This is a Task Assignment Notification Form issued by the Florida Department of Environmental Protection (FDEP) under Contract HW558 with Earth Systems, a contractor providing environmental engineering services. The task assignment, designated DC002L, authorizes work at the Extra Mile Cleaners site (ERIC_4527) located at 5111 Baymeadows Road #13 in Jacksonville, Duval County, Florida. The assignment was executed on December 9, 2020, with DEP Contract Manager Killian Talley overseeing the engagement.
Earth Systems is authorized to conduct annual groundwater monitoring activities consisting of two subtasks: Project Management and Annual Natural Attenuation Monitoring (NAM) Sampling and Reporting for the 2021 calendar year. Work includes collecting water level data from five monitoring wells, collecting groundwater samples from seven additional wells, analyzing samples for volatile organic compounds via EPA Method 8260B, and preparing a comprehensive Natural Attenuation Monitoring Report with updated tables, figures, analytical data, and recommendations. The total task assignment value is $4,971.92, comprised of $427.87 for Project Management and $4,544.05 for NAM Sampling. The assignment utilizes a Fixed Price compensation structure with no retainage. The deliverable—a Natural Attenuation Monitoring Report and GIS/ADaPT documentation—is due June 30, 2021, with final project completion by August 31, 2021. Payment is contingent upon FDEP receipt and approval of the deliverables, which encompass 39 total labor hours and associated field, laboratory, and equipment costs.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO.
Task Assignment #: Module #: Grant #:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
DEP Site #:
Site Name:
Address(Street, City, County):
Phase:
Task Description [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverables:
Final Deliverable Due Date:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
FIXED FEE
RETAINAGE:
TOTAL TASK ASSIGNMENT VALUE: $0.00
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93)
Section Representative ________
TASK ASSIGNMENT NOTIFICATION FORM
COST PLUS FIXED FEE
COST REIMBURSEMENT
FIXED PRICE FEE SCHEDULE
Period of Performance:
Execution of Task Assignment through:
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
WCP TAFORM 01_18
HW558
D000 N/ADC002L
Earth Systems
Jim Paxton
850-245-8928Killian Talley
ERIC_4527
Extra Mile Cleaners
5111 Baymeadows Road #13, Jacksonville, Duval
Monitoring
This Task Assignment authorizes Earth Systems to conduct annual groundwater monitoring activities in accordance with the attached scope of work and cost estimate.
Natural Attenuation Monitoring Report; GIS/ADaPT
06/30/2021
09/24/2021
$ 4,971.92 $ 0.00 $ 0.00 $ 0.00
$ 0.00
Killian Talley Digitally signed by Killian Talley Date: 2020.12.09 15:01:35 -05'00'
Killian Talley Digitally signed by Killian Talley Date: 2020.12.09 15:01:44 -05'00'
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2020.12.09 15:27:05 -05'00'
Mark A. Tumeo Digitally signed by Mark A. Tumeo Date: 2020.12.11 14:06:20 -05'00'
$ 4,971.92
Task Assignment Notification/Change Order
Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Subtasks 1-2: Submittal of Natural Attenuation Monitoring Report; GIS/ADaPT 06/30/2021
Subtasks 1-2: FDEP receipt and approval of Natural Attenuation Monitoring Report;
GIS/ADaPT $ 4,971.92
$ 4,971.92
HW558
DC002L
Florida Department of Memorandum Environmental Protection
Printed on recycled paper.
To:
From:
Date:
HW558 Contract Negotiation File Extra Mile Cleaners Jacksonville, Duval County
ERIC_4527
Killian Talley, Project Manager December 9, 2020
Subject: Negotiation Summary
HW558 DC002L
Task Assignment authorizes Earth Systems to conduct annual groundwater monitoring at the Moses Cleaners site.
Subtask 1: Project Management An automatic calculation based upon total direct labor hours determines the labor hours within this subtask.
Subtask 2: Annual NAM Sampling & Reporting Subtask includes costs and labor for Earth Systems to conduct groundwater sampling along with analysis and reporting. Field event will be comprised of the following activities; collection of depth to water will be measured from site monitoring wells, field parameters for geochemical data, and seven (7) groundwater samples for analysis of volatile organic compounds via EPA Method 8260B. Upon receipt of the groundwater analytical data, Earth Systems will generate an Natural Attenuation Monitoring Report outlining and describing the field event, procedures, and analytical results. The report will also provide conclusion and recommendations.
The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost for this Task Assignment is $4,971.92 with 39 labor hours.
Earth Systems may invoice following the schedule established in the Deliverables and Invoice Schedule Attachment, which accompanies the Task Assignment Notification Form.
FDEP COST ESTI MATEContractor: Earth Systems
Date: 12/9/2020
Task #: SubTask 1 Project Management SubTask 6
Site: Former Extra Mile Cleane SubTask 2 Annual MNA Sampling 2021 SubTask 7
Activity/Phase: Annual NAM - 2021 SubTask 3 SubTask 8
Project Manager: Killian Talley SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$40.62 Project Manager (Paxton) 4 3.6 $42.30 Principal Manager (M Tumeo) 3 3 0 0 0 0 0 0 0 0 $30.80 Associate Eng./Geologist/Scientist 0 0 0 0 0 0 0 0 0 0 $42.30 Senior Engineer 0 0 0 0 0 0 0 0 0 0 $40.62 Senior Scientist (J Paxton) 18 18 0 0 0 0 0 0 0 0 $26.15 Field Geologist (L. Russell) 1 1.0 0 0 0 0 0 0 0 0 $23.02 Senior Technician (T. Byrnes) 10 10 0 0 0 0 0 0 0 0 $17.60 Eng./Geologist/Scientist Technician 0 0 0 0 0 0 0 0 0 0 $18.00 Technician/Draftsperson II (K. Morse) 2 2 0 0 0 0 0 0 0 0 $12.75 Technician/Draftsperson I 0 0 0 0 0 0 0 0 0 0 $17.00 Administrative Assistant (S. Meserve) 1 1 0 0 0 0 0 0 0 0
$0.00 General Office Clerk 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0
Total Hours 39 4 35.0 0 0 0 0 0 0 0 0
Direct Labor $1,313.34 $145.93 $1,167.41 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 63.00% $827.41 $91.94 $735.47 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 65.00% $853.67 $94.85 $758.82 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 34.00% $446.54 $49.62 $396.92 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $3,440.96 $382.34 $3,058.62 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Other Direct Costs $65.67 $7.30 $58.37 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Travel
Cost Estimate
FDEP COST ESTI MATEContractor: Earth Systems
Date: 12/9/2020
Task #: SubTask 1 Project Management SubTask 6
Site: Former Extra Mile Cleane SubTask 2 Annual MNA Sampling 2021 SubTask 7
Activity/Phase: Annual NAM - 2021 SubTask 3 SubTask 8
Project Manager: Killian Talley SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Vehicle Rental $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $528.00 $528.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $528.00 $528.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $32.50 $32.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $114.50 $114.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $349.20 $349.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $496.20 $496.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $4,627.83 $389.64 $4,238.19 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $344.09 $38.23 $305.86 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $4,971.92 $427.87 $4,544.05 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cost Estimate
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Extra Mile Cleaners SUBTASK: Annual MNA 2020
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Terry Byrnes - Sr. Tech. Travel time to and from site 1
WLs (MW005, 011, 014, 019) & Sample 7 additional wells, MW020, MW008 9 three intermediate (MW010, MW018, MW013), and two deep (MW017 and MW012) plus Trip Blank.
Analyses for VOHs via 8260C. Purge water treated and disposedon-site as non-haz per generator's knowled
Report:
M. Tumeo - Senior Eng. Annual MNA report review 3
J. Paxton - Senior Scientist Annual MNA report preparation 18
L. Russell - Field Geologist ADaPT (8 mins/well * 7 wells) 1
S. Meserve - Admin Compiling PDF of MNA report, printing and shipping hard copy 1
Kath Morse - Drafting Figures 1-4 2
TOTAL LABOR 35.0
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Deep GW sampling kit $349.20 day 1 $349.20
Portable Compressor $48.50 day 1 $48.50
Expendables $32.50 day 1 $32.50
Portable Generator $66.00 day 1 $66.00
TOTAL EQUIPMENT $496.20
VEHICLE TYPE RATE UNIT USEAGE
Truck $97.00 day 1 $97.00
TOTAL VEHICLE $97.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
7 MWs, 1 TB, VOH by 8260B $66.00 7 1 $528.00
TOTAL LAB $528.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
12/9/2020
LOE WORKSHEET
223 12th Avenue North, Jacksonville Beach, Florida 32250, Tel 904.247.0740, Fax 904.247.7650
Florida • Colorado • North Dakota • New Jersey
December 4, 2020
Mr. Killian Talley Bureau of Waste Cleanup Division of Waste Management Florida Department of Environmental Protection 2600 Blair Stone Road, M. S. 4520 Tallahassee, Florida 32399-2400
Subject: Proposal to Conduct NAM Sampling- 2021 Extra Mile Cleaners 5111 Baymeadows Road #13, Jacksonville, Florida
ERIC_4527
Dear Mr. Talley:
Earth Systems has prepared this proposal for conducting annual Natural Attenuation Monitoring (NAM) sampling at the subject site. The sampling plan is based on the 20120 MNA recommendations, FDEP’s July 7, 2020 approval memo, The tasks associated with this scope of work are as follows:
SUBTASK 1 – Project Management
Allowable costs for Project Management according to the Bureau of Waste Cleanup’s (BWC) contract with Earth Systems.
SUBTASK 2 – Annual NAM Sampling and Reporting
Earth Systems will mobilize a senior technician to the site to collect water level data from 5 wells (MW005, MW010, MW011, MW014, and MW019) and groundwater samples (with water level data) from 7 additional wells, MW020, MW008, MW010, MW012, MW013, MW017, and MW018. The samples will be analyzed for VOHs using EPA Method 8260.
One trip blank will also be analyzed. All VOH samples will be analyzed by one of Earth Systems’ contract laboratories, Pace Analytical or Accutest.
After receipt of the analytical results, Earth Systems will provide a Natural Attenuation Monitoring Report. The report will include updated tables and figures, the laboratory analytical data, and recommendations for additional work.
Proposal to Conduct Annual NAM Sampling - 2021 Extra Mile Cleaners, Jacksonville, Florida
ERIC_4527
Task Proposed
Cost Proposed Schedule/Deliverables
Subtask 1 – Project Management $427.87
August 31, 2021
Subtask 2 – 2021 NAM Sampling $4,544.05 June 30, 2021 Submittal of NAM Report
Total/Completion Date $4,971.92
August 31, 2021
If you have questions or comments concerning this proposal, please contact me at (904) 247-0740.
Sincerely, James Paxton Operations Manager