CN-370000-HW553-CSS-17A.pdf
PDF 1 MB Posted
- Contract number
- HW553
- Issued by
- Florida
About this file
Document Summary
This is a Task Assignment Notification Form (TA CSS-17A) under Florida Department of Environmental Protection (FDEP) Contract HW553 with Ecology and Environment, Inc. (E&E), a contractor providing environmental consulting services. The task assignment is for Site Inspection (SI) activities at the Pensacola Iron Triangle site (COM_303255) located at 3241 N Palafox Street in Pensacola, Escambia County, Florida. The work is being conducted in accordance with the U.S. EPA Superfund State Political Subdivision and Indian Tribe Site Specific Cooperative Agreement (No. 00D57717), administered by FDEP. The DEP Contract Manager is Carrie Kruchell, P.G., and the contractor representative is Stephen Elliot.
The task assignment encompasses four subtasks with a fixed price total of $22,810.83. Subtask 1 (Project Management) is $2,113.77 and includes 12.5% of direct labor costs; Subtask 2 (SI Work Plan Package) is $3,589.92 and covers preparation of a work plan, Quality Assurance Project Plan, and Health and Safety Plan; Subtask 3 (SI Field Activities) is $11,722.24 and includes utility locates, XRF screening, soil and groundwater sampling, and onsite data management; and Subtask 4 (SI Report) is $5,384.90 for the final Site Inspection Report. The period of performance extends through November 2, 2018, with deliverables due by September 3, 2018. Invoicing occurs upon completion of each subtask on a net 30-day payment term, with no retainage or additional fees beyond the fixed price amount.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
www.dep.state.fl.us
Florida Department of Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, Florida 32399-2400
Rick Scott Governor
Carlos Lopez-Cantera
Lt. Governor
Noah Valenstein Secretary
TO: Ecology and Environment, Inc., HW553 Contract File CERCLA Site Screening
FROM: Carrie L. Kruchell, P.G., Contract Manager
DATE: June 7, 2018
SUBJECT: Negotiation Summary – Task Assignment (TA) CSS-17A
Pensacola Iron Triangle, COM_303255 Pensacola, Escambia Co.
Site Inspection (SI) Phase
The Scope of Work (SOW) for this TA as agreed by both DEP and Ecology and Environment, Inc. (E & E), is to perform Site Inspection (SI) activities at the above referenced site, in accordance with the U.S. EPA Superfund State Political Subdivision and Indian Tribe Site Specific Cooperative Agreement (No. 00D57717), administered by
DEP.
Subtask 1: Project Management This subtask is for project management and includes a percentage of the overall project fees and has been negotiated as a contract rate. The agreed upon cost of this subtask is $2,113.77.
Subtask 2: SI Work Plan Package This subtask includes the completion of a SI Work Plan and Health and Safety Plan and set up of the U.S. EPA Scribe tables to be used for the sampling event. The agreed upon cost of this subtask is $3,589.92.
Subtask 3: SI Field Activities This subtask covers labor and subcontractor costs for the utility locates, XRF screening, soil and groundwater sampling, and onsite data management. Deliverables of this subtask include field notes, monitoring well sampling logs, chain of custody, XRF screening logs, and photographic log from the SI activities. The agreed upon cost of this subtask is $11,722.24.
Subtask 4: SI Report This subtask is for the final deliverable SI report. This SI report will document field and laboratory findings and will include maps showing the site and sampling locations, contaminant concentrations in soil and groundwater, and tables documenting data from the laboratory analyses, depths to and relative elevations of groundwater, and analytical results. The agreed upon cost of this subtask is $5,384.90.
www.dep.state.fl.us
Summary The FDEP Contract Manager agrees to the SOW and final cost. The final cost associated with this Task Assignment is $22,810.83. Documentation of these costs is included in the Level of Effort/Cost Estimate Form and cover letter provided by E & E on June 6, 2018, as well as the Task Assignment Form for CSS-17A prepared by DEP.
FDEP Contract HW553 Cost Estimate
Contractor:
Date:
Task #: CSS-17A SubTask 1 Project Management (12.5% of direct labor costs) Site: SubTask 2 SI Work Plan Package
Site ID #: SubTask 3 SI Field Activities Activity/Phase: SubTask 4 SI Report
Project Manager: SubTask 5
10OHBOA.3077.G5
Labor Rate Category Totals 1 2 3 4 5
$47.79 PM 12.5% of direct labor costs 14.5 14.510 Principal
$47.79 Kelso 4.0 1.0 1.0 2.0 0.0 $60.17 Brown 0.0 0.0 0.0 0.0 0.0
Chief $39.08 Werth 0.0 0.0 0.0 0.0 0.0 $39.25 Moore 0.0 0.0 0.0 0.0 0.0 $40.15 Ringo 0.0 0.0 0.0 0.0 0.0 $41.93 Long 0.0 0.0 0.0 0.0 0.0 $42.68 Hansen 0.0 0.0 0.0 0.0 0.0
Senior $32.99 Krajewski 0.0 0.0 0.0 0.0 0.0 $35.23 Jacobs 0.0 0.0 0.0 0.0 0.0 $36.85 Eucogno 8.0 2.0 0.0 6.0 0.0 $37.82 Elliott 80.0 24.0 32.0 24.0 0.0 $38.40 Casey 0.0 0.0 0.0 0.0 0.0 $39.09 Guerrero 0.0 0.0 0.0 0.0 0.0
Associate $23.08 Oien 38.0 4.0 34.0 0.0 0.0 $24.84 Witherington 0.0 0.0 0.0 0.0 0.0 $25.63 Percifull 0.0 0.0 0.0 0.0 0.0 $28.09 Fowler 8.0 2.0 0.0 6.0 0.0 $28.09 Hammond 0.0 0.0 0.0 0.0 0.0
Junior $22.84 Marks 0.0 0.0 0.0 0.0 0.0 $23.35 Jeter 40.0 0.0 24.0 16.0 0.0 $24.47 Bender 0.0 0.0 0.0 0.0 0.0
Technician $18.72 N/A 0.0 0.0 0.0 0.0 0.0
Clerical $16.00 Williams 0.0 0.0 0.0 0.0 0.0 $22.28 Rodriguez 0.0 0.0 0.0 0.0 0.0
Total Hours 192.5 14.5 33.0 91.0 54.0 0.0
1) Direct Labor $6,240.74 $693.42 $1,177.67 $2,603.15 $1,766.50 $0.00
2) Fringe (33.44% of Lines 1 ) $2,086.90 $231.88 $393.81 $870.49 $590.72 $0.00
3) Overhead (49.90% of Lines 1 + 2) $4,155.49 $461.72 $784.17 $1,733.35 $1,176.25 $0.00
4) Gen & Admin (36.27% of Lines 1 + 2 + 3) $4,527.63 $503.07 $854.39 $1,888.58 $1,281.59 $0.00
5) Total Labor (Sum Lines 1 thru 4) $17,010.76 $1,890.09 $3,210.04 $7,095.57 $4,815.06 $0.00
6) Other Direct Costs (5.0% of Line 1) $312.04 $34.67 $58.88 $130.16 $88.33 $0.00 Travel
7a) Vehicle Rental $495.00 $0.00 $0.00 $495.00 $0.00 $0.00 7b) Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 7c) Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 7d) Per diem + Hotel $498.00 $0.00 $0.00 $498.00 $0.00 $0.00 7e) Total Travel $993.00 $0.00 $0.00 $993.00 $0.00 $0.00
Subcontractor (Equipment Procurement) 8a) Provider - Task # $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 8b) Provider - Task # $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 8c) Provider - Task # $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 8d) Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 8e) Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 8f) Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) 9a) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 9b) Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 9c) Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 9d) Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 9e) IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 9f) Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 9g) Other Sub 1 - Task # $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 9h) Other Sub 2- Task # $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 9i) Other Sub 3 - Task # $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 9j) Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
9k) Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 9l) Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory 10a) Analytical Costs (Fixed Lab) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 10b) Fast Turnaround Rate (%) (Fixed Lab) 0% 100% 0% 0% 0% 10c) Fast Turnaround Charges (Fixed Lab) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 10d) Sample Shipping $654.00 $0.00 $0.00 $654.00 $0.00 $0.00 10e) Total Laboratory $654.00 $0.00 $0.00 $654.00 $0.00 $0.00
Field Expenses 11a) Personal Protection $252.00 $0.00 $0.00 $252.00 $0.00 $0.00 11b) Expendables $97.50 $0.00 $0.00 $97.50 $0.00 $0.00 11c) Equipment (Drilling Related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 11d) Equipment (Analytical Related) $1,585.85 $0.00 $0.00 $1,585.85 $0.00 $0.00 11e) Equipment (IDW Related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 11f) Equipment (Other) $204.60 $0.00 $0.00 $204.60 $0.00 $0.00 11g) Total Field Expenses $2,139.95 $0.00 $0.00 $2,139.95 $0.00 $0.00
Subtotal $21,109.75 $1,924.76 $3,268.92 $11,012.68 $4,903.39 $0.00 Completion Fee 12) (10.0% of Line 5) $1,701.08 $189.01 $321.00 $709.56 $481.51 $0.00
13) Total Estimated Cost $22,810.83 $2,113.77 $3,589.92 $11,722.24 $5,384.90 $0.00
June 6, 2018
* Equipment Procurement - 10.0% Per Subcontractor, maximum $2,500 per Subcontractor.
** Utilities fees are calculated based on $20 per utility bill per month.
*** Except for utilities fees, 10% of first $50,000, 7% of next $50,000, 5% over $100,000 per Subcontractor.
Ecology and Environment, Inc.
FDEP: J. McCarthy / E & E: S. Elliott
Pensacola Iron Triangle
CERCLA Site Inspection
Pensacola Iron Triangle_Cost Proposal_June2018C_ 6/8/2018 Page 1
SITE: Pensacola Iron Triangle
SUBTASK NO.: 1 DESCRIPTION:
DATE: June 6, 2018 FACILITY ID NO.: 0
TASK NO: CSS-17A FOR PM ONLY….HOURS CALC AUTOMATICALLY ON COST EST SHEET
LABOR HOURS
Labor Category Work Description Hours
Principal 0 Chief 0 Senior 0 Associate 0 Junior 0 Technician 0 Clerical 0
0.00
Project Management (12.5% of direct labor costs)
TOTAL LABOR HOURS
Pensacola Iron Triangle_Cost Proposal_June2018C_/1 Page 5
SUBTASK NO.: 2 DESCRIPTION:
DATE: June 6, 2018 FACILITY ID NO.: 0
TASK NO: CSS-17A
LABOR HOURS
Labor Category Work Description Hours
Principal Kelso Principal Review 1 Brown
Chief Werth Moore Ringo Long Hansen
Senior Krajewski Jacobs Eucogno GIS / graphics / figures 2 Elliott WP Author 24 Casey Guerrero
Associate Oien WP support (tables, references) 4 Witherington Percifull Fowler Technical Editor 2 Hammond
Junior Marks Jeter Bender
Technician N/A
Clerical Williams Rodriguez
33.00
VEHICLE RENTAL
ITEM RATE UNIT USAGE TOTAL
Automobile $68.00 Day 0 $0.00 Equipment Truck/Van $97.00 Day 0 $0.00 Equipment Truck/Van $420.00 Week 0 $0.00
$0.00
MILEAGE AND AIRFARE
ITEM RATE UNIT USAGE TOTAL
Mileage INCLUDED IN VEHICLE RENTAL RATE $0.00 Airfare $0.00
$0.00
MEALS AND LODGING
ITEM Labor Category RATE UNIT USAGE TOTAL
MEALS
$36.00 Day 0 $0.00 $36.00 Day 0 $0.00
$36.00 Day 0 $0.00 $36.00 Day 0 $0.00
Subtotal - Meals 0 $0.00
LODGING RATE* UNIT USAGE
$77.00 Day 0 $0.00 $77.00 Day 0 $0.00
$77.00 Day 0 $0.00 $77.00 Day 0 $0.00
Subtotal - Lodging $0.00 $0.00
EQUIPMENT PROCUREMENT
Provider List of Equipment RATE UNIT USAGE TOTAL Provider - Task # $0.00 0 $0.00 Provider - Task # $0.00 0 $0.00 Provider - Task # $0.00 0 $0.00
$0.00
SUBCONTRACTOR
Provider Name of Sub Description of Work RATE UNIT USAGE TOTAL Drilling (Conventional) $0.00 Lump Sum 0 $0.00 Drilling (Non-conventional) $0.00 Lump Sum 0 $0.00 Mobile Laboratory $0.00 Lump Sum 0 $0.00 Surveying $0.00 Lump Sum 0 $0.00 IDW $0.00 Drum 0 $0.00 Utilities $0.00 0 $0.00 Other Sub 1- Task # $0.00 0 $0.00 Other Sub 2- Task # $0.00 0 $0.00 Other Sub 3 - Task # $0.00 0 $0.00
$0.00 LABORATORY and SAMPLE SHIPMENTS
SI Work Plan Package
TOTAL LABOR HOURS
TOTAL VEHICLE RENTAL
TOTAL MILEAGE AND AIRFARE
*Rate may be higher based on geographical location or special events.
TOTAL MEALS AND LODGING
TOTAL EQUIPMENT PROCUREMENT
TOTAL SUBCONTRACTOR
Pensacola Iron Triangle_Cost Proposal_June2018C_/2 Page 6
ANALYSIS/PARAMETER
FAST TURNAROUND
RATE (%)
No. for Fast
Turnaround Rate RATE Media No. of
Samples No. of
QA/QC
Fast Turn- Around Charges TOTAL
EPA 6010 Lead 100% 0 $11.50 Water 0 0 $0.00 $0.00 EPA 9040 pH 100% 0 $8.00 Water 0 0 $0.00 $0.00 EPA 6010 Lead 100% 0 $11.50 Soil 0 0 $0.00 $0.00 EPA 6010 Lead 100% 0 $11.50 SPLP 0 0 $0.00 $0.00 TCLP/SPLP Bottle extraction 100% 0 $40.00 Soil 0 0 $0.00 $0.00 Digestion 100% 0 $6.00 Soil 0 0 $0.00 $0.00
*Rate negotiated. Subtotal-Lab Analyses 0 0 $0.00 $0.00
SAMPLE SHIPMENTS
CONTAINER SIZE
Shipment Method
24 hr No. of
Containers Shipment Method
2 day No. of
Containers Ice No. of
Containers TOTAL Small (<50 lbs.) $63.00 0 $35.00 0 $5.00 0 $0.00 Large (>50 lbs. < 70 lbs.) $104.00 0 $60.00 0 $5.00 0 $0.00
Subtotal-Sample Shipments $0.00 $0.00
FIELD EXPENSES
Personal Protection
ITEM RATE UNIT USAGE TOTAL
Level B $172.50 Per Man Day 0 $0.00 Level C $110.00 Per Man Day 0 $0.00 Level D $28.00 Per Man Day 0 $0.00
SUBTOTAL - PERSONAL PROTECTION $0.00
Expendables
ITEM RATE UNIT USAGE TOTAL ITEM TOTAL
Expendables $32.50 Day 0 $0.00
SUBTOTAL - EXPENDABLES $0.00
Drilling Related Equipment
RATE UNIT USAGE
Well Locks $3.40 ea 0 $0.00 2" Well Caps $10.20 ea 0 $0.00 4" Well Caps $14.55 ea 0 $0.00
SUBTOTAL - DRILLING RELATED EQUIPMENT $0.00
Analytical Related Equipment
RATE ITEM UNIT NO OF ITEMS USAGE TOTAL ITEM
Soil Sampling Kit (Corer, generator, auger, WL ind.) $834.20 week 0 0 $0.00 FID/PID Combination OVA $106.70 day 0 0 $0.00 Multiprobe 9000 (ph, cond, temp, do, redox) $126.10 day 0 0 $0.00 Multiprobe 9000 (ph, cond, temp, do, redox) $504.40 week 0 0 $0.00
$208.55 day 0 0 $0.00 Construction/O&M Supplies (Various items for work/repair) $63.05 day 0 0 $0.00 Turbidity Meter $24.25 day 0 0 $0.00
SUBTOTAL - ANALYTICAL RELATED EQUIPMENT $0.00
IDW Related Equipment
55-Gal Drum $58.20 0 $0.00
SUBTOTAL - IDW RELATED EQUIPMENT $0.00
Other Equipment
RATE ITEM UNIT NO OF ITEMS USAGE TOTAL ITEM
Total GPS Station (Trimble Pro XRS; Trimble GeoX) $566.60 week 0 0 $0.00 Peristaltic Tubing (Silicon 3/8 x 5/8) $3.20 ft 0 0 $0.00 Disposable Bailers (HDPE) $4.85 ea 0 0 $0.00 Peristaltic Pump $29.10 day 0 0 $0.00 Water Level Indicator $19.40 day 0 0 $0.00 Color-Tec Kit $19.40 day 0 0 $0.00 PCE Detection Tubes $67.90 10 pack 0 0 $0.00 Vacuum Gauges $19.40 ea 0 0 $0.00 Teflon Tubing (1/4 inch OD) $1.95 ft 0 0 $0.00 HDPE Poly tubing (1/4 inch OD) $0.25 ft 0 0 $0.00 Total Survey Station $41.75 day 0 0 $0.00 Water level indicator $19.40 day 0 0 $0.00 Hand Held GPS $25.25 day 0 0 $0.00
*Rate negotiated. SUBTOTAL - OTHER EQUIPMENT $0.00 $0.00
TOTAL LABORATORY and SHIPMENTS
Shallow GW Sampling Kit (WL ind., Per Pump, Multiprobe, turb meter, and
FIELD EXPENSES
Pensacola Iron Triangle_Cost Proposal_June2018C_/2 Page 6
SUBTASK NO.: 3 DESCRIPTION:
DATE: June 6, 2018 FACILITY ID NO.: 0
TASK NO: CSS-17A
LABOR HOURS
Labor Category Work Description Hours Principal
Kelso Principal support 1 Brown
Chief Werth Moore Ringo Long Hansen
Senior Krajewski Jacobs Eucogno Elliott Field team leader / SCRIBE management 32 Casey Guerrero
Associate Oien Travel, field team, equipment prep 34 Witherington Percifull Fowler Hammond
Junior Marks Jeter Field team 24 Bender
Technician N/A
Clerical Williams Rodriguez
91.00
VEHICLE RENTAL
ITEM RATE UNIT USAGE TOTAL
Automobile $68.00 Day 3 $204.00 Equipment Truck/Van $97.00 Day 3 $291.00 Equipment Truck/Van $420.00 Week 0 $0.00
$495.00
MILEAGE AND AIRFARE
ITEM RATE UNIT USAGE TOTAL
Mileage INCLUDED IN VEHICLE RENTAL RATE $0.00 Airfare $0.00
$0.00
MEALS AND LODGING
ITEM Labor Category RATE UNIT USAGE TOTAL
MEALS
Oien $36.00 Day 3 $108.00
$36.00 Day 0 $0.00 $36.00 Day 0 $0.00 $36.00 Day 0 $0.00
Subtotal - Meals 0 $108.00 LODGING RATE* UNIT USAGE PC-I have verified that this is a reasonable rate for that time and location.
Oien GSA rate is $159 June 2018) but found hotels for $130. $130.00 Day 3 $390.00
$77.00 Day 0 $0.00 $77.00 Day 0 $0.00 $77.00 Day 0 $0.00
Subtotal - Lodging $390.00 $498.00
EQUIPMENT PROCUREMENT
Provider List of Equipment RATE UNIT USAGE TOTAL Provider - Task # $0.00 0 $0.00 Provider - Task # $0.00 0 $0.00 Provider - Task # $0.00 0 $0.00
$0.00
SUBCONTRACTOR
Provider Name of Sub Description of Work RATE UNIT USAGE TOTAL Drilling (Conventional) $0.00 Lump Sum 0 $0.00 Drilling (Non-conventional) $0.00 Lump Sum 0 $0.00 Mobile Laboratory $0.00 Lump Sum 0 $0.00 Surveying $0.00 0 $0.00
IDW $0.00 0 $0.00
Utilities $0.00 0 $0.00 Other Sub 1- Task # $0.00 0 $0.00 Other Sub 2- Task # $0.00 0 $0.00 Other Sub 3 - Task # $0.00 0 $0.00
$0.00 LABORATORY and SAMPLE SHIPMENTS
ANALYSIS/PARAMETER
FAST
TURNAROUND
RATE (%)
No. for Fast
Turnaround Rate RATE Media No. of
Samples No. of
QA/QC
Fast Turn- Around Charges TOTAL
EPA 8021 B VOCs - Hall/PID Series $100 Water/Soil 0 $0.00 $0.00 EPA 8260B VOCs $135 Water/Soil 0 $0.00 $0.00 TO-15 VOCs $200 Air 0 $0.00 $0.00 TCLP/SPLP Bottle extraction $40 Soil 0 $0.00 $0.00 EPA 8270 BNAs $220 Water/Soil 0 $0.00 $0.00 EPA 8270/8310 PAHs - Low Level $100 Water/Soil 0 $0.00 $0.00 FL-PRO TRPH $84 Water/Soil 0 $0.00 $0.00 Digestion $6.00 Water/Soil 0 $0.00 $0.00
*Rate negotiated. Subtotal-Lab Analyses 0 0 $0.00 $0.00
SAMPLE SHIPMENTS
CONTAINER SIZE
Shipment Method
24 hr No. of
Containers Shipment Method
No. of Containers Ice
No. of Containers TOTAL
Small (<50 lbs.) $63.00 0 $35.00 0 $5.00 0 $0.00 Large (>50 lbs. < 70 lbs.) $104.00 6 $60.00 0 $5.00 6 $654.00
Subtotal-Sample Shipments $654.00 $654.00
FIELD EXPENSES
Personal Protection
ITEM RATE UNIT USAGE TOTAL
Level B $172.50 Per Man Day 0 $0.00 Level C $110.00 Per Man Day 0 $0.00 Level D $28.00 Per Man Day 9 $252.00
SUBTOTAL - PERSONAL PROTECTION $252.00
Expendables
ITEM RATE UNIT USAGE TOTAL ITEM TOTAL
Expendables $32.50 Day 3 $97.50
SUBTOTAL - EXPENDABLES $97.50
Drilling Related Equipment
RATE UNIT USAGE
Well Locks $3.40 ea 0 $0.00 2" Well Caps $10.20 ea 0 $0.00 4" Well Caps $14.55 ea 0 $0.00
SUBTOTAL - DRILLING RELATED EQUIPMENT $0.00
Analytical Related Equipment
RATE ITEM UNIT NO OF ITEMS USAGE TOTAL ITEM
Soil Sampling Kit (Corer, generator, auger, WL ind.) $208.55 day 1 2 $417.10 XRF Probe $447.00 day 1 2 $894.00 Multiprobe 9000 (ph, cond, temp, do, redox) $126.10 day 0 0 $0.00
TOTAL EQUIPMENT PROCUREMENT
TOTAL SUBCONTRACTOR
TOTAL MILEAGE AND AIRFARE
TOTAL MEALS AND LODGING
SI Field Activities
TOTAL LABOR HOURS
TOTAL VEHICLE RENTAL
*Rate may be higher based on geographical location or special events.
TOTAL LABORATORY and SHIPMENTS
Pensacola Iron Triangle_Cost Proposal_June2018C_/3 Page 7
Sample Bottles $66.20 1 1 $66.20 $208.55 day 1 1 $208.55
Construction/O&M Supplies (Various items for work/repair) $63.05 day 0 0 $0.00 Turbidity Meter $24.25 day 0 0 $0.00
SUBTOTAL - ANALYTICAL RELATED EQUIPMENT $1,585.85
IDW Related Equipment
55-Gal Drum $58.20 0 $0.00
SUBTOTAL - IDW RELATED EQUIPMENT $0.00
Other Equipment
RATE ITEM UNIT NO OF ITEMS USAGE TOTAL ITEM
Tedlar Bag $14.55 ea 0 0 $0.00 Peristaltic Tubing (Silicon 3/8 x 1 ft per well $3.20 ft 0 3 $9.60 Disposable Bailers (HDPE) $4.85 ea 0 0 $0.00 Peristaltic Pump $29.10 day 0 0 $0.00 Water Level Indicator $19.40 day 0 0 $0.00 Color-Tec Kit $19.40 day 0 0 $0.00 PCE Detection Tubes $67.90 10 pack 0 0 $0.00 Vacuum Gauges $19.40 ea 0 0 $0.00 Teflon Tubing (1/4 inch OD) 3 wells, ~35ft each $1.95 ft 0 100 $195.00 HDPE Poly tubing (1/4 inch OD) $0.25 ft 0 0 $0.00 Total Survey Station $41.75 day 0 0 $0.00 Water level indicator $19.40 day 0 0 $0.00 Hand Held GPS $25.25 day 0 1 $0.00
*Rate negotiated. SUBTOTAL - OTHER EQUIPMENT $204.60 $2,139.95
Shallow GW Sampling Kit (WL ind., Per Pump, Multiprobe, turb meter, FIELD EXPENSES
Pensacola Iron Triangle_Cost Proposal_June2018C_/3 Page 7
SUBTASK NO.: 4 DESCRIPTION:
DATE: June 6, 2018 FACILITY ID NO.: 0
TASK NO: CSS-17A
LABOR HOURS
Labor Category Work Description Hours
Principal Kelso Principal Review 2 Brown
Chief Werth Moore Ringo Long Hansen
Senior Krajewski Jacobs Eucogno GIS Figures and Maps 6 Elliott Report Author 24 Casey Guerrero
Associate Oien Witherington Percifull Fowler Technical Editor 6 Hammond
Junior Marks Jeter Tables and Report Generation 16 Bender
Technician N/A
Clerical Williams Rodriguez
54.00
VEHICLE RENTAL
ITEM RATE UNIT USAGE TOTAL
Automobile $68.00 Day 0 $0.00 Equipment Truck/Van $97.00 Day 0 $0.00 Equipment Truck/Van $420.00 Week 0 $0.00
$0.00
MILEAGE AND AIRFARE
ITEM RATE UNIT USAGE TOTAL
Mileage INCLUDED IN VEHICLE RENTAL RATE $0.00 Airfare $0.00
$0.00
MEALS AND LODGING
ITEM Labor Category RATE UNIT USAGE TOTAL
MEALS
$36.00 Day 0 $0.00 $36.00 Day 0 $0.00 $36.00 Day 0 $0.00 $36.00 Day 0 $0.00
Subtotal - Meals 0 $0.00
LODGING RATE* UNIT USAGE
$77.00 Day 0 $0.00 $77.00 Day 0 $0.00 $77.00 Day 0 $0.00 $77.00 Day 0 $0.00
Subtotal - Lodging $0.00 $0.00
EQUIPMENT PROCUREMENT
Provider List of Equipment RATE UNIT USAGE TOTAL Provider - Task # $0.00 0 $0.00 Provider - Task # $0.00 0 $0.00 Provider - Task # $0.00 0 $0.00
$0.00
SUBCONTRACTOR
Provider Name of Sub Description of Work RATE UNIT USAGE TOTAL Drilling (Conventional) $0.00 Lump Sum 0 $0.00 Drilling (Non-conventional) $0.00 Lump Sum 0 $0.00 Mobile Laboratory $0.00 Lump Sum 0 $0.00 Surveying $0.00 Lump Sum 0 $0.00 IDW $0.00 Drum 0 $0.00 Utilities $0.00 0 $0.00 Other Sub 1 - Task # $0.00 0 $0.00 Other Sub 2- Task # $0.00 0 $0.00 Other Sub 3 - Task # $0.00 0 $0.00
$0.00 LABORATORY and SAMPLE SHIPMENTS
SI Report
*Rate may be higher based on geographical location or special events.
TOTAL LABOR HOURS
TOTAL VEHICLE RENTAL
TOTAL MILEAGE AND AIRFARE
TOTAL MEALS AND LODGING
TOTAL EQUIPMENT PROCUREMENT
TOTAL SUBCONTRACTOR
Pensacola Iron Triangle_Cost Proposal_June2018C_/4 Page 8
ANALYSIS/PARAMETER
FAST TURNAROUND
RATE (%)
No. for Fast Turnaround
Rate RATE Media No. of
Samples No. of
QA/QC
Fast Turn- Around
Charges TOTAL EPA 8021 B VOCs - Hall/PID Series $100 Water/Soil 0 $0.00 $0.00 EPA 8260B VOCs $135 Water/Soil 0 $0.00 $0.00 TO-15 VOCs $200 Air 0 $0.00 $0.00 TCLP/SPLP Bottle extraction $40 Soil 0 $0.00 $0.00 EPA 8270 BNAs $220 Water/Soil 0 $0.00 $0.00 EPA 8270/8310 PAHs - Low Level $100 Water/Soil 0 $0.00 $0.00 FL-PRO TRPH $84 Water/Soil 0 $0.00 $0.00 Digestion $6.00 Water/Soil 0 $0.00 $0.00
*Rate negotiated. Subtotal-Lab Analyses 0 0 $0.00 $0.00
SAMPLE SHIPMENTS
CONTAINER SIZE
Shipment Method
24 hr No. of
Containers Shipment Method
No. of Containers Ice
No. of Containers TOTAL
Small (<50 lbs.) $63.00 0 $35.00 0 $5.00 0 $0.00 Large (>50 lbs. < 70 lbs.) $104.00 0 $60.00 0 $5.00 0 $0.00
Subtotal-Sample Shipments $0.00 $0.00
FIELD EXPENSES
Personal Protection
ITEM RATE UNIT USAGE TOTAL
Level B $172.50 Per Man Day 0 $0.00 Level C $110.00 Per Man Day 0 $0.00 Level D $28.00 Per Man Day 0 $0.00
SUBTOTAL - PERSONAL PROTECTION $0.00
Expendables
ITEM RATE UNIT USAGE TOTAL ITEM TOTAL
Expendables $32.50 Day 0 $0.00
SUBTOTAL - EXPENDABLES $0.00
Drilling Related Equipment
RATE UNIT USAGE
Well Locks $3.40 ea 0 $0.00 2" Well Caps $10.20 ea 0 $0.00 4" Well Caps $14.55 ea 0 $0.00
SUBTOTAL - DRILLING RELATED EQUIPMENT $0.00
Analytical Related Equipment
RATE ITEM UNIT NO OF ITEMS USAGE TOTAL ITEM
Soil Sampling Kit (Corer, generator, auger, WL ind.) $208.55 day 0 0 $0.00 FID/PID Combination OVA $106.70 day 0 0 $0.00 Multiprobe 9000 (ph, cond, temp, do, redox) $126.10 day 0 0 $0.00 Multiprobe 9000 (ph, cond, temp, do, redox) $504.40 week 0 0 $0.00
$208.55 day 0 0 $0.00 Construction/O&M Supplies (Various items for work/repair) $63.05 day 0 0 $0.00 Turbidity Meter $24.25 day 0 0 $0.00
SUBTOTAL - ANALYTICAL RELATED EQUIPMENT $0.00
IDW Related Equipment
55-Gal Drum $58.20 0 $0.00
SUBTOTAL - IDW RELATED EQUIPMENT $0.00
Other Equipment
RATE ITEM UNIT NO OF ITEMS USAGE TOTAL ITEM
Tedlar Bag $14.55 ea 0 0 $0.00 Peristaltic Tubing (Silicon 3/8 x 5/8) $3.20 ft 0 0 $0.00 Disposable Bailers (HDPE) $4.85 ea 0 0 $0.00 Peristaltic Pump $29.10 day 0 0 $0.00 Water Level Indicator $19.40 day 0 0 $0.00 Color-Tec Kit $19.40 day 0 0 $0.00 PCE Detection Tubes $67.90 10 pack 0 0 $0.00 Vacuum Gauges $19.40 ea 0 0 $0.00 Teflon Tubing (1/4 inch OD) $1.95 ft 0 0 $0.00 HDPE Poly tubing (1/4 inch OD) $0.25 ft 0 0 $0.00 Total Survey Station $41.75 day 0 0 $0.00 Water level indicator $19.40 day 0 0 $0.00 Hand Held GPS $25.25 day 0 0 $0.00
*Rate negotiated. SUBTOTAL - OTHER EQUIPMENT $0.00 $0.00
Shallow GW Sampling Kit (WL ind., Per Pump, Multiprobe, turb meter, and
FIELD EXPENSES
TOTAL LABORATORY and SHIPMENTS
Pensacola Iron Triangle_Cost Proposal_June2018C_/4 Page 8
June 6, 2018
Padraic Conner
Environmental Specialist III
Bureau of Waste Cleanup
CERCLA Site Screening Section
Bob Martinez Center
2600 Blair Stone Road
Tallahassee, Florida 32399-2400
Re: Cost Proposal to Prepare a CERCLA Site Inspection Work Plan, Perform a CERCLA
Site Inspection, and Prepare a Site Inspection Report for Iron Triangle Site, Pensacola, Escambia County, Florida (COMET Site ID # COM_303255)
Dear Padraic:
As requested by the Florida Department of Environmental Protection (FDEP), Ecology and
Environment, Inc. (E & E) has prepared this cost proposal to develop a CERCLA site inspection
(SI) work plan package, to conduct field activities associated with the SI work plan, and prepare the SI report for the above-referenced site. The package will be developed under four tasks, which will include:
o Conduct project management activities (Subtask 1);
o Preparation of a work plan package for the site inspection (Subtask 2);
o Performing field activities specified in the site inspection site work plan including the collection of soil and groundwater samples for analysis and soil screening using XRF
(Subtask 3); and o Preparing the site inspection report (Subtask 4).
E & E’s cost estimate is based on project details available to date and the following assumptions:
Subtask 1 – Program Management
This subtask consists of project management hours only and is automatically calculated based upon 12.5% of the direct labor costs; and
Subtask 2 – Work Plan Package
The Work Plan Package incorporates the information in a standard work plan as well as a Quality
Assurance Project Plan (QAPP) and also includes a health and safety (H&S) plan for the SI field work.
The Work Plan / QAPP document will include the following:
o Title and Approval page o List of project personnel and contact information o Site background and history o Project description o Applicable regulatory standards and action levels o Project schedule o Sample collection, handling, and custody requirements o QA/QC Requirements o Data Quality Objectives o Table of proposed sampling locations and identifications o Table of sample container and equipment requirements o Table of potable wells in the area (if applicable).
o Figures for project site location and sampling locations.
Incorporated into the final Work Plan / QAPP document will be a site specific H&S Plan. This plan will include the following:
o Scope of work / task descriptions o Site description / work zones o Field team organization and responsibilities o Training required o Safe work practices o Physical hazards for each task and potential control measures o Chemical hazard for each task and potential control measures o Protective equipment required by task o Site H&S monitoring (if applicable) o Decontamination procedures o Emergency response / contact information o Local and site resources o Equipment / supplies checklist o Map to nearest hospital
Once prepared, an electronic copy of the preliminary draft work plan package (pdf and Word) will be uploaded to the FDEP File Transfer Protocol (FTP) site for internal department review. Upon approval of the draft work plan, an electronic copy of the work plan (final version, pdf and Word), will be uploaded to the FDEP FTP for distribution.
Subtask 3 – Field Work
For the field activities, FDEP has identified 17 soil sampling locations (3 depths collected at each location) and three groundwater wells to be sampled. All soil locations/depths will be screened using a handheld x-ray fluorescence (XRF) analyzer. Based on the number of soil and groundwater samples to be screened and/or collected, it is anticipated to take 2.5 days to conduct the field activities.
E & E will be responsible for obtaining all sampling/screening equipment, bottles, and supplies necessary to perform the activities describe in the final site inspection work plan. Upon review in the field of the XRF screening results by E & E and FDEP, it is anticipated ~20% of samples (~10 samples) will be selected/submitted for laboratory analysis (SVOCs and metals). As the number of samples to be submitted for analysis is approximate, the bottle quotes were based on 30% (FDEP approved) to account for the required QA/QC samples and in case additional locations are selected for submittal during the field activities.
E & E will provide three people to conduct the field activities, the team leader (Elliott) and two crew
(Oien, Jeter). Elliott and Jeter are based in Pensacola and do not require lodging or per dium for this event. Oien is based in Tallahassee and this cost proposal includes six hours of travel (three each way) and lodging and per dium for three days/nights. Elliott and Jeter will use one company car from
Pensacola and Oien will use the company work truck from Tallahassee for the event.
The anticipated schedule is as follows (but may be modified due to site conditions with FDEP approval):
o Day 1: Elliott to identify/mark all soil sampling locations and identify groundwater wells to be sampled and GPS all locations. Oien and Jeter will sample 8-9 soil locations and perform decontamination of equipment while Elliott performs XRF screening, takes site photos and maintains the logbook, and manages SCRIBE input of samples selected for analysis. Ten hours per person.
o Day 2: Continue soil screening/sampling for remaining 8-9 locations. Ten hours per person.
o Day 3: Sample the three groundwater wells, collect DTW measurements, and ship samples to laboratory. 4 hours per person.
Additional time is included in this subtask to account for equipment preparation prior to the mob
(Oien, 4 hours), and pre- and post-event SCRIBE management (Elliott, 8 hours). SCRIBE management includes setting up the database with all available project details prior to the event, nightly upload of COCs to EPA if applicable, and then a final upload of complete COCs and an XML file (validated using Earthsoft EQuIS data processor) to EPA after the event.
This subtask also includes costs for soil and groundwater sampling equipment (daily rates), the rental of an XRF analyzer (low bid, daily rate), a GPS (daily rate), sample bottles (low bid), and shipping costs (estimated six coolers). Tubing costs for the groundwater well sampling were based on historical water depths of 30 to 35 feet per well (three wells total).
Upon completion of the field activities, an electronic copy of all field notes and photos, sampling forms, and chain of custodies will be uploaded to the FDEP FTP site for internal department review.
Subtask 4 – Site Inspection Report (SIR)
Once analytical data has been received from the laboratory for the activities performed in Subtask 3 above, E & E will prepare an SIR. The final SIR report will be prepared in accordance with the requirements of the USEPA SESD Operating Procedure for Report Preparation and Distribution
(SESDPROC-003-R5). The SIR will include the following sections:
o Site Background o Site Geology and Hydrogeology o Field Investigation Methodology and Findings o Pathway / Exposure Evaluation o Conclusions o References o Analytical Results Tables (by matrix/depth) o Figures o Project Area o Site / Parcel Map o Sampling Locations Map o Map of Exceedances (3-5 depending on results) o Appendices o Photo Log o Field Logs o Laboratory Results o XRF Screening Logs
An electronic copy of the draft SIR (pdf and Word) will be uploaded to the FDEP FTP site for internal department review. Upon approval (with FDEP comments and revisions to the draft incorporated or addressed), two electronic versions of the final SIR (pdf and Word) will be uploaded to the FDEP FTP for distribution; one including all references and one without.
Total Costs and Invoicing
E & E is prepared to begin work on this project upon receipt of FDEP’s notice to proceed. The total cost estimate to prepare the work plan is $22,810.83. Attachment A presents a breakdown of the cost proposal.
E & E will complete the work described in Subtasks 1 through 4 above on a fixed-price basis.
Invoicing will proceed as follows:
An invoice will be submitted upon completion of Subtask 2 (submittal of the final work plan;
An invoice will be submitted upon completion of Subtask 3 (upload of site inspection notes and forms);
An invoice will be submitted upon completion of Subtask 4 (final SIR). This final invoice will also include costs for Subtask 1;
Payment terms are net 30 days.
If you have any questions or comments concerning the proposed costs or costing assumptions, please call me at 850-435-8925 Ext 4304.
Sincerely, ECOLOGY AND ENVIRONMENT, INC.
Steven Elliott
Project Manager
Attachments cc: Carrie Kruchell , FDEP
–Site File
2650 East 40th Avenue Denver, CO 80205
(800) 833-7958 Fax: (303) 322-7242
Geotech Environmental Equipment, Inc Steven Elliott
PENSACOLA ,FL 35202
ECOLOGY & ENVIRONMENT, INC.
Quote Date 6/4/2018 9:31:26 AM
Quoted By: Jacob Morgan
Quote Number 3471Rental Quotation
Quoted To:
700 S PALAFOX ST SUITE 100
Qty RentalNum Daily Rate Weekly Rate Monthly Rate Description
Rates Per UnitBillable Days Total
1 $500.00 $1,500.00 $4,500.00Innov-X Portable XRF R8700010 $500.001
$500.00Total Estimated Rental Charges:
Quotation Does Not Include Taxes Or Shipping/Handling.
3355 McLemore Drive • Pensacola, FL 32514 • Tel: 850 474 1001 • Fax:850-478-2671
QUOTATION FOR: QUOTATION DATE:
COMPANY: QUOTATION NO.:
ADDRESS: PROJECT MGR:
QUOTED BY:
TELEPHONE/FAX: 850-523-0954 ACCOUNT EXECUTIVE:
EMAIL:
PROJECT REFERENCE CODE: 4
PROJECT REFERENCE:
PROJECT SCOPE:
PROJECT INITIATION/DURATION:
DELIVERABLE REQUIREMENTS:
Fee/Sample ($) Fee/Sample ($)
Parameter LabCode Method
Reference Qty Aqueous Total Qty
Non- Aqueous
Total
1-Liter Amber Unpreserved 15 $1.75 $26.25 1-liter Plastic unpreserved 8 $1.50 $12 8 oz WM Soil jar 40 $ 1.00 $ 40.00
$78.25
TERMS & ADDITIONAL INFORMATION:
31-May-18
E&E05312018-MHS
Mark Swafford
Erik Olen Ecology & Environment 325 John Knox Rd., Bldg F, Ste 140
EOien@ene.com
(1) Air Force (2) US Army (3) Navy (4) Commercial (5) Miscellaneous Military (6) Pulp & Paper
Grand Total
Mark SwaffordTallahassee, FL 32303
Quote for bottles
| Excel1.pdf |
| Cost Estimate |
| Excel2.pdf |
| 1 |
| 2 |
| 3 |
| 4 |
| Excel1.pdf |
| Cost Estimate |
| Excel2.pdf |
| 1 |
| 2 |
| 3 |
| 4 |
| Iron Triangle_Cost Proposal_June2018C.pdf |
| Cost Proposal for Iron Triangle Site, Pensacola, |
Escambia County, Florida
| Bottle Quotes |
| Rental Quotes |