CN-370000-HW560-DC032B.pdf PDF
CN-370000-HW560-DC035B.pdf PDF
CN-370000-HW560-DC036F.pdf PDF
CN-370000-HW560-DC03CCO1.pdf PDF
CN-370000-HW560-DC03I.pdf PDF
CN-370000-HW560-DC04CCO1.pdf PDF
CN-370000-HW560-DC04CCO2.pdf PDF
CN-370000-HW560-DC04D.pdf PDF
CN-370000-HW560-DC04E.pdf PDF
CN-370000-HW560-DC05D.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEP CONTRACT NO.

Task Assignment #: Module #: Grant #:

Contractor Name:

Contractor Representative:

DEP Contract Manager: Phone #:

DEP Site #:

Site Name:

Address(Street, City, County):

Phase:

Task Description [use additional pages if necessary]:

The Deliverable and Invoice Schedule is attached.

Final Deliverables:

Final Deliverable Due Date:

TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:

FIXED FEE

RETAINAGE:

TOTAL TASK ASSIGNMENT VALUE: $0.00

DEP Task Manager:

DEP Contract Manager:

Contractual Authority:

Contractor Representative:

CC: Procurement Section (MS 93) Section Representative ________

TASK ASSIGNMENT NOTIFICATION FORM

COST PLUS FIXED FEE

COST REIMBURSEMENT

FIXED PRICE FEE SCHEDULE

Period of Performance:

Execution of Task Assignment through:

DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).

WCP TAFORM 01_18

HW560

D000 NADC027L

Tetra Tech

Shawn Oullette

850-245-8969Dean Cox

ERIC_5049

Palace Cleaners

733 S. Orange Blossom Trail, Apopka, Orange County

Operation & Maintenenance (O&M)

Tetra Tech will conduct three months O&M in accordance with the December 2021 scope of work.

The payment of utilities is the only part of this TA that is cost plus fixed fee.

Quarterly O&M Summary

05/31/2022

08/31/2022

$ 6,198.79 $ 0.00 $ 1,050.00 $ 0.00

$ 0.00

Dean Cox Digitally signed by Dean Cox Date: 2021.12.10 15:16:54 -05'00'

Dean Cox Digitally signed by Dean Cox Date: 2021.12.10 15:17:08 -05'00'

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2021.12.10 15:40:08 -05'00'

Shawn Ouellette Digitally signed by Shawn Ouellette Date: 2021.12.10 15:51:00 -05'00'

$ 7,248.79

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 01-2018

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

HW560

Quarterly O&M Summary/Project Management - Subtasks 1 & 2 05/31/2022

Subtasks 1 & 2: Upon completion of O&M activities and FDEP approval of the Quarterly O&M Summary/Project Management $ 6,138.79

FDEP receipt of utility invoices for 3 months; Utilities (Cost Plus Fixed Fee) = not to exceed $1,050; Utilities Handling Fee = $60 - Subtask 3 $ 1,110.00

$ 7,248.79

DC027L

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Interim Secretary

TO: HW 560 Contract File Palace Cleaners

ERIC_5049

Apopka, Orange County

FROM: Dean Cox, Contract Manager

DATE: December 10, 2021

SUBJECT: Task Assignment DC027L

Negotiation Summary Operation & Maintenance

Tetra Tech will conduct 3 months O&M of the Soil Vapor Extraction (SVE) system.

Specific subtasks are detailed below.

Subtask 1: Project Management Project management is calculated at 12.5 percent of the direct labor.

Subtask 2: SVE O&M Subtask 2 includes costs for O&M and reporting. O&M activities will include monthly site visits and periodic vapor sampling. Upon completion of O&M, a Quarterly O&M Summary will be generated. The summary will include laboratory analytical reports, O&M data tables update, monthly system checklists, fieldwork documentation, and a recommendation for future system operations.

Subtask 3: Utilities Subtask 3 includes 3 months of utility service and $20 per month handling fee. The utility invoices will be submitted to the Department for reimbursement.

Documentation of the costs is included in the attached CEF, Level-of-Effort sheets, and the Tetra Tech proposal.

The final cost total for DC027L is $7,248.79.

FDEP COST ESTI MATEContractor: Tetra Tech

Date: December 9, 2022

Task #: HW560-DC027L SubTask 1 Project Management SubTask 6

Site: Palace Dry Cleaners, Apopka SubTask 2 SVE System O&M - (Jan- Mar '22) SubTask 7

Activity/Phase: O&M SubTask 3 Utility Services (Jan-Mar 22) SubTask 8

Project Manager: Dean Cox SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$48.08 Project Manager (SO) 3 2.8 $34.10 Senior Technician (MM) 27 27.0 0 0 0 0 0 0 0 0 $57.63 Engineer V (MJ) 3 3 0 0 0 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0 Total Hours 33 3 30.0 0 0 0 0 0 0 0 0

Direct Labor $1,230.29 $136.70 $1,093.59 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 143.00% $1,759.31 $195.48 $1,563.83 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 12.20% $364.74 $40.53 $324.21 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $3,354.34 $372.71 $2,981.63 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Other Direct Costs $61.52 $6.84 $54.68 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Travel

Vehicle Rental $291.00 $291.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs 160 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $291.00 $291.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 Page 1

FDEP COST ESTI MATEContractor: Tetra Tech

Date: December 9, 2022

Task #: HW560-DC027L SubTask 1 Project Management SubTask 6

Site: Palace Dry Cleaners, Apopka SubTask 2 SVE System O&M - (Jan- Mar '22) SubTask 7

Activity/Phase: O&M SubTask 3 Utility Services (Jan-Mar 22) SubTask 8

Project Manager: Dean Cox SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Subcontractor (Equipment Procurement)

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $1,050.00 $0.00 $1,050.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $1,050.00 $0.00 $1,050.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $60.00 $0.00 $60.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $1,110.00 $0.00 $1,110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $1,000.00 $1,000.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $126.00 $126.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $1,126.00 $1,126.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $97.50 $97.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $873.00 $873.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $970.50 $970.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $6,913.36 $379.55 $5,423.81 $1,110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $335.43 $37.27 $298.16 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $7,248.79 $416.82 $5,721.97 $1,110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Palace Dry Cleaners, Apopka SUBTASK 2: SVE System O&M - (Jan - Mar '22)

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Technician (MM) January Monthly system performance (Collect Influent Air Sample analyze for TO-15 DC Shortlist) 9 6 hrs round trip travel and 3 hr on-site

Senior Technician (MM) February Monthly system performance 8.5 6 hrs round trip travel and 2.5 hr on-site

Senior Technician (MM) March Monthly system performance (Collect Influent and all VEW Air Samples analyze for TO-15 DC Shortlist) 9.5 6 hrs round trip travel and 3.5 hr on-site

Engineer V (MJ) Submit 3 O&M Checklists 3 O&M Tables 6 tables per visit @ 0.5

TOTAL LABOR 30

EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS

Equipment O&M Kit $291.00 day 3 $873.00 Expendables $32.50 day 3 $97.50

TOTAL EQUIPMENT $970.50

VEHICLE TYPE RATE UNIT USAGE

Equipment Van $97.00 day 3 $291.00

TOTAL VEHICLE $291.00

PER DIEM STAFF RATE UNIT USAGE

MEALS

HOTEL

TOTAL PER DIEM $0.00

LABORATORY COSTS

PARAMETER MEDIA METHOD RATE # SAMPLES # QA/QC

Organics Air TO15 $200.00 1 0 (influent - January 2021) $200.00

Organics Air TO15 $200.00 4 0 (All Vews and Common INF - March 202 $800.00

Shipping, FedEx, 5 lb @ 24 hrs $63.00 2 (from SVE) $126.00

TOTAL LAB $1,126.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

TOTAL $0.00

CEF DC027L LOE 2

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Palace Dry Cleaners, Apopka SUBTASK 3: Utility Invoice Services - (Jan- Mar 2022)

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

TOTAL LABOR 0

EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS

Equipment

TOTAL EQUIPMENT $0.00

VEHICLE TYPE RATE UNIT USAGE

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USAGE

MEALS

HOTEL

TOTAL PER DIEM $0.00

LABORATORY COSTS

PARAMETER MEDIA METHOD RATE # SAMPLES # QA/QC

TOTAL LAB $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Duke Energy 3 month of power $350 month $1,050.00

TOTAL $1,050.00

CEF DC027L LOE 3

759 South Federal Highway, Suite 314 Stuart, FL 34994 Tel 772.781.3400 Fax 772.781.3411 www.tetratech.com

December 9, 2021

TTST-HW560-21-093

Mr. Dean Cox Contract Manager Florida Department of Environmental Protection 2600 Blair Stone Road Tallahassee, FL 32399-2400

SUBJECT: REQUEST FOR TASK ASSIGNMENT HW560-HW027L

PALACE DRY CLEANERS

733 S. ORANGE BLOSSOM TRAIL

APOPKA, FL 32703

ERIC_5049

Dear Mr. Cox:

Tetra Tech, Inc. is requesting a Task Assignment to continue the SVE system’s operation and maintenance (O&M) at the Palace Cleaners site in Apopka, Florida. The following presents a scope of work (SOW) summary and the proposed schedule.

SOW – Field Activities The field activities associated with the proposed SOW will include travel to the site and completion of the O&M checklist on a monthly basis for one quarter.

The Task Assignment request also includes 3 months of Utility Invoice Services (January- March 2022) from Duke Energy to operate the SVE system, estimated at $350/month.

SOW – Reporting Following completion of field activities and receipt of the analytical data, the data will be incorporated into the O&M tables. Costs for this activity has been accounted for in subtask 2.

The proposed deliverables and deliverable due dates are summarized below:

• Subtask 1 – Project Management

• Subtask 2 – Monthly System Monitoring - (January Mar 2022):

Deliverable (3 Monthly O&M checklists field documentation, laboratory report, email recommendations and data tables) due date. May 31, 2022

• Subtask 3 – Submittal of three months of paid utility invoices:

Deliverable due date May 31, 2022

Sincerely, Shawn Ouellette, P.G.

Project Manager c: File

HW560 DC027L signed (002).pdf
TANF DC027L.pdf
Task Assignment Notification
BWC Task Assignment Form (Rev 02_17).pdf
BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf
Deliverable & Invoice Schedule
CEF DC027L.pdf
CE
LOE 2
LOE 3

proposal DC027L.pdf

DC027L NSrev.pdf

File details come from the government source that posted it. Updated .