About this file

This document is a Task Assignment Notification (TA BF602B) issued under the Florida Department of Environmental Protection (FDEP) Consolidated Contract HW560, administered through the State and Tribal Response (SRP) Program in cooperation with the U.S. Environmental Protection Agency (EPA). The task assignment was awarded to Tetra Tech, Inc. for supplemental site assessment activities at the Port of Fort Pierce (formerly King Maritime Group) located at 101 Port Avenue A, Fort Pierce, Florida 34950. The work is being conducted under FDEP's Waste Cleanup Programs with federal funding from the SRP cooperative agreement.

The task assignment encompasses a Supplemental Site Assessment involving four subtasks: Project Management ($2,393.89), Quality Assurance Project Plan and Health and Safety Plan development ($4,354.99), supplemental soil and groundwater sampling activities including 66 soil samples from 22 boring locations and 12 groundwater samples from newly installed and existing monitoring wells ($25,547.88), and preparation of a final Supplemental Site Assessment Report ($4,075.32). The total fixed-price contract value is $36,372.08 with a performance period ending February 15, 2021 and a final deliverable due date of January 15, 2021. Invoicing is structured in three milestones based on departmental approval of deliverables: approval of the work plan ($4,354.99), approval of field documentation ($25,547.88), and approval of the final report ($6,469.21). The work includes utility location services from GeoTek Services ($1,500.00) and drilling services from Preferred Drilling Solutions ($5,105.00), with laboratory analysis performed by TestAmerica using contract rates under HW560.

View the file

Other files

File Type Posted
CN-370000-HW560-A9.pdf PDF
CN-370000-HW560-BF005.pdf PDF
CN-370000-HW560-BF005B.pdf PDF
CN-370000-HW560-BF005C.pdf PDF
CN-370000-HW560-BF02C.pdf PDF
CN-370000-HW560-BF02CCO1.pdf PDF
CN-370000-HW560-BF03A.pdf PDF
CN-370000-HW560-BF03BCO1.pdf PDF
CN-370000-HW560-BF04BCO1.pdf PDF
CN-370000-HW560-BF04CCO1.pdf PDF
CN-370000-HW560-BF04CCO3.pdf PDF
CN-370000-HW560-BF04DCO1.pdf PDF
CN-370000-HW560-BF05A.pdf PDF
CN-370000-HW560-BF05ACO3.pdf PDF
CN-370000-HW560-BF07B.pdf PDF
CN-370000-HW560-BF07BCO3.pdf PDF
CN-370000-HW560-BF601A.pdf PDF
CN-370000-HW560-BF601C.pdf PDF
CN-370000-HW560-CS18ACO1.pdf PDF
CN-370000-HW560-CSS-16A.pdf PDF
CN-370000-HW560-CSS-21A.pdf PDF
CN-370000-HW560-CSS-26A.pdf PDF
CN-370000-HW560-CSS25A.pdf PDF
CN-370000-HW560-CSS3A.pdf PDF
CN-370000-HW560-CSS3ACO2.pdf PDF
CN-370000-HW560-DC005K.pdf PDF
CN-370000-HW560-DC006B.pdf PDF
CN-370000-HW560-DC009N.pdf PDF
CN-370000-HW560-DC010I.pdf PDF
CN-370000-HW560-DC010N.pdf PDF
CN-370000-HW560-DC011A C.pdf PDF
CN-370000-HW560-DC015I.pdf PDF
CN-370000-HW560-DC019D.pdf PDF
CN-370000-HW560-DC019F.pdf PDF
CN-370000-HW560-DC01ACO3.pdf PDF
CN-370000-HW560-DC023E.pdf PDF
CN-370000-HW560-DC023F.pdf PDF
CN-370000-HW560-DC025E.pdf PDF
CN-370000-HW560-DC026C.pdf PDF
CN-370000-HW560-DC027A.pdf PDF
CN-370000-HW560-DC027B.pdf PDF
CN-370000-HW560-DC027K.pdf PDF
CN-370000-HW560-DC027i.pdf PDF
CN-370000-HW560-DC028H.pdf PDF
CN-370000-HW560-DC029C.pdf PDF
CN-370000-HW560-DC030C.pdf PDF
CN-370000-HW560-DC030F.pdf PDF
CN-370000-HW560-DC033C.pdf PDF
CN-370000-HW560-DC034A.pdf PDF
CN-370000-HW560-DC038C.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Task Assignment Notification/Change Order

Deliverables and Invoice Schedule Attachment

WC) TAFORM $'"&$%(

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

QAPP/Work Plan and HASP 11/16/2020

Field notes, photographic log, chain of custody, soil sampling logs, groundwater sampling logs. 12/18/2020

Supplemental Site Assessment Report 01/15/2021

Department approval of QAPP/Work Plan and HASP (Subtask 2)

$ 4,354.99

Department approval of field notes, photographic log, chain of custody, soil sampling logs, and groundwater sampling logs (Subtask 3) $ 25,547.88

Department approval of Supplemental Site Assessment Report (Subtasks 1 & 4)

$ 6,469.21

$ 36,372.08

HW560

BF602B

Negotiation Summary – Task Assignment (TA) BF602B Port of Fort Pierce aka: Former King Maritime Group

ERIC_15269

October 22, 2020 monitoring wells at select locations to assess groundwater contamination. Soil samples will be collected from three depth intervals, 0-0.5 feet, 0.5-2 feet, and 2-4 feet below land surface, and analyzed for TRPH and/or arsenic. Groundwater samples will be collected and analyzed for arsenic and/or TRPH, ammonia, and nitrate. In addition, quality assurance/quality control samples will be collected for analysis. These include field duplicates for both soil and groundwater (1 per 10 sample minimum) and equipment rinsate samples for both soil and groundwater (1 per 20 minimum). The soil and groundwater samples will be analyzed by TestAmerica. The agreed upon cost of this subtask is $25,547.88.

Subtask 4: Supplemental Site Assessment Report A Supplemental Site Assessment Report will be prepared detailing the field and laboratory results.

This report will also include figures, maps, tables, and conclusions and recommendations for any future work. The agreed upon cost of this subtask is $4,075.32.

Summary The Department’s SRP Contract Manager and Tetra Tech’s Contract Manager have both agreed to the scope of work and associated costs. The final cost associated with this TA is $36,372.08.

Documentation of these costs is included in the Cost Proposal/Level of Effort (CP/LOE) Form and CP/LOE letter provided by Tetra Tech on October 8, 2020, as well as the Task Assignment Form for BF602B prepared by the Department. The final deliverable must be received by the Department no later than January 15, 2021.

Tetra Tech, Inc.

1558 Village Square Blvd., Ste. 2, Tallahassee, FL 32309-2478

Tel 850.385.9899 Fax 850.385.9860 www.tetratech.com

TetraTech/TAL-20-078-HW560

October 8, 2020

Department of Environmental Protection Waste Cleanup Programs ATTN: Ms. Megan Johnson MS #4535 Bob Martinez Center 2600 Blair Stone Road Tallahassee, Florida 32399-2400

Reference: Florida Department of Environmental Protection (DEP) Waste

Subject:

Cleanup Programs Consolidated Contract HW560

Cost Proposal – "+))&$'$(*#& "%*$ Assessment at Former King Maritime Group (AKA: Port of Fort Pierce), Fort Pierce, St. Lucie County, Florida

Dear Ms. Johnson:

Tetra Tech is pleased to submit to the Florida Department of Environmental Protection (FDEP) this revised cost proposal to conduct #-**'%(%),$' #&,% Assessment activities at the Former King Maritime Group Site at 101 Port Avenue A, Fort Pierce, Florida (See Figure 1). This site is owned by St. Lucie County.

Tetra Tech conducted soil and groundwater assessment work at the site in May 2020, which was documented in our report to FDEP of September 10, 2020. Based on the report findings, FDEP identified the need for additional work to complete delineation of Total Recoverable Petroleum Hydrocarbons (TRPH) in the soil at several areas on the site, the need for a background study for Arsenic in soil and groundwater, and confirmatory groundwater quality sampling. The proposed work to address these needs includes additional soil assessment to delineate TRPH at Areas B, C, and I; confirmatory sampling of groundwater from existing monitoring wells; an additional well for TRPH and Arsenic sampling at Area I; and off site sampling to help establish background concentrations for Arsenic in soil and groundwater. The proposed work described herein also includes additional sampling for Arsenic in soil at potential source areas along former railroad spur lines on the property.

The detailed activities associated with collection of the additional data are shown in Table 1. These subtasks will include the following activities:

Subtask 1 - Project Management: Project Management includes managing the project scope, schedule, and budget. The level of effort is based on the HW560 Contract requirements and assumes 13 hours for Task 1.

Subtask 2 - Work Plan & Health and Safety Plan (HASP): This task includes pre-intrusive field activities including: a teleconference and site reconnaissance to coordinate with the site contact and local government representatives and identify specific sampling locations to be included in the

Tel 850.385.9899 Fax 850.385.9860 www.tetratech.com work plan, including locations for the background study; preparation of the work plan; and update of the site HASP for the monitoring well installation and sampling activities. Additional description of the activities includes:

� Site reconnaissance. This activity will be conducted under the supervision of a Senior Scientist (Scientist V) based in the Tetra Tech Tallahassee, FL office who is experienced in site assessment under the FDEP CERCLA/Brownfields program and will have direct contact with FDEP throughout the project. A Senior Scientist (Scientist IV) based in the Tetra Tech Cocoa, FL office will be field operations lead for the project. Prior to other field activities, the Scientist IV will conduct a site walkover with onsite representatives and locate proposed boring and well locations on the site and on public rights of way and obtain information on right of way and public property access.

� Work plan and Health and Safety Plan. After the site reconnaissance is conducted, the project work plan and updated HASP will be produced by Tallahassee-based staff. The work plan will include tables and figures identifying the sampling locations and providing details on laboratory analyses and quality assurance samples. The HASP originally developed for the project will be updated to reflect scope and personnel changes.

The level of effort assumes 1 hour for a Project Manager to review the work plan, 7 hours for a Senior Scientist (Scientist V) for coordination, communication and work plan production; 12 hours for a Senior Scientist (Scientist IV) for the reconnaissance; 12 hours for a Staff Scientist for work plan preparation; 1 hour for a Staff Engineer (office health and safety officer) to update the HASP;

and 2 hours for figure preparation.

Subtask 3 – Soil Sampling, Well Installation, and Groundwater Sampling: This subtask includes subsurface utility location, monitoring well installation, groundwater sampling, soil sampling and other field activities. The field activities and level of effort summary are described below and the level of effort, subcontractor, equipment, travel, and supplies needed for this subtask are described in the cost estimate worksheets. Sampling objectives and proposed activities are described in Table 1. The site map with areas of interest is provided as Figure 1. Specific sampling locations will be provided in the work plan.

� Utility location and right of way access. Prior to intrusive field activities, underground utilities on the property will be marked and all proposed monitoring well and soil boring locations will be cleared for underground utilities. In addition to the standard 811 one call location of public utilities, a private utility location service will be employed to clear proposed well and boring locations. This service will be provided by GeoTech, a subcontractor that has provided these services in the past for Tetra Tech and FDEP. A Tetra Tech representative will be on site to coordinate the work provided by the subcontractor. Background soil borings and monitoring well locations will most likely be on public property and rights of way, which will require obtaining formal permission and right of way access permits. The right of way access permitting process will begin once proposed locations are approved by FDEP. No costs for right of way permits are included in this proposal. Right of way permit costs, if applicable, will be included in a change order request.

� Monitoring well installation and shallow soil coring. Permanent monitoring wells will be installed at four locations by a Florida-licensed drilling subcontractor, Preferred Drilling.

The wells will include one well at Area I onsite and three wells at offsite locations for the background study. The monitoring wells will be small diameter (micro) PVC wells installed by a direct-push rig. Each well will be completed to an estimated depth of 13 feet below

Tel 850.385.9899 Fax 850.385.9860 www.tetratech.com land surface. Actual well depths and screen placement will be determined based on lithology and depth to groundwater encountered in continuous core holes advanced at each well site. Well screens will be placed so that the upper 1/3 of the screen is above the water table. Each well will be constructed of 1-inch-diameter PVC casing with a 10-foot-long pre-packed well screen, with a fine sand seal above the well screen and will be completed in flush mount vaults embedded in concrete pads. After the wells are installed, they will be developed by pumping until the discharged water is clear. By using the direct push method for well installation, no drill cuttings will be generated as investigation-derived waste (IDW).

Development water will be allowed to infiltrate into the soil near the well sites. While onsite for well installation, the drill rig will be used to cut asphalt and underlying base material at the soil boring locations to be included in soil sampling.

� Soil sampling. Soil samples will be collected from 22 proposed boring locations described in Table 1. Soil samples will be collected from three depth intervals, 0-0.5 ft; 0.5 ft to 2 ft and 2 to 4 ft below land surface. Analysis of soil samples will be conducted for TRPH per Florida PRO and/or Arsenic per USEPA Method 6010 as described in Table 2. Specifics on soil sampling, including the analytical methods and quality assurance samples to be collected, will be detailed in the work plan. Soil sample aliquots for each of the depth intervals will be collected using pre-cleaned stainless-steel hand augers and homogenized in Pyrex bowls (or approved alternative) prior to transfer to sample containers. After sampling, excess soil will be returned to the boreholes and asphalt cold patch or concrete will be used to complete restoration in paved areas.

� Groundwater sampling. Existing and newly installed monitoring wells identified in Table 1 will be sampled under this subtask. Newly installed wells will be sampled after they have been developed and allowed to set for a minimum of 24 hours. Each well will be purged with a peristaltic pump and polyethylene tubing using low-flow sampling procedures and samples will be collected for laboratory analysis for Arsenic (per Method 6010) and other analytes (TRPH per Florida PRO or Ammonia per Method 350.2 and Nitrate per Method 353.2) as described in Table 1.

� In addition, Quality Assurance/Quality Control samples will be collected for analysis. These include field duplicates for both soil and groundwater (1 per 10 sample minimum), and equipment rinsate samples for both soil and groundwater sampling equipment (1 per 20 sample minimum). Temperature blanks will be carried in all coolers.

� A Trimble GeoXH hand-held global positioning system (GPS) will be used by Tetra Tech staff to survey latitude and longitude coordinates of the soil borings and monitoring wells.

In addition, all monitoring well tops of casings will be surveyed by Tetra Tech staff to a common onsite datum and at least one synoptic set of depth-to-groundwater measurements will be taken from all onsite and background monitoring wells.

� The field personnel conducting monitoring well installation and sampling activities will mobilize from the Tetra Tech Cocoa, FL office to minimize travel costs, commuting to the site from their home location for day trips to obtain right of way access and clear utilities and staying overnight for drilling and sampling activities. Level of effort for the Tallahassee-based Senior Scientist (Scientist V) to coordinate this subtask is 4 hours. Anticipated level of effort for the Cocoa-based Senior Scientist (Scientist IV), including utility location/permitting, equipment staging, field work and mobilization is 76 hours. Level of effort for a Tallahassee-based Staff Scientist to prepare the field task deliverable is 4 hours.

All staff are thoroughly trained and experienced in FDEP standard operating procedures for collection of soil and groundwater samples, documentation and reporting.

� Utility location, permitting and well installation and sampling activities should be completed in three mobilizations to the site, with drilling and sampling work anticipated to take approximately 1 week. The field task deliverable will be submitted to FDEP once field

Tel 850.385.9899 Fax 850.385.9860 www.tetratech.com notes, field sheets, site photos, chain of custody, shipping and laboratory receipt documentation are compiled.

Subtask 4 - Report: The level of effort assumes 2 hours for a Project Manager to review and seal the document, 4 hours for a Senior Scientist (Scientist V), 36 hours for a Staff Scientist, and 4 hours for figure preparation by a Staff GIS Specialist. Report tasks include preparation of draft and final reports documenting the field activities, site conditions, and results of the sampling effort. The report will adhere to the FDEP approved template for #-**'%(%),$' #&,% "++%++(%), Reports. It will include as appendix the detailed documentation and results of the assessment. The document will include a site location map, sampling location maps, a map showing direction of groundwater flow, and maps showing contaminant concentrations in soil and groundwater. The report will also contain tables of summary information for the groundwater and soil samples collected, monitoring well construction, depths to and relative elevations of groundwater, summary data from the laboratory analyses, and comparisons of analytical results to FDEP groundwater and soil cleanup target levels and background target levels. The report will also include an analysis of background concentrations and proposed background target concentrations for soil and groundwater. Appendices will also be provided that include the laboratory analytical data sheets, copies of field notes, groundwater sampling forms, field equipment calibration sheets, chain of custody forms, and photographs of the sampling sites.

Tetra Tech’s cost proposal is based on the following assumptions:

" Site access to enter the property and complete the indicated fieldwork will be obtained by

FDEP.

" Tetra Tech will obtain right of way permits for sample collection on public rights of way.

Permit fees, if required, are not yet determined and will be included in a change order request.

" FDEP may be requested to assist in coordinating access from local governments to public properties for background sampling.

" Soil and water samples will be analyzed by TestAmerica using rates included in Contract HW560 unless otherwise noted. Tetra Tech will coordinate the laboratory’s reservation and analysis.

" Electronic copies of all reports and field information (field notes, soil sample logs, groundwater sample logs, etc.) and laboratory results will be submitted to FDEP. Paper copies of reports and project deliverables will not be submitted.

" The field activities will be scheduled once the project work plan is approved by FDEP.

" The selected subcontractors provide the utility location and well installation services.

" IDW will not be containerized.

Tetra Tech is prepared to begin work on this project following receipt of a signed FDEP task order.

A signed task order will reflect the approval of this proposal and authorize use of associated funding required to commence project activities. The total fixed price cost to complete the activities described above is $36,372.08.

Please find a cost summary attached that provides details concerning this cost proposal. Tetra Tech anticipates completion of this project on a fixed price basis and will invoice costs incurred at 100% completion based on approval of deliverables and in accordance with deliverable due dates.

Tel 850.385.9899 Fax 850.385.9860 www.tetratech.com

Period of Performance Tetra Tech will schedule the site reconnaissance and begin work on the work plan upon receipt of the signed task assignment. Assuming no delays in conducting the site reconnaissance, the draft work plan will be submitted to FDEP within 21 days of task assignment and the subsequent field activities and subcontracted services will be scheduled as soon as the work plan is approved. Draft and final deliverables will be provided promptly after laboratory results are reported from the sampling event.

If you have any questions, please call myself or Richard Hicks (850) 385-9899.

Sincerely yours, Gerald Walker, P.G.

Brownfields Program Manager rh/GAW

Attachments c: Kelly Crain, FDEP Justin Cross, FDEP Richard Hicks, Tetra Tech Jay McGovern, Tetra Tech Tallahassee File FDEP Contract HW560

Figure 1. Site Features

B u il d in g n o lo n g e r p re s e n t

F is h e rm a n s

W h a rf

P a lm d a le

O il

C o m p a n y

G

C

I

E

B

D

A

H

F

J

³

JA

X C

G

IS

\M

IS

C

\K

IN

G M

A R

IT

IM

E \K

M F

IG

U

R E

S

IT

E

F

E A

T U

R E

S

B L

A N

K

R R

S

P U

R S

.M X

D

/0

/2

F e e t

L e g e n d

A p p ro x.

R a ilr o a d S p u r

L in e L o c a ti o n

A re a s o f F o cu s

P ro je ct

B o u n d a ry

S it e

F e a tu re s

P o rt o f

F o rt P ie rc e

(A K

A

F o rm e r K in g

M a ri ti m e G ro u p

S t.

L u c ie

C o u n ty

F lo ri d a

F

IG

U R

E N

U M

B E

RD

A

T E

D R

A W

N B

YP

R

O J E

C T

IC

J.

M

A D

D E

N

/0

/2

D A

T E

C H

E C

K E

D B

Y

R .H

IC

K

S

/0 /2

A e ri a l p ro vi d e d b y

E S

R I

W o rl d Im a g e ry

Tel 850.385.9899 Fax 850.385.9860 www.tetratech.com

Table 1. Sampling Objective and Proposed Activities

Table 1. Sampling Objective and Proposed Activities

Area Objective Activity Sample Summary B Complete delineation of

TRPH in soil and confirm Arsenic in groundwater

Advance 4 soil borings;

resample existing well

MW01

12 soil (TRPH, Arsenic); 1 GW (TRPH, As)

C Complete delineation of TRPH in soil and confirm Arsenic in groundwater

Advance 4 soil borings;

resample existing well

MW02

12 soil (TRPH); 1 GW (Arsenic)

D Confirm groundwater concentrations at former Ammonia detection location

Resample existing well

MW03

1 GW (Nitrate, Ammonia, Arsenic)

E Confirm Arsenic in groundwater

Resample existing well

MW04

1-GW (Arsenic)

G Confirm Arsenic in groundwater

Resample existing well

MW05

1-GW (Arsenic)

I Complete delineation of TRPH in soil; evaluate TRPH leachability, Arsenic in groundwater

Advance 2 soil borings;

install 1 new monitoring well at KMI-SS57 location

6 soil (TRPH); 1

GW (TRPH,

Arsenic)

J Confirm Arsenic in groundwater

Resample existing wells MW06, MW07, and MW23

3 GW (Arsenic)

Onsite Railroad Spur Lines

Explore potential Arsenic source locations

Advance 2 borings at former spur line locations on site

6-Soil (Arsenic)

Background Collect data to establish anthropogenic background Arsenic concentrations for soil and groundwater

Advance soil borings at 10 offsite locations; install new monitoring wells at 3 offsite locations

30-Soil (Arsenic); 3- GW (Arsenic)

Tel 850.385.9899 Fax 850.385.9860 www.tetratech.com

Attachment A

Contract HW560 Cost Estimate Spreadsheets and Backup Documentation

FDEP COST ESTIMATE

SITE :

SUBTASK 2: Phase II Work Plan

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager (GW) 1

Scientist V (RH) Tallahassee Office; Develop/review Work Plan [4]; Coordination, teleconference with staff, County and FDEP [3] 7

Scientist IV (CA) Site Recon to identify, mark proposed locations [8], coordinate with County, City and Derecktor on access to site and rights of way [4] 12

Scientist I (DH) Tallahassee Office; Work plan preparation, draft figures, text and tables [12] 12

Engineer I (MQ) Tallahassee Office; Revise, recertify HASP [2] 1

Staff GIS Specialist (JM) Jacksonville Office; Figure preparation, approximately 6 figures with proposed locations and previous results shown [2] 2

TOTAL LABOR 34

FIELD EXPENSES ITEM RATE COSTING UNIT USAGE TOTALS

Equipment

Hand Auger $8.25 Each 0 $0.00

Monitoring Well Installation Kit $184.30 Day 0 $0.00

Shallow Groundwater Sampling Kit $208.55 Day 0 $0.00

Expendables $32.50 Day 1 $32.50

Personal Protection (Level D) $28.00 Day 0 $0.00

Total GPS Station $141.65 Each 1 $141.65

TOTAL EQUIPMENT $174.15

VEHICLE TYPE RATE UNIT USAGE

Air Fare $0.00 Each 0 $0.00

Van/Truck $97.00 day 0 $0.00

Car $68.00 day 1 Cocoa to Ft. Pierce, 1 dy $68.00

Subtotal $68.00

Mileage Miles 0

TOTAL VEHICLE $68.00

PER DIEM STAFF RATE UNIT USAGE

MEALS

Scientist V (RH) $36.00 Day 0 $0.00

Engineer I (MQ) $36.00 Day 0 $0.00

HOTEL 0

Scientist V (RH) $120.00 Day 0 $0.00

Engineer I (MQ) $120.00 Day 0 $0.00

TOTAL PER DIEM $0.00

LABORATORY COSTS

PARAMETER Media Method RATE # SAMPLES #QAQC Analysis

Subtotal $0.00

Unit Cost Quantity

Sample Containers Lot $0.00 0 $0.00

Encore Samplers Each $8.75 0 $0.00

Sample Shipping Coolers $104.00 0 $0.00

Subtotal $0.00

TOTAL LAB $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST Units

TOTAL $0.00

Former King Maritime Group

Tallahassee Office; Review Work Plan [1]

SUBTASK 3: Fieldwork - Soil and Groundwater Assessment

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Scientist V (RH) Coordination with Subs, Review field work deliverable [2] 4

Scientist IV (CA) Cocoa Office; ROW permits [4]; Field work (mobs [3 times, 12], uti loc [8], soil borings/splng [20], GPS/TOC svy [4]; 76 well instal [6]; gw splng [12]; gw level meas in all mon wells [2]; field prep, documentation, shipping [4])

Scientist I (DH) Tallahassee office; Field deliverable prep [4] 4

Engineer I (MQ) 0

Staff GIS Specialist (JM) 0

TOTAL LABOR 84

FIELD EXPENSES ITEM RATE COSTING UNIT USAGE TOTALS

Equipment

Soil Assessment Kit $208.55 Day 2 $417.10

Monitoring Well Installation Kit $184.30 Day 1 $184.30

Shallow Groundwater Sampling Kit $208.55 Day 2 $417.10

Expendables $32.50 Day 5 $162.50

Personal Protection (Level D) $28.00 Per Person x Day 0 $0.00

Teflon Tubing (1/4-inch diameter) $1.95 Foot 0 $0.00

Total Survey Station $41.75 Each 1 $41.75

Peristaltic Pump $29.10 Each 1 Extra pump for well purging $29.10

Hammer Drill $50.95 Each $0.00

MiniRae 3000 PID $87.30 Each Included in MW and Soil kits $0.00

Total GPS Station $141.65 Each 1 Trimble GeoXH $141.65

TOTAL EQUIPMENT $1,393.50

VEHICLE TYPE RATE UNIT USAGE

Air Fare $0.00 Each 0 $0.00

Van/Truck $420.00 week 1 Staff from Cocoa for field work (6 days) $420.00

Car $68.00 day 2 Staff from Cocoa for utility location and ROW permitting $136.00

Subtotal $556.00

Mileage Miles 0

TOTAL VEHICLE $556.00

PER DIEM STAFF RATE UNIT USAGE

MEALS

Scientist V $36.00 Day 0 $0.00

Scientist IV (CA) $36.00 Day 5 $180.00

Engineer I $36.00 Day 0 $0.00

HOTEL

Scientist V $120.00 Day 0 $0.00

Scientist IV (CA) $120.00 Day 4 $480.00

Engineer I $120.00 Day 0 $0.00

TOTAL PER DIEM $660.00

LABORATORY COSTS

PARAMETER Media Method RATE # SAMPLES #QAQC Analysis

Metals Liquid 6010-As $11.50 12 4 QA includes 2 GW dup, GW EB, Soil EB $184.00

Nitrate Liquid 353.2 $20.00 1 2 QA includes GW dup, GW EB $60.00

Ammonia Liquid 350.2 $20.00 1 2 QA includes GW dup, GW EB $60.00

TRPH Liquid Florida PRO $84.00 2 5 QA includes 1 GW dup, 1 GW EB, 3 Soil EB $588.00

SVOC Liquid 8270 $100.00 $0.00

Mercury Liquid 7470 $23.00 $0.00

Pesticides Liquid 8081 $90.00 $0.00

Metals Soil 6010 -As $11.50 48 5 QA includes 6 soil dups $609.50

Metals Soil 6010- Pb $11.50 $0.00

Volatile Organics Soil 8260 $135.00 $0.00

TRPH Soil Florida PRO $84.00 30 3 QA includes 3 soil dups $2,772.00

SVOC Soil 8270 $100.00 $0.00

TRPH Fractionation (see note) Soil TPH-CWG $250.00 $0.00

Pesticides Soil 8081 $90.00 $0.00

Subtotal $4,273.50

Unit Cost Quantity

Sample Containers Lot $0.00 $0.00

Encore Samplers Each $8.75 $0.00

Sample Shipping Coolers $104.00 4 priority overnight shipping FedEx $416.00

Subtotal $416.00

Note: TRPH fractionation rate in attached lab quote. TOTAL LAB $4,689.50

SUBCONTRACTOR COSTS

NAME PURPOSE COST Units

Preferred Drilling Solutions Drilling $5,105.00 $5,105.00

GeoTek Utility Locate $1,500 1 $1,500.00

TOTAL $6,605.00

Former King Maritime Group

LEVEL OF EFFORT/EXPENSE WORKSHEET

SUBTASK 4: Report

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager (GW) Tallahassee Office; Document review and seal 2

Scientist V (RH) Tallahassee Office; Document review and editing 4

Scientist IV (CA)

Scientist I (DH) 36

Engineer I (MQ)

Staff GIS Specialist (JM) Jacksonville Office; Process GPS data, figure preparation 4

TOTAL LABOR 44

FIELD EXPENSES ITEM RATE COSTING UNIT USAGE TOTALS

Equipment

Hand Auger $8.25 Each 0 $0.00

Monitoring Well Installation Kit $184.30 Day 0 $0.00

Shallow Groundwater Sampling Kit $208.55 Day 0 $0.00

Expendables $32.50 Day 0 $0.00

Personal Protection (Level D) $28.00 Day 0 $0.00

Site Reconnaissance Kit $81.48 Each 0 $0.00

TOTAL EQUIPMENT $0.00

VEHICLE TYPE RATE UNIT USAGE

Air Fare $0.00 Each 0 $0.00

Van/Truck $97.00 day 0 $0.00

Car $68.00 day 0 $0.00

Subtotal $0.00

Mileage Miles 0

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USAGE

MEALS

Scientist V (RH) $36.00 Day 0 $0.00

Engineer I (MQ) $36.00 Day 0 $0.00

HOTEL

Scientist III (WO) $120.00 Day 0 $0.00

Engineer I (MQ) $120.00 Day 0 $0.00

TOTAL PER DIEM $0.00

LABORATORY COSTS

PARAMETER Media Method RATE # SAMPLES #QAQC Analysis

Volatiles Liquid 8260 $135.00 Standard Turn Around $0.00

Semivolatiles Liquid 8270 $100.00 Standard Turn Around $0.00

Pesticides Liquid 8081 $90.00 Standard Turn Around $0.00

Herbicides Liquid 8151 $150.00 Standard Turn Around $0.00

TRPH Liquid Florida PRO $84.00 Standard Turn Around $0.00

Lead Liquid 6010 $11.50 Standard Turn Around $0.00

Total Dissolved Fe and Mn Liquid 6010 $23.00 Standard Turn Around $0.00

COD Liquid SM5220 $25.00 Standard Turn Around $0.00

BOD (5 day) Liquid SM5210 $25.00 Standard Turn Around $0.00

Methane/CO2/02 Liquid 3810 $110.00 Standard Turn Around $0.00

In-line Filter (0.45 Micron) Each $17.50 $0.00

Subtotal $0.00

Unit Cost Quantity

Sample Containers Lot $0.00 0 $0.00

Encore Samplers Each $8.75 0 $0.00

Sample Shipping Coolers $104.00 0 $0.00

Subtotal $0.00

TOTAL LAB $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST Units

TOTAL $0.00

Former King Maritime Group

Compare onsite and offsite data, calculate background reference levels [20], report prep, tables and draft figs [16]

REV: 03/23/17 Page 2

04 October 2020

To: Richard Hicks Tetra Tech, Inc.

1558 Village Square Blvd., Suite 2 Tallahassee, FL 32309

From: GeoTek Services, LLC 4060 Sparrow Hawk Road

Melbourne, FL 32934

RE: Utility Locating Services – 26 Bore Locations, Port of Ft. Pierce, FL

Mr. Hicks, GeoTek Services is pleased to respond to your request for Utility Locating services at the Port of Ft. Pierce, Florida. We will scan a 10’ x 10’ area around the 26 proposed bore locations with the goal of locating underground utilities. We can only scan the easily accessible open areas for utilities. Note that we cannot scan beneath fixed objects such as vehicles, fencing, or buildings. We will scan as close as reasonably possible to fixed objects such as obstructions, landscaping, etc. Our deliverable will be marking paint and/or flags indicating the location of potential underground utilities. It is the client’s responsibility to protect and preserve all marks.

We will use both Electromagnetic Induction instruments as well as Ground Penetrating Radar (GPR) to detect objects below the surface. Due to the nature of sub-surface detection and the physical laws governing radio wave propagation, some buried objects may not be detectable due to depth, obscuration, or a weak radar signature. GeoTek Services will use industry standard best practices to locate sub-surface objects, however some objects may not be detectable. Geotek Services does not guarantee that all underground objects can be found. GeoTek Services assumes no liability for any damages.

We request access to any as-built site plans of the scan areas prior to rendering services. Our fixed price quote for this effort is $1,500.00. No out-of-pocket expenses are expected for this project. This quote is valid for sixty days.

Best Regards, Martin (Bud) Connor GeoTek Services, LLC

4060 Sparrow Hawk Road " Melbourne, FL 32934-8525 " info@GeoTekServices.com " 321.473.7498

REVISED

COST QUOTE FOR

DIRECT PUSH WELL INSTALLATION SUPPORT

FDEP Brownfields Site

King Maritime (AKA: Port of Fort Pierce) Phase 2

100 Terminal Drive

Fort Pierce, St. Lucie County, FL

BACKGROUND

Tetra Tech is requesting a cost quote for providing direct push services for the second phase of assessment work at an FDEP site in Fort Pierce, St. Lucie County, FL. The site is the historical Port of Fort

Pierce, which is owned by St. Lucie County and is being redeveloped. This is an industrial property, mostly covered by asphalt pavement, that includes scattered industrial buildings and warehouses. Level

D health and safety protocol should be followed. Tetra Tech representative will be on site to coordinate.

All site access will be obtained, and all utilities will be located via One Call by Tetra Tech and/or by a private utility locator in advance of subsurface work. Work will be conducted on the site and on nearby public rights of way. All sites are accessible to a track-mounted direct push rig. One of the soil boring locations is in a garage building with a concrete floor. Asphalt will need to be penetrated at most sites.

All work is shallow, with water table expected to be between 3 and 5 feet below land surface.

SCOPE OF WORK

The scope of work will include:

1- Installing 4 permanent monitoring wells and advance soil borings at 18 locations shown on the attached figures. Details include the following:

a. Post hole or auger each hole for well installation to confirm utility clearance.

b. Decontaminate casing and rods before and between well locations using liquinox and clean potable quality water. A source for decon water is available on site.

c. Advance a soil core hole at each well location, collecting soil samples continuously from

5 to 15 feet below land surface for description by Tetra Tech rep. Put cores back into hole.

d. Install 4 permanent wells. Each well will be constructed of 1-inch-diameter polyvinyl chloride (PVC) with a 10-foot-long, pre-packed, 0.006-inch slotted, PVC screen. A 30/45 grade sand filter pack will be installed to a height of 1 foot above the top of the screen through the direct push casing, followed by a 1-foot seal of fine 30/65 grade sand. The remaining annular space will be grouted to the surface. Each well will be an estimated

12 feet total depth. Use clean sand to fill the annular space around and above screens and top off with fine sealer sand. Add no water. Complete wells in flush mount manholes installed in 2x2 foot concrete pads. Install water-tight, lockable well caps.

e. Investigation derived waste does not need to be drummed. Put soil cores back into holes. Decontamination site will be on porous ground and rinsate can be allowed to soak into the ground. Remove all trash generated from your activities.

f. Develop each well by pumping for up to 1 hour or to the satisfaction of the onsite Tetra

Tech representative. Development water is to be spread on a nearby pervious surface to allow it to infiltrate into the soil.

g. Obtain all permits for well construction as appropriate.

h. Assist Tetra Tech field representative in collecting soil samples from 22 locations identified by Tetra Tech. Cut pavement and underlying base material using the probe rig’s asphalt/concrete cutting bit or a core drill, hand auger or use macro-core sampler to collect soil samples to a depth of approximately 4 feet below land surface at each location. After soil sampling, backfill holes and patch pavement (if penetrated) with concrete or asphalt patch as appropriate.

i. Tetra Tech will have each boring location cleared by a private utility locator in advance of doing the work.

2- Include mobilization and per diem costs as appropriate.

3- Drill crew members must have current health and safety training and medical monitoring, with documentation provided to the Tetra Tech project manager before mobilization.

4- Work anticipated to be performed in late November or early December, 2020.

Please provide a quote via email to Richard Hicks (Richard.Hicks@tetratech.com) by October 7, 2020 and email or call (850-509-2720) with questions.

DRILL QUOTE COMPARISON

Contractor Quoted Amount

Preferred Drilling Solutions $5105.00

Cascade Drilling $7130.00

Betts Drilling $8849.00

Recommended contractor is Preferred Drilling Solutions based on cost and past performance.

;O`QORS HSZSRWOaW\[ IS_cWQS` i .-/- I\baV 5/[R Ia_SSa i JOZ]O) >B 003.6 i '5.0( 3/3*.4.4

.* @[`aOYYW[U 1 ]S_ZO[S[a Z\[Wa\_W[U dSYY` Oa Y\QOaW\[` `V\d[ \[ aVS OaaOQVSR TWUb_S+ <SaOWY` W[QYbRS aVS T\YY\dW[U7

O+ F\`a V\YS \_ ObUS_ SOQV V\YS T\_ dSYY W[`aOYYOaW\[ a\ Q\[TW_Z baWYWaf QYSO_O[QS+

P+ <SQ\[aOZW[OaS QO`W[U O[R _\R` PST\_S O[R PSadSS[ dSYY Y\QOaW\[` b`W[U YW^bW[\e O[R QYSO[ ]\aOPYS ^bOYWaf dOaS_+ 9

`\b_QS T\_ RSQ\[ dOaS_ ZOf [\a PS OcOWYOPYS \[ `WaS+

Q+ 9RcO[QS O `\WY Q\_S V\YS Oa SOQV dSYY Y\QOaW\[) Q\YYSQaW[U `\WY `OZ]YS` Q\[aW[b\b`Yf T_\Z 2 a\ .2 TSSa PSY\d YO[R `b_TOQS

T\_ RS`Q_W]aW\[ Pf JSa_O JSQV _S]+ Fba Q\_S` POQX W[a\ V\YS+

R+ @[`aOYY 1 ]S_ZO[S[a dSYY`+ =OQV dSYY dWYY PS Q\[`a_bQaSR \T .*W[QV*RWOZSaS_ ]\YfcW[fY QVY\_WRS 'FL;( dWaV O .- T\\a*Y\[U)

]_S*]OQXSR) -+--3*W[QV `Y\aaSR) FL; `Q_SS[+ 9 0-,12 U_ORS `O[R TWYaS_ ]OQX dWYY PS W[`aOYYSR a\ O VSWUVa \T . T\\a OP\cS aVS a\] \T aVS `Q_SS[ aV_\bUV aVS RW_SQa ]b`V QO`W[U) T\YY\dSR Pf O .*T\\a `SOY \T TW[S 0-,32 U_ORS `O[R+ JVS _SZOW[W[U O[[bYO_

`]OQS dWYY PS U_\baSR a\ aVS `b_TOQS+ =OQV dSYY dWYY PS O[ S`aWZOaSR ./ TSSa a\aOY RS]aV+ K`S QYSO[ `O[R a\ TWYY aVS O[[bYO_

`]OQS O_\b[R O[R OP\cS `Q_SS[` O[R a\] \TT dWaV TW[S `SOYS_ `O[R+ 9RR [\ dOaS_+ ;\Z]YSaS dSYY` W[ TYb`V Z\b[a ZO[V\YS`

W[`aOYYSR W[ /e/ T\\a Q\[Q_SaS ]OR`+ @[`aOYY dOaS_*aWUVa) Y\QXOPYS dSYY QO]`+

S+ @[cS`aWUOaW\[ RS_WcSR dO`aS R\S` [\a [SSR a\ PS R_bZZSR+ Fba `\WY Q\_S` POQX W[a\ V\YS`+ <SQ\[aOZW[OaW\[ `WaS dWYY PS

\[ ]\_\b` U_\b[R O[R _W[`OaS QO[ PS OYY\dSR a\ `\OX W[a\ aVS U_\b[R+ HSZ\cS OYY a_O`V US[S_OaSR T_\Z f\b_ OQaWcWaWS`+

T+ <ScSY\] SOQV dSYY Pf ]bZ]W[U T\_ . V\b_ \_ a\ aVS `OaW`TOQaW\[ \T aVS \[`WaS JSa_O JSQV _S]_S`S[aOaWcS+ <ScSY\]ZS[a dOaS_ W` a\ PS `]_SOR \[ O [SO_Pf ]S_cW\b` `b_TOQS a\ OYY\d Wa a\ W[TWYa_OaS W[a\ aVS `\WY+

U+ @T dSYY Q\[`a_bQaW\[,OPO[R\[ZS[a ]S_ZWa` O_S _S^bW_SR) Wa dWYY PS [SQS``O_f T\_ aVS Q\[a_OQa\_ a\ _Sab_[ a\ aVS `WaS O[R

OPO[R\[ aVS dSYY` Pf a_SZWS U_\baW[U W[ OQQ\_RO[QS dWaV I>MC<,Ia+ BbQWS ;\b[af _S^bW_SZS[a`+

V+ EPaOW[ OYY ]S_ZWa` T\_ dSYY Q\[`a_bQaW\[,OPO[R\[ZS[a O` O]]_\]_WOaS+

/* ;ba ]OcSZS[a O[R b[RS_YfW[U PO`S ZOaS_WOY b`W[U aVS ]_\PS _WUh` O`]VOYa,Q\[Q_SaS QbaaW[U PWa \_ O Q\_S R_WYY a\ O RS]aV \T

O]]_\eWZOaSYf 1 T\\a Oa // Y\QOaW\[` WRS[aWTWSR Pf JSa_O JSQV \[`WaS _S]_S`S[aOaWcS+

O+ FS[Sa_OaS O`]VOYa \_ ]\``WPYf Q\[Q_SaS O[R b[RS_YfW[U PO`S ZOaS_WOY a\ Q_SOaS 0*0+2 W[QV RWOZSaS_ V\YS` aV_\bUV dVWQV

JSa_O JSQV QO[ Q\YYSQa `\WY `OZ]YS` b`W[U O VO[R ObUS_ Oa O YOaS_ aWZS+

P+ JSa_O JSQV dWYY TWYY O[R ]OaQV aVS V\YS` OTaS_ Q\YYSQaW[U `\WY `OZ]YS`+

Q+ JSa_O JSQV dWYY VOcS SOQV P\_W[U Y\QOaW\[ QYSO_SR Pf O ]_WcOaS baWYWaf Y\QOa\_ W[ ORcO[QS \T R\W[U aVS d\_X+

PPO_aYSf8QO`QORS*S[c+Q\Z=ZOWY:_\[`\[ :O_aYSfF_S]O_SR :f

<@H=;J@EDI

.-- JS_ZW[OY <_>\_a FWS_QS) >B

>\_a FWS_QS) >B 0162-

M\_X IWaS

JSa_O JSQV) @[Q+ * AW[U CO_WaWZS* >a) FWS_QS

><=F JSZ] MSYY` * <FJ * --.1.-51

E]]\_ab[Waf DOZS

.-,/,/-/- 372/ 9CGb\aS HScW`W\[

<OaS

---2/-10Gb\aS DbZPS_

/,/1,/-/-:WR <OaS

J=JJ=;//-N:WYY J\ 9QQ\b[a

DbZPS_

52-,052*6564FV\[S

_WQVO_R+VWQX`8aSa_OaSQV+Q\Z=ZOWY

HWQVO_R ?WQX`;\[aOQa DOZS

.1-. EcS[ FO_X <_WcS

JOYYOVO``SS) >Y\_WRO 0/0-5

9RR_S``

JSa_O JSQV) @[Q+9QQ\b[a DOZS

;O`QORS HS] ;\[aOQa @[T\_ZOaW\[

IQ\]S \T M\_X

F_\RbQa <S`Q_W]aW\[ GbO[aWaf K[Wa IOYS` F_WQS E]aW\[OY IbPa\aOY

C\PWYWgOaW\[,<SZ\PWYWgOaW\[ .+-- BbZ] IbZ #262+-- #262+--

/ FS_`\[ ;_Sd ']S_ RWSZ O[R Y\RUW[U( /+-- =OQV #0--+-- #3--+--

45// J_OQX) / FS_`\[ ;_Sd) /+-- <Of #.)52-+-- #0)4--+--

I\WY :\_W[U` ';\_W[U) IOZ]YS) :OQXTWYY % FOaQV( .0-+-- FS_ >a #0+2- #122+--

@[`aOYY MSYY * .") .-& F_SFOQX -+--3- 1+-- =OQV #.42+-- #4--+--

MSYY Q\Z]YSaW\[ * TYb`V Z\b[a cObYa) /&e/& ;\[Q_SaS ]OR 1+-- =OQV #//2+-- #6--+--

;O`QORS HSZSRWOaW\[ IS_cWQS` i .-/- I\baV 5/[R Ia_SSa i JOZ]O) >B 003.6 i '5.0( 3/3*.4.4

Cascade provides management of investigation derived waste. Call us today for information on a full range of additional options to meet your drilling needs.

Signature of Authorized Cascade Representative

Name & Title of Authorized Cascade Representative

Date

Signature of Client/ Owner Authorized Representative

Name & Title of Authorized Representative and Company

Date

This quote is based on information provided by you and is valid for 45 days from the bid date. Your firm is responsible for 1) Obtaining any site specific permits, 2) Locating and clearly marking underground installations or utilities, 3) Furnishing dig Alert numbers at least three working days prior to scheduled start date and proof of private locating services, 4) Obtaining access to site with no overhead wires within 20' of the holes. On-site soil disposal, unless Cascade expressly assumes responsibility in writing.Cascade shall not be responsible for damages to underground improvements not clearly and accurately marked.

If bedrock, cobbles, flowing sands or other adverse or unsafe drilling conditions are encountered, drilling may continue on a time and materials basis or be terminated at the discretion of Cascade. Additional costs may apply if scope is significantly changed. Prices assume standard labor rates and no work hour restrictions. Proposal is subject to final review of terms and conditions.

#4).0-+--Gb\aS J\aOY

#-+--JOeS`

-+----$JOe FS_QS[aOUS

#4).0-+--F_S*JOe J\aOY

MSYY <ScSY\]ZS[a) ]bZ]`) abPW[U) Q\[`bZOPYS` 1+-- =OQV #12+-- #.5-+--

EcS_aWZS 'EcS_ .- V\b_` \[`WaS( .+-- ]S_ V\b_ #/2-+-- #-+--

Cost Estimate Date

10/2/2020

Client

Tetra Tech Inc.

Richard Hicks

1558 Village Square Blvd., Ste 2

Tallahassee, Florida 32309

850-385-9897

(22) DPT Soil Borings to 15'bgs- Put cores back in holes and patch surfaces

(4) 1" x 12' MW's w/10' of .006" Prepacked screen- 8" Boltdown Completions- No Soil Sampling

Spread soils and waters

Wells are onsite and in right of way

Betts will hand auger or post hole the first 5' of all boring for utility clearance prior to drilling.

Betts is responsible for 811 utility locate call and maintaining an active locate ticket.

Client will provide access to well location as well as as-builts of the site

Payment terms are net 60 days from Betts invoice date.

Prices include a ten hour work day unless otherwise stated in this proposal

Unit QTY Unit Cost TOTAL

Mobilization of Rig/Crew Lump Sum 1 $1,250.00 $1,250.00

Drill Crew Per Diem (2 men) Day 4 $200.00 $800.00

Daily Rate: DPT Rig Per Day 3 $1,425.00 $4,275.00

Daily Rate: DPT Rig Per 1/2 day 1 $1,050.00 $1,050.00

1" Well materials Per Foot 48 $3.00 $144.00

1" x 5' .006" prepack screens Each 8 $75.00 $600.00

8" Boltdown Completions Each 4 $100.00 $400.00

Well Development (Up to 1 hr per well) Each 4 $75.00 Included

Drums (Includes Staging) Each 0 $60.00 $0.00

Well Permits- Wells (St Lucie Co DOEH) Each 1 $100.00 $100.00

Well Permits- Wells (St Lucie Co DOEH) Each 1 $230.00 $230.00

Total $8,849.00

Thank you for this opportunity

David Boggs

Sr. Project Manager/Safety Specialist

Orlando, Florida

407-493-9763

DESCRIPTION

Completion - 3-3.5 Days onsite plus travel

Estimate No.

Site Information

Corporate Office - 361 Airport Square, Adel, GA 31620

Scope of Work

FL1020001.rev

Fort Pierce, Florida

100 Terminal Drive

Assist Tetra Tech in taking soil samples from (22) locations to ~4-5'bgs

King Maritime - Port of Ft. Pierce

DPT Soil Sampling & Well Installations

File details come from the government source that posted it. Updated .