This document is a Task Assignment Notification Form (DC002J) issued under DEP Contract No. HW558 by the Florida Department of Environmental Protection (FDEP). The contract involves Earth Systems Inc, a contractor based in Jacksonville Beach, Florida, with Jim Paxton serving as the contractor representative. The work is being performed at the Extra Mile Cleaners facility located at 5111 Baymeadows Road #13, Jacksonville, Duval County, Florida (FDEP Site ERIC_4527). Crystal Posey serves as the FDEP Project Manager and Contract Manager overseeing this task assignment.

The task assignment authorizes Earth Systems to conduct additional groundwater sampling from two monitoring wells (MW012 and MW018) and analysis for volatile organic hydrocarbons (VOHs) using EPA Method 8260 to verify May 2019 monitored natural attenuation (MNA) results. The scope of work consists of two subtasks: Subtask 1 (Project Management) at a cost of $220.54 and Subtask 2 (2019 NAM Sampling and Reporting) at a cost of $2,414.82, for a total fixed-price task assignment value of $2,635.36. The final deliverable is a 2019 Groundwater Sampling Report including updated tables and figures, laboratory analytical data, and recommendations for additional work. The report submittal deadline is January 31, 2020, with the task execution period ending March 31, 2020. The cost estimate includes direct labor, overhead, general and administrative costs, fringe benefits, travel expenses, laboratory analytical costs, field equipment, and a completion fee, with no retainage or cost reimbursement components.

View the file

Other files

File Type Posted
CN-370000-HW558-A3.pdf PDF
CN-370000-HW558-A5.pdf PDF
CN-370000-HW558-A7.pdf PDF
CN-370000-HW558-CO2.pdf PDF
CN-370000-HW558-DC001G.pdf PDF
CN-370000-HW558-DC005G.pdf PDF
CN-370000-HW558-DC005i.pdf PDF
CN-370000-HW558-DC012FCO.pdf PDF
CN-370000-HW558-DC013F.pdf PDF
CN-370000-HW558-DC017E.pdf PDF
CN-370000-HW558-DC017F.pdf PDF
CN-370000-HW558-DC017H.pdf PDF
CN-370000-HW558-DC018C.pdf PDF
CN-370000-HW558-DC019F.pdf PDF
CN-370000-HW558-DC019H.pdf PDF
CN-370000-HW558-DC01ACO4.pdf PDF
CN-370000-HW558-DC01E.pdf PDF
CN-370000-HW558-DC01F.pdf PDF
CN-370000-HW558-DC022D.pdf PDF
CN-370000-HW558-DC023F.pdf PDF
CN-370000-HW558-DC025B.pdf PDF
CN-370000-HW558-DC027G.pdf PDF
CN-370000-HW558-DC028A.pdf PDF
CN-370000-HW558-DC028F.pdf PDF
CN-370000-HW558-DC02C.pdf PDF
CN-370000-HW558-DC02E.pdf PDF
CN-370000-HW558-DC02EC01.pdf PDF
CN-370000-HW558-DC02L.pdf PDF
CN-370000-HW558-DC03J.pdf PDF
CN-370000-HW558-DC03L.pdf PDF
CN-370000-HW558-DC04G.pdf PDF
CN-370000-HW558-DC04J.pdf PDF
CN-370000-HW558-DC04L.pdf PDF
CN-370000-HW558-DC04MCO1.pdf PDF
CN-370000-HW558-DC05C.pdf PDF
CN-370000-HW558-DC08ECO1.pdf PDF
CN-370000-HW558-DC09GCO1.pdf PDF
CN-370000-HW558-DC09H.pdf PDF
CN-370000-HW558-DC09I.pdf PDF
CN-370000-HW558-DC09ICO1.pdf PDF
CN-370000-HW558-DC09ICO2.pdf PDF
CN-370000-HW558-DC10E.pdf PDF
CN-370000-HW558-DC11G.pdf PDF
CN-370000-HW558-DC11GCO1.pdf PDF
CN-370000-HW558-DC11GCO2.pdf PDF
CN-370000-HW558-DC11H.pdf PDF
CN-370000-HW558-DC11J.pdf PDF
CN-370000-HW558-DC11MCO1.pdf PDF
CN-370000-HW558-DC11oCO1.pdf PDF
CN-370000-HW558-DC12B.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Task Assignment #: DC002J Module #: D000 Grant #: N/A Contractor Name:

Contractor Representative:

DEP Contract Manager: Phone #: 850-245-8851 DEP Site #:

Site Name:

Address(Street, City, County):

Phase:

Task Description [use additional pages if necessary]:

The Deliverable and Invoice Schedule is attached.

Final Deliverables:

Final Deliverable Due Date:

3/31/2020

TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:

FIXED FEE

$0.00 $0.00

RETAINAGE: $0.00

TOTAL TASK ASSIGNMENT VALUE: $2,635.36

DEP Task Manager: Date:

DEP Contract Manager: Date:

Contractual Authority: Date:

Contractor Representative: Date:

CC: Procurement Section (MS 93) Section Representative ________

$2,635.36 $0.00

DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).

COST REIMBURSEMENT

FIXED PRICE FEE SCHEDULE

2019 Groundwater Sampling Report

Period of Performance:

Execution of Task Assignment through:

5111 Baymeadows Road #13 Jacksonville, Duval County, FL

MNA

1/31/2020

COST PLUS FIXED FEE

TASK ASSIGNMENT NOTIFICATION FORM

DEP CONTRACT NO. HW558

Earth Systems Inc Jim Paxton Crystal Posey

ERIC_4527

Extra Mile Cleaners

This Task Assignment authorizes additional groundwater sampling, as requested in the attached Earth memo, dated September 27, 2019.

WCP TAFORM 01_18

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number: HW558 Task Assignment #: DC002J

Deliverables:

Deliverable Deliverable Due Date

2019 Groundwater Sampling Report (submittal electronically and hardcopy) 31-Jan-20

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced Subtask 1 and 2: FDEP approval of 2019 Groundwater Sampling Report (submittal electronically and hardcopy) $2,635.36

TOTAL COST $2,635.36

BWC TAFORM 01/18

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Noah Valenstein Secretary

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 3

2399-2400

Memorandum

TO:

FROM:

SUBJECT:

DATE:

HW558 Contract File

Crystal Posey, Project Manager

Extra Mile Cleaners

ERIC_4527

HW558 DC002J

Task Assignment

October 30, 2019

This Task Assignment authorizes Earth Systems to conduct groundwater sampling (with water level data) from two wells (MW012 and MW018) and will be analyzed for VOHs using EPA Method 8260 to verify the May 2019 MNA results, at the request of the Department during the annual review meeting on September 26, 2019.

Earth Systems will provide a Groundwater Sampling Report with updated tables and figures, the laboratory analytical data, and recommendations for additional work. This Task Assignment is in accordance with the Earth Systems proposed scope of work and cost estimate form attached and dated September 27, 2019.

The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment, total task amount is $2,635.36.

223 12th Avenue North, Jacksonville Beach, Florida 32250, Tel 904.247.0740, Fax 904.247.7650

Florida • Colorado • North Dakota • New Jersey

September 27, 2019

Ms. Crystal Posey Bureau of Waste Cleanup Division of Waste Management Florida Department of Environmental Protection 2600 Blair Stone Road, M. S. 4520 Tallahassee, Florida 32399-2400

Subject: Proposal to conduct Groundwater Sampling- November 2019 Extra Mile Cleaners 5111 Baymeadows Road #13, Jacksonville, Florida FDEP Facility ERIC_4527

Dear Ms. Posey:

Earth Systems has prepared this proposal for conducting groundwater sampling at the subject site. The additional groundwater sampling scope was requested during Earth Systems contractor review meeting on September 26, 2019. The tasks associated with this scope of work are as follows:

SUBTASK 1 – Project Management

Allowable costs for Project Management according to the Bureau of Waste Cleanup’s (BWC) contract with Earth Systems.

SUBTASK 2 – Annual NAM Sampling and Reporting

In November 2019, Earth Systems will mobilize a senior technician to the site to collect groundwater samples (with water level data) from two wells (MW012 and MW018) to verify the May 2019 MNA results. The samples will be analyzed for VOHs using EPA Method 8260. One trip blank will also be analyzed. All VOH samples will be analyzed by one of Earth Systems’ contract laboratories, Pace Analytical or Accutest.

After receipt of the analytical results, Earth Systems will provide a Groundwater Sampling Report. The report will include updated tables and figures, the laboratory analytical data, and recommendations for additional work.

Proposal to Conduct GWS Sampling – November 2019 Extra Mile Cleaners, Jacksonville, Florida

ERIC_4527

Task Proposed

Cost Proposed Schedule/Deliverables

Subtask 1 – Project Management $220.54 March 30, 2020

Subtask 2 – 2019 NAM Sampling $2,414.82 January 31, 2020 Submittal of NAM Report

Total/Completion Date $2,635.36 March 30, 2020

If you have questions or comments concerning this proposal, please contact me at (904) 247-0740.

Sincerely, James Paxton Operations Manager

GROUNDWATER ANALYTICAL

RESULTS

(MARCH 2012 - MAY 2019)

Figure 2

LEGEND

N

0 8040

( SCALE IN FEET )

FORMER EXTRA

MILE CLEANERS

BOLD

14.8

11.2 14.9

CEs >GCTLs

8.7

4.00

4.7

79.3

5.0 4.2

5.9

Luke Text Box 3.0

Jim Highlight

Jim Highlight

Jim Highlight

Jim Highlight

Jim Highlight

FDEP COST ESTIMATEContractor: Earth Systems

Date: 10/30/2019

Task #: SubTask 1 Project Management SubTask 6

Site: Extra Mile Cleaners SubTask 2 GW Sampling 2019 SubTask 7

Activity/Phase: GWS - November 2019 SubTask 3 SubTask 8

Project Manager: Crystal Posey SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$40.62 Project Manager (Paxton) 2 1.9 $42.30 Principal Manager (G Beardall) 1 1 0 0 0 0 0 0 0 0 $30.80 Associate Eng./Geologist/Scientist 0 0 0 0 0 0 0 0 0 0 $42.30 Senior Engineer 0 0 0 0 0 0 0 0 0 0 $40.62 Senior Scientist (J Paxton) 10 10 0 0 0 0 0 0 0 0 $26.15 Field Geologist (L. Russell) 1 1.0 0 0 0 0 0 0 0 0 $23.02 Senior Technician (T. Byrnes) 4 4 0 0 0 0 0 0 0 0 $17.60 Eng./Geologist/Scientist Technician 0 0 0 0 0 0 0 0 0 0 $18.00 Technician/Draftsperson II (K. Morse) 1 1 0 0 0 0 0 0 0 0 $12.75 Technician/Draftsperson I 0 0 0 0 0 0 0 0 0 0 $17.00 Administrative Assistant (S. Meserve) 1 1 0 0 0 0 0 0 0 0

$0.00 General Office Clerk 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 20 2 18.0 0 0 0 0 0 0 0 0

Direct Labor $676.95 $75.22 $601.73 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 63.00% $426.48 $47.39 $379.09 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 65.00% $440.01 $48.89 $391.12 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 34.00% $230.16 $25.57 $204.59 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $1,773.60 $197.07 $1,576.53 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Other Direct Costs $33.85 $3.76 $30.09 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Travel

Cost Estimate

FDEP COST ESTIMATEContractor: Earth Systems

Date: 10/30/2019

Task #: SubTask 1 Project Management SubTask 6

Site: Extra Mile Cleaners SubTask 2 GW Sampling 2019 SubTask 7

Activity/Phase: GWS - November 2019 SubTask 3 SubTask 8

Project Manager: Crystal Posey SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Vehicle Rental $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $198.00 $198.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $198.00 $198.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $32.50 $32.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $114.50 $114.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $208.55 $208.55 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $355.55 $355.55 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $2,458.00 $200.83 $2,257.17 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $177.36 $19.71 $157.65 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $2,635.36 $220.54 $2,414.82 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Cost Estimate

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Extra Mile Cleaners SUBTASK: 2 GW Sampling

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Terry Byrnes - Sr. Tech. Travel time to and from site 1 GW samples from 2 wells MW012 and MW018 plus Trip Blank. Analyses for VOHs via 8260 3 Purge water treated and disposed on-site as non-haz per generator's knowledge.

Report:

G. Beardall - Senior Eng. GWS report review 1 J. Paxton - Senior Scientist GWS report preparation with recommendations 10 L. Russell - Field Geologist ADaPT (8 mins/well * 2 wells) 1 S. Meserve - Admin Compiling PDF of MNA report, printing and shipping hard copy 1 Kath Morse - Drafting Figures 1-4 1

TOTAL LABOR 18.0

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Shallow GW sampling kit $208.55 day 1 $208.55 Portable Compressor $48.50 day 1 $48.50 Expendables $32.50 day 1 $32.50 Portable Generator $66.00 day 1 $66.00

TOTAL EQUIPMENT $355.55

VEHICLE TYPE RATE UNIT USEAGE

Truck $97.00 day 1 $97.00

TOTAL VEHICLE $97.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

2 MWs, 1 TB, VOH by 8260B $66.00 2 1 $198.00

TOTAL LAB $198.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

TOTAL $0.00

10/30/2019

LOE WORKSHEET

Task Assignment Notification
Deliverable & Invoice Schedule

File details come from the government source that posted it. Updated .