About this file

This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for the Waterfront Park Improvements project located in Franklin County, Florida. The document involves FDEP, the consultant firm VBA Design, Inc., and the relevant project management personnel including FDEP Contract Manager Mae Roth and consultant representative Victoria Williams.

The change order is a no-cost time extension for construction management and administration services provided by VBA Design, Inc. The original task execution period was from January 19, 2016 to December 31, 2016, with a fixed fee of $52,709.74 and a reimbursement amount of $50.00. This change order extends the task end date by 273 days to July 31, 2018, to accommodate design changes and project rebidding delays, with no adjustment to the contract amount. The total task amount remains $52,759.74, and the project is identified as FDEP Contract No. CN226, Task Assignment No. 3, Change Order No. 3, Project No. N1806. The extension was necessary to enable the consultant to complete construction administration services as outlined in their Scope of Services, with construction contract award anticipated to begin around January 2018.

View the file

Other files

File Type Posted
CN-370000-CN226-T1CO2.pdf PDF
CN-370000-CN226-T3CO1.pdf PDF
CN-370000-CN226-T3CO2.pdf PDF
CN-370000-CN226-T4.pdf PDF
CN-370000-CN226-T5CO1.pdf PDF
CN-370000-CN226-T5CO7.pdf PDF
CN-370000-CN226-T5CO9.pdf PDF
CN-370000-CN226-T6.pdf PDF
CN-370000-CN226-A1.pdf PDF
CN-370000-CN226-T2.pdf PDF
CN-370000-CN226-T2CO1.pdf PDF
CN-370000-CN226-T3CO6.pdf PDF
CN-370000-CN226-T5 CO8.pdf PDF
CN-370000-CN226-T7CO1.pdf PDF
CN-370000-CN226.pdf PDF
CN-370000-CN226-CMC3.pdf PDF
CN-370000-CN226-T11.pdf PDF
CN-370000-CN226-T1CO1.pdf PDF
CN-370000-CN226-T2.pdf.crdownload CRDOWNLOAD file
CN-370000-CN226-T2CO2.pdf PDF
CN-370000-CN226-T5.pdf PDF
CN-370000-CN226-T5CO5.pdf PDF
CN-370000-CN226-T5CO6.pdf PDF
CN-370000-CN226-T8.pdf PDF
CN-370000-CN226-CMC1.pdf PDF
CN-370000-CN226-CMC2.pdf PDF
CN-370000-CN226-CMC4.pdf PDF
CN-370000-CN226-T1.pdf PDF
CN-370000-CN226-T1CO3.pdf PDF
CN-370000-CN226-T3.pdf PDF
CN-370000-CN226-T3CO4.pdf PDF
CN-370000-CN226-T5CO2.pdf PDF
CN-370000-CN226-T5CO3.pdf PDF
CN-370000-CN226-T5CO4.pdf PDF
CN-370000-CN226-T7.pdf PDF
CN-370000-GC771-CO2.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

Required Signatures: Adobe Signature

FDEP Contract No.: I lask Assignment No.: Change Order No.: I Project No.:

CN226 3 N1806

Project Location: Project Name:

Waterfront Park, Franklin Co., FL Waterfront Park Improvements Consultant Name:

VBA Design, Inc.

Consultant Representative: Phone: Email:

Victoria Williams 850-769-3357 VWilliams@vbadesign.us FDEP Contract Manager: Phone: Email:

Mae Roth, FCCM 850-245-2781 Mae.Rothca2dep.state.fl.us Description and Justification of Change:

This project has been delayed due to design changes and re-bidding. The no-cost time extension is necessary for the Consultant to provide construction management services in accordance with their Scope of Services .

Ch anf!e in as • 1'; kA t moun:

Item Reimbursement Fixed Fee

Original Task Amount: $ 50.00 $52,709.74 Task amount including all previous Change Orders: $ 0.00 $0.00 Net increase/decrease in task amount for this Change Order: $ 0.00 $0.00 Total Amounts with all Change Orders: $ 50.00 $ 52.709.74 angein as ,me: Ch ' T. k 11· Original Task Execution Date: 01/19/2016

Janet Parramore Budget Representative, FDEP

Jim Oskowis, P .E.

Project Manager, FDEP

Mae Roth Contract Manager, FDEP

Victoria Williams

Original Task End Date: 12/31/2016

Present Task End Date: 10/31 /2017

Net Change in Days: 273

New Task End Date: 07/31/18

Approval Signatures:

J P Digitally signed by Janet anet arramore Parramore Date: 2017.10.23 09:55:57 -04'00'

Signature

Jl·m Oskow1·s DigitallyslgnedbyJimOskowis Data: 2017.10.23 09:52:32 -04'00'

Signature

Mae Roth Signature

Digitally signed by Mae Roth Date: 2017.10.26 09:52:31 -04'00'

Date

Date

Date

To_tal $ 52.759.74

$0.00 $ 0.00

$52,759.74

Consultant

Phil Coram, P .E.

Signamre l rl L--- Date

Jvfacfi7 Contract Authority, FDEP Signature Date

Project# Grant# Org Code Cat/Year Fund Module Object Code EO Amount Nl806 NRD03 3 7220500000 08365412 099005 NRDR 139900 FJ $0.00

29 Digit FLAIR Code: 37202099005372201000008365412 Total: $0.00

000- 012 (Effective 5-19-2016) Page 1 of 1

From:

To:

Cc:

Subject:

Date:

Attachments:

Victoria Williams Roth Mae Qskow;s. Jim; Irene Field Franklin County Waterfront Part< Wednesday, October 25, 2017 4:48:20 PM imageoo1.png

Good afternoon, Ms. Roth.

Based on the rebid of the project and the intent to award the construction contract to begin around the first of next year, we respectfully request a Task Order extension to 7 /31/18 in order to provide construction administration services.

If you have any questions, or require additional information, please do not hesitate to contact me.

Thank you and have a great day.

Victoria Williams, AIA, LEED AP BD+C VBA Design, Inc.

2424 Jenks Avenue, Suite B Panama City, Florida 32405 T: 850-769-3357

F: 850-763-0410

C: 850-960-0870

402 Bellangee Ave.

Fairhope, Alabama 36532 T: 251-517-4315

N WOSB Cf.RHH£0

**Please note that reproduction or electronic transmission of these drawings/sketches/any other documents or any part thereof is prohibited without written approval of the architect, VBA Design, Inc. These drawings/sketches/documents are protected by U.S. copyright laws and violators are subject to legal recourse.

fl ave a wonderful day**

File details come from the government source that posted it. Updated .