Task Assignment Notification Change Order Summary
This document is a Task Assignment Notification Change Order Form (Change Order No. 3) issued under DEP Contract No. HW553 by the Department of Environmental Protection (DEP). The contractor is Ecology and Environment, Inc., represented by Richard Stephens, with DEP Contract Manager Justin Cross overseeing the engagement. The task assignment (BF-004 D) is located at the Old Carrabelle Water Plant Site.
The change order extends the project completion date from 12/9/2016 to 2/7/2017, representing a 60-day increase in the task period. The original task completion date was 11/15/2016. The final deliverable is a Limited Scope Source Removal Report, due 2/7/2017. The purpose of this extension is to allow for final billing discussions and submission of subcontractor invoices to E&E. There is no net increase in the task amount; the total task cost remains $73,610.16, with no additional cost reimbursement or fixed fees assessed under this change order. Specific invoice deliverables include owner coordination and backfill sampling work ($60,403.76), groundwater sampling report and project management ($7,743.27), and the Limited Scope Source Removal Report ($5,463.13).
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .