This document is a Task Assignment Change Order (Change Order No. 04) issued by the Florida Department of Environmental Protection (FDEP) to Stantec Consulting Services Inc. (SCSI) for design and permitting services related to the Delnor-Wiggins Pass State Park Redevelopment project in Collier County, Florida. The change order modifies an existing indefinite delivery contract (CN-222, Task Assignment 11) and involves multiple subconsultants including Dodstone Architects, McGinniss & Fleming, Bliss & Nyitray, Velocity Engineering, and Humiston & Moore. The project is funded through state and federal grants with oversight by FDEP's Bureau of Design and Construction.
The scope of services encompasses architectural, civil, structural, electrical, environmental, and landscape design for the reconstruction of park facilities damaged by Hurricane Ian, including five elevated restrooms, administrative and maintenance buildings, site improvements, and utility infrastructure. The net increase in task amount is $917,492.88, bringing the total task cost to $1,225,755.11. Compensation is structured as fixed-price fees totaling $912,592.88 plus reimbursable costs of $4,900.00, with payment upon FDEP approval of deliverables for each subtask. The project schedule extends approximately 311 calendar days from contract execution, with design deliverables progressing through schematic, 60%, 100%, and final bid document phases, followed by permit applications to multiple regulatory agencies including Collier County, FDEP, South Florida Water Management District, USACE, and the State Fire Marshall.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
( ) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN222 11 04 6i411C
Delnor-Wiggins Park Redevelopment
Stantec Consulting Services Inc.
Chris Brockmeier, PE 239-649-4040 chris.brockmeier@stantec.com
Ralph Perkins 850-245-2721 Ralph.Perkins@FloridaDEP.gov
The project consist of design and permitting of the shop, roadways/parking lots, restrooms, payment kiosks and administration buildings replace due to Hurricane Ian. See proposal dated 4.9.24.
$ 500.00 $ 50,524.08 $ 51,024.08 $ 17,000.00 $ 291,262.23 $ 308,262.23 $ 4,900.00 $ 912,592.88 $ 917,492.88 $ 21,900.00 $ 1,203,855.11 $ 1,225,755.11
2/8/2023
2/25/2025
2/25/2025
4.29.25
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2024.04.11 16:17:20 -04'00'
Garland Sandel Garland Sandel Digitally signed by Garland Sandel Date: 2024.04.12 07:39:27 -04'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2024.04.12 08:57:24 -04'00'
Chris E. Brockmeier, PE Brockmeier, Chris Digitally signed by Brockmeier, Chris Date: 2024.04.12 09:49:39 -04'00'
Shawn Hamilton
6I411C FD091 37504000091 088040/24 675002 U3200 131500 XR $ 917,492.88
$ 917,492.88
3510 Kraft Road, Suite 200, Naples, FL 34105
April 9, 2024
Garland Sandel, Design Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3800 Commonwealth Boulevard, MS 520 Tallahassee, FL 32399
RE: CN-222 - TASK ASSIGNMENT 11 CO#04
Delnor-Wiggins Pass State Park Rebuild (Restrooms, Administrative/Support Building and Maintenance/Shop Building)
Dear Garland, For your review, Stantec Consulting Services Inc. (SCSI), is hereby providing a proposal summary and man-hour documentation to include the following scope of services in support of the Delnor-Wiggins Pass State Park Rebuild: architectural (including building mechanical, electrical, structural and plumbing), site survey, civil, structural, and electrical engineering design services, geotechnical investigation, hydraulic analysis (required for building permit), environmental services, landscape and permitting.
Project Description: The Project scope addresses reconstruction of the park due to destruction caused by Hurricane Ian and specifically includes reconstruction of the park entrance, five (5) elevated restrooms, rinse off showers and water fountains, ADA-compliant building access ramps, one (1) administration building, one (1) shop building, site / civil improvements, including pavement restoration / maintenance / repair within parking areas 1 through 5, a pad-mounted payment/collection kiosk at the park entrance and each of the (5) parking areas, wastewater and stormwater infrastructure improvements, potable water and wastewater services to each structure, site electrical service restoration and miscellaneous features including, parking area manually-operated gates, and informational kiosks (one at each restroom). As the project resides seaward of the Collier County Coastal Construction Line, relocation of the structures and utilities shall be is proposed landward from the FDEP 30-year beach erosion line (Client provided). SCSI assumes the project will be completed in one construction phase.
Project Design Process: In support of the design and preparation of construction plans and permit documents, the Project will have four (5) submittal intervals: Schematic Design, 60% Design Development, 100% Design Documents, Final Bid Documents, and Permit Drawings/Construction Documents.
Restroom Design: Regarding the proposed restroom buildings, it is SCSI�s understanding that the restrooms will be based upon DEP�s prototype plan #15 (20 fixture) and modified, as required, to comply with current ADA codes based on anticipated construction type. The construction type for the restroom is assumed, as follows:
Concrete piles Hollow core slabs w/ a concrete topping Concrete Block walls, with cementitious lap siding on the exterior Pre-engineered wood trusses Standing seam metal roof Fiberglass or Aluminum doors
The restrooms are proposed to be naturally ventilated with a mechanical exhaust assist. Lighting will be limited to the interior, breezeway, and along the building access ramps. All lighting will be LED, turtle-friendly, and tied to photocells/motion sensors. Based upon current FEMA maps through February 2024, the lowest structural member of the buildings will be raised to a minimum of 1-foot above the base flood elevation. The area adjacent to the restrooms will include rinse-off showers, water fountains, ADA picnic table location and payment kiosk. Design services for the restroom will include schematic through permit phases. While the restroom design will be universal for all five locations.
Maintenance/Shop Building Design: Regarding the Maintenance/Shop Building, the design used for �San Felasco State Park�, will be adapted for the current site, wind loads, and updated per current code. Note: The architectural fees for this building have been discounted, as it is a project our subconsultant, Dodstone, has on file (slab on grade, with masonry walls and pre-engineered wood roof trusses)
Administrative/Support Building Design: SCSI and our subconsultant, are in receipt of an Administrative/Support Building design by others, dated May 10, 2017 (with cast in place concrete-framed podium, masonry walls and pre-engineered wood roof trusses). Our subconsultants will review the plans and update, as required, to meet current codes.
For your review, Stantec Consulting Services Inc. (SCSI), has provided a proposal summary and man-hour documentation for the service tasks identified below:
Subtask 36A: Restrooms � Schematic Design Subtask 36B: Restrooms � 60% Design Development Subtask 36C: Restrooms � 100% Design Documents Subtask 36D: Restrooms � Final Bid Documents Subtask 36E: Restrooms � Permit Drawings / Construction Documents Subtask 37A: Maintenance/Shop � Schematic Design Subtask 37B: Maintenance/Shop � 60% Design Development Subtask 37C: Maintenance/Shop � 100% Design Documents Subtask 37D: Maintenance/Shop � Final Bid Documents Subtask 37E: Maintenance/Shop � Permit Drawings / Construction Documents Subtask 38A: Administrative/Support Building � Schematic Design Subtask 38B: Administrative/Support Building � 60% Design Development Subtask 38C: Administrative/Support Building � 100% Design Documents Subtask 38D: Administrative/Support Building � Final Bid Documents Subtask 38E: Administrative/Support Building � Permit Drawings / Construction Document Subtask 39: Hydraulic Analysis Report � Restrooms Subtask 40A: Park Layout, Site Plan & Utilities � Civil Schematic Design Subtask 40B: Park Layout, Site Plan & Utilities � Civil 60% Design Development Subtask 40C: Park Layout, Site Plan & Utilities � Civil 100% Design Documents Subtask 40D: Park Layout, Site Plan & Utilities � Civil Final Bid Documents Subtask 41: Geotechnical Services Subtask 42A: Survey Services Subtask 42B: Limited Existing Vegetation Location Plan Subtask 43: Limited Environmental Analysis Subtask 44A: Access Ramps and Stairs (Restrooms) � 60% Design Development Subtask 44B: Access Ramps and Stairs (Restrooms) � 100% Design Documents
Subtask 44C: Access Ramps and Stairs (Restrooms) � Final Bid Documents Subtask 44D: Access Ramps and Stairs (Restrooms) � Permit Drawings / Construction Documents Subtask 45A: Site Electrical � Electrical Schematic Design Subtask 45B: Site Electrical � Electrical 60% Design Development Subtask 45C: Site Electrical � Electrical 100% Design Documents Subtask 45D: Site Electrical � Electrical Final Bid Documents Subtask 45E: Site Electrical � Electrical Permit Drawings / Construction Documents Subtask 46A: Pre-Application Meeting � Collier County Growth Management Subtask 46B: Pre-Application Meeting � South Florida Water Management District Subtask 46C: Pre-Application Meeting � South FDEP Coastal Construction Control Line (CCCL) Permit Subtask 46D: Pre-Application Meeting � North Collier Fire District State Subtask 47A: Permit Application � Collier County Site Development Plan (SDP) Permit Subtask 47B: Permit Application � FDEP Coastal Construction Control Line (CCCL) Permit Subtask 47C: Permit Application � South Florida Water Management District (SFWMD) Environmental Resource Permit (ERP) Subtask 47D: Permit Application � Collier County Special Treatment (ST) Exemption Request Subtask 47E: Permit Application � FDEP Wastewater Permit Subtask 47F: Permit Application � USACE Section 404 Subtask 47G: Permit Application � State Fire Marshall Subtask 48A: Limited Existing Vegetation Analysis Subtask 48B: Landscape 60% Design Development Subtask 48C: Landscape 100% Design Documents Subtask 48D: Landscape Final Construction Documents
Services Specifically Excluded:
Architectural, Civil, Structural and Site Electrical Services During Bidding, to be negotiated at a later date.
Architectural, Civil, Structural (Limited) and Site Electrical Construction Administration Services.
Enclosed please find our detailed proposal summary and deliverables.
Respectfully Submitted, Stantec Consulting Services, Inc.
Sincerely, Michelle Kelly, P.E.
Michelle Kelly, P.E. Chris E. Brockmeier, P.E.
Associate/Senior Project Manager Senior Principal Phone: 239-649-7649 Phone: 239-263-6453 Email: Michelle.Kelly@stantec.com Email: Chris.Brockmeier@stantec.com
Delnor-Wiggins Pass State Park Rebuild Contract Number 222, Task Assignment Number 11, Change Order Number 04
Subtask 36A: Restrooms � Schematic Design Description: SCSI�s subconsultant will utilize the existing FDEP 20-Fixture Restroom Prototype (Plan #15) to perform a preliminary code search to identify any areas of the plan that may need to be revised based on the latest adopted codes. SCSI�s subconsultant will provide one architectural schematic floor plan and elevations of the proposed restroom structure.
Deliverable: SCSI�s subconsultant will submit a PDF plan, 22� x 34�, of the architectural schematic floor plan and exterior elevations for the restroom structure.
One (1) PDF Document - architectural schematic floor plan and exterior elevations Order of magnitude cost projection (based upon square footage)
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Design Assumptions and/or Exceptions:
This proposal assumes that a single set of plans will be utilized for each restroom.
An order of magnitude cost projection will be based upon square foot only and will be provided via email.
Fixed Price Cost: $9,857.26 Subtask 36A - Restrooms � Schematic Design Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost
SCSI (Civil) Senior Project Engineer (PE) $166.05 8 $1,328.40
Dodstone Architects Principal Architect $168.00 2 $336.00 Dodstone Architects Registered Architect $133.00 25 $3,325.00 Dodstone Architects Graduate Architect $88.00 33 $2,904.00 Dodstone Architects CADD Operator $60.00 23 $1,380.00 Dodstone Architects Clerical / Staff Support $48.41 5 $242.05 $8,187.05 McGinniss & Fleming Principal Engineer/PE $125.73 2 $251.46 McGinniss & Fleming Engineer II $90.35 1 $90.35 $341.81 $9,857.26 Total for Subtask 36A: $9,857.26
Subtask 36B: Restrooms � 60% Design Development Description: SCSI�s subconsultants will develop the schematic design of the restroom to a 60% Construction Document level, incorporating any prior comments received from the FDEP. Deliverables will include an architectural floor plan, ceiling plan, life safety plan and roof plan; interior and exterior elevations; and the start of finish, door, window, and restroom accessory schedules. Mechanical, electrical, structural, and plumbing plans will be developed to a 60% Construction Document level.
Deliverable: SCSI will submit a PDF plan, 22� x 34�, of the architectural 60% design floor plans and exterior elevations for the restroom structure, including the 60% design level for structural, mechanical, electrical, and plumbing.
One (1) PDF Document � 60% Design Plans
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Design Assumptions and/or Exceptions:
This proposal assumes that a single set of plans will be utilized for all five (5) restrooms.
Fixed Price Cost: $28,856.89 Subtask 36B - Restrooms � 60% Design Development Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost
SCSI (Civil) Senior Project Engineer (PE) $166.05 8 $1,328.40 $1,328.40
Dodstone Architects Principal Architect $168.00 2 $336.00 Dodstone Architects Registered Architect $133.00 45 $5,985.00 Dodstone Architects Graduate Architect $88.00 56 $4,928.00 Dodstone Architects CADD Operator $60.00 40 $2,400.00 Dodstone Architects Clerical / Staff Support $48.41 5 $242.05 $13,891.05 McGinniss & Fleming Principal Engineer/PE $125.73 30 $3,771.90 McGinniss & Fleming Engineer II $90.35 10 $903.50 McGinniss & Fleming Engineer I $75.16 8 $601.28 McGinniss & Fleming Technician $47.70 6 $286.20 $5,562.88 Bliss & Nyitray Principal $178.77 8 $1,430.16 Bliss & Nyitray Project Engineer $119.18 40 $4,767.20 Bliss & Nyitray CADD Operator $93.86 20 $1,877.20 $8,074.56 $28,856.89 Total for Subtask 36B: $28,856.89
Subtask 36C: Restrooms � 100% Design Documents Description: SCSI�s subconsultants will develop the previous set to a 100% Construction Document level, incorporating any prior comments received from the FDEP. Specifications will be included either on the drawings or in booklet form at the discretion of the design team. The package will be marked �NOT FOR CONSTRUCTION� but would otherwise be sufficient for bidding and permitting purposes. The previous cost projection will be updated to reflect any design changes.
Deliverable: SCSI will submit a PDF plan, 22� x 34�, of the architectural 100% design floor plans and exterior elevations for the restroom structure, including the 100% design level for structural, mechanical, electrical, and plumbing.
One (1) PDF Document � 100% Design Plans Order of magnitude cost projection (for a single restroom).
Design Assumptions and/or Exceptions:
This proposal assumes that a single set of plans will be utilized for all five (5) restrooms.
Fixed Price Cost: $27,883.41 Subtask 36C - Restrooms � 100% Design Documents Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost
SCSI (Civil) Senior Project Engineer (PE) $166.05 8 $1,328.40 $1,328.40
Dodstone Architects Principal Architect $168.00 3 $504.00 Dodstone Architects Registered Architect $133.00 35 $4,655.00 Dodstone Architects Graduate Architect $88.00 55 $4,840.00 Dodstone Architects CADD Operator $60.00 48 $2,880.00 Dodstone Architects Clerical / Staff Support $48.41 5 $242.05 $13,121.05 McGinniss & Fleming Principal Engineer/PE $125.73 20 $2,514.60 McGinniss & Fleming Engineer II $90.35 20 $1,807.00 McGinniss & Fleming Engineer I $75.16 10 $751.60 McGinniss & Fleming Technician $47.70 6 $286.20 $5,359.40 Bliss & Nyitray Principal $178.77 8 $1,430.16 Bliss & Nyitray Project Engineer $119.18 40 $4,767.20 Bliss & Nyitray CADD Operator $93.86 20 $1,877.20 $8,074.56 $27,883.41 Total for Subtask 36C: $27,883.41
Subtask 36D: Restrooms � Final Bid Documents Description: SCSI�s subconsultants will incorporate any final comments from the FDEP and prepare final signed and sealed bid sets for use by FDEP in acquiring bids from contractors. The cost projection will be updated to reflect any drawing changes. The note �NOT FOR CONSTRUCTION� will be removed from the set.
Deliverable: SCSI will submit a PDF plan, 22� x 34�, of the architectural final bid documents for the restroom structure, including the final bid documents for structural, mechanical, electrical, and plumbing.
One (1) PDF Document � Signed and Sealed Plans Order of magnitude cost projection for a single restroom (OPCC)
Design Assumptions and/or Exceptions:
The Consultant has no control over the cost of labor, materials, equipment, or over the construction contractor�s methods of determining prices or over competitive bidding or market conditions.
OPCCs provided herein are based on the information known to consultant at the time the OPCC is prepared and represent only the Consultant's judgment as a design professional familiar with the construction industry. The Consultant cannot and does not guarantee that proposals, bids, or actual construction costs will not vary from its OPCCs.
Fixed Price Cost: $9,706.80 Subtask 36D - Restrooms � Final Bid Documents Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost
SCSI (Civil) Senior Project Engineer (PE) $166.05 8 $1,328.40 $1,328.40
Dodstone Architects Principal Architect $168.00 3 $504.00 Dodstone Architects Registered Architect $133.00 14 $1,862.00 Dodstone Architects Graduate Architect $88.00 5 $440.00 Dodstone Architects CADD Operator $60.00 10 $600.00 Dodstone Architects Clerical / Staff Support $48.41 4 $193.64 $3,599.64 McGinniss & Fleming Principal Engineer/PE $125.73 6 $754.38 McGinniss & Fleming Engineer II $90.35 2 $180.70 McGinniss & Fleming Engineer I $75.16 $0.00 McGinniss & Fleming Technician $47.70 2 $95.40 $1,030.48 Bliss & Nyitray Principal $178.77 4 $715.08 Bliss & Nyitray Project Engineer $119.18 16 $1,906.88 Bliss & Nyitray CADD Operator $93.86 12 $1,126.32 $3,748.28 $9,706.80
Total for Subtask 36D: $9,706.80
Subtask 36E: Restrooms � Permit Drawings / Construction Documents Description: SCSI�s subconsultants will prepare permit drawings for FDEP�s use in acquiring a building permit. Responses to one round of comments, as issued by Collier County�s Building Plan Review and Inspection Department, are included. It is assumed that the permit application fee and submission to the permitting department will be paid by the Building Contractor. The final approved permit submittal will serve as the contractor�s construction documents.
Deliverable: SCSI will submit a PDF plan, 22� x 34�, of the architectural permit drawings for the restroom structure, including the permit drawings for structural, mechanical, electrical, and plumbing.
One (1) PDF Document � Signed and Sealed Plans
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Design Assumptions and/or Exceptions:
All construction permits will be the responsibility of the contractor.
Fixed Price Cost: $5,266.97 Subtask 36E - Restrooms � Permit Drawings / Construction Documents Firm Name Position Classification Hourly
Rate Hours Total Fixed
SCSI (Civil) Senior Project Engineer (PE) $166.05 10 $1,660.50
Dodstone Architects Registered Architect $133.00 5 $665.00 Dodstone Architects Graduate Architect $88.00 5 $440.00 Dodstone Architects CADD Operator $60.00 5 $300.00 Dodstone Architects Clerical / Staff Support $48.41 3 $145.23 $1,886.23 McGinniss & Fleming Principal Engineer/PE $125.73 6 $754.38 McGinniss & Fleming Engineer II $90.35 2 $180.70 McGinniss & Fleming Engineer I $75.16 $0.00 McGinniss & Fleming Technician $47.70 2 $95.40 $1,030.48 Bliss & Nyitray Principal $178.77 2 $357.54 Bliss & Nyitray Project Engineer $119.18 2 $238.36 Bliss & Nyitray CADD Operator $93.86 1 $93.86 $689.76 $5,266.97 Total for Subtask 36E: $5,266.97
Subtask 37A: Maintenance/Shop � Schematic Design Description: SCSI�s subconsultants will utilize the San Felasco Shop Building design to perform a preliminary code search to identify any areas of the plan that may need to be revised based on the latest adopted codes. SCSI will provide one architectural schematic floor plan and exterior elevations of the proposed structure. No ADA ramps or stairs are assumed for this scope. However, the building will require flood vents.
Deliverable: SCSI will submit a PDF plan, 22� x 34�, of the architectural schematic floor plans and exterior elevations for the maintenance/shop building.
Order of magnitude cost projection
Design Assumptions and/or Exceptions:
An order of magnitude cost projection will be based upon square foot only and will be provided via email.
Fixed Price Cost: $5,684.26 Subtask 37A - Maintenance/Shop � Schematic Design Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost
SCSI (Civil) Senior Project Engineer (PE) $166.05 8 $1,328.40 $1,328.40
Dodstone Architects Principal Architect $168.00 1 $168.00 Dodstone Architects Registered Architect $133.00 12 $1,596.00 Dodstone Architects Graduate Architect $88.00 16 $1,408.00 Dodstone Architects CADD Operator $60.00 10 $600.00 Dodstone Architects Clerical / Staff Support $48.41 5 $242.05 $4,014.05 McGinniss & Fleming Principal Engineer/PE $125.73 2 $251.46 McGinniss & Fleming Engineer II $90.35 1 $90.35 $341.81 $5,684.26 Total for Subtask 37A: $5,684.26
Subtask 37B: Maintenance/Shop � 60% Design Development Description: SCSI�s subconsultants will develop the schematic design of the Maintenance/Shop Building to a 60% Construction Document level, incorporating any prior comments received from FDEP. Deliverables will include an architectural floor plan, ceiling plan, life safety plan and roof plan; exterior elevations; and the start of finish, door, and window schedules. Structural, mechanical and electrical plans will be developed to a 60% Construction Document level.
Deliverable: SCSI will submit a PDF file of the 60% design floor plans and exterior elevations for the maintenance/shop building.
One (1) PDF Document � 60% Design Plans
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Design Assumptions and/or Exceptions:
The fees for this building have been discounted, as it is a project our subconsultant has on file.
Should the DEP choose to modify this plan in any way, additional design fees will be required.
Fixed Price Cost: $19,983.73 Subtask 37B - Maintenance/Shop � 60% Design Development Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost
SCSI (Civil) Senior Project Engineer (PE) $166.05 12 $1,992.60 $1,992.60
Dodstone Architects Principal Architect $168.00 2 $336.00 Dodstone Architects Registered Architect $133.00 18 $2,394.00 Dodstone Architects Graduate Architect $88.00 27 $2,376.00 Dodstone Architects CADD Operator $60.00 28 $1,680.00 Dodstone Architects Clerical / Staff Support $48.41 5 $242.05 $7,028.05 McGinniss & Fleming Principal Engineer/PE $125.73 22 $2,766.06 McGinniss & Fleming Engineer II $90.35 10 $903.50 McGinniss & Fleming Engineer I $75.16 8 $601.28 McGinniss & Fleming Technician $47.70 6 $286.20 $4,557.04 Bliss & Nyitray Principal $178.77 4 $715.08 Bliss & Nyitray Project Engineer $119.18 32 $3,813.76 Bliss & Nyitray CADD Operator $93.86 20 $1,877.20 $6,406.04 $19,983.73 Total for Subtask 37B: $19,983.73
Subtask 37C: Maintenance/Shop � 100% Design Documents Description: SCSI�s subconsultants will develop the previous set to a 100% Construction Document level, incorporating any prior comments received from the FDEP. Specifications will be included either on the drawings or in booklet form at the discretion of the design team. The package will be marked �NOT FOR CONSTRUCTION� but would otherwise be sufficient for bidding and permitting purposes. The previous cost projection will be updated to reflect any design changes.
Deliverable: SCSI will submit a PDF plan, 22� x 34�, of the architectural 100% design floor plans and exterior elevations for the maintenance/shop building, including the 100% design level for structural, mechanical, electrical, and plumbing
Order of magnitude cost projection.
Fixed Price Cost: $20,172.65 Subtask 37C - Maintenance/Shop � 100% Design Documents Firm Name Position Classification Hourly
Rate Hours Total Fixed
SCSI (Civil) Senior Project Engineer (PE) $166.05 12 $1,992.60
Dodstone Architects Registered Architect $133.00 16 $2,128.00 Dodstone Architects Graduate Architect $88.00 28 $2,464.00 Dodstone Architects CADD Operator $60.00 27 $1,620.00 Dodstone Architects Clerical / Staff Support $48.41 5 $242.05 $6,790.05 McGinniss & Fleming Principal Engineer/PE $125.73 20 $2,514.60 McGinniss & Fleming Engineer II $90.35 20 $1,807.00 McGinniss & Fleming Engineer I $75.16 10 $751.60 McGinniss & Fleming Technician $47.70 6 $286.20 $5,359.40 Bliss & Nyitray Principal $178.77 4 $715.08 Bliss & Nyitray Project Engineer $119.18 32 $3,813.76 Bliss & Nyitray CADD Operator $93.86 16 $1,501.76 $6,030.60 $20,172.65 Total for Subtask 37C: $20,172.65
Subtask 37D: Maintenance/Shop � Final Bid Documents Description: SCSI�s subconsultants will incorporate any final comments from the FDEP and prepare final signed and sealed bid sets for use by FDEP in acquiring bids from contractors. The cost projection will be updated to reflect any drawing changes. The note �NOT FOR CONSTRUCTION� will be removed from the set.
Deliverable: SCSI will submit a PDF plan, 22� x 34�, of the architectural final bid documents for the maintenance/shop building, including the final bid documents for structural, mechanical, electrical, and plumbing.
Fixed Price Cost: $8,862.56 Subtask 37D - Maintenance/Shop � Final Bid Documents Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost
SCSI (Civil) Senior Project Engineer (PE) $166.05 12 $1,992.60 $1,992.60
Dodstone Architects Principal Architect $168.00 2 $336.00 Dodstone Architects Registered Architect $133.00 9 $1,197.00 Dodstone Architects Graduate Architect $88.00 5 $440.00 Dodstone Architects CADD Operator $60.00 5 $300.00 Dodstone Architects Clerical / Staff Support $48.41 4 $193.64 $2,466.64 McGinniss & Fleming Principal Engineer/PE $125.73 6 $754.38 McGinniss & Fleming Engineer II $90.35 2 $180.70 McGinniss & Fleming Engineer I $75.16 $0.00 McGinniss & Fleming Technician $47.70 2 $95.40 $1,030.48 Bliss & Nyitray Principal $178.77 4 $715.08 Bliss & Nyitray Project Engineer $119.18 16 $1,906.88 Bliss & Nyitray CADD Operator $93.86 8 $750.88 $3,372.84 $8,862.56 Total for Subtask 37D: $8,862.56
Subtask 37E: Maintenance/Shop � Permit Drawings / Construction Documents Description: SCSI�s subconsultants will prepare permit drawings for FDEP�s use in acquiring a building permit. Responses to one round of comments, as issued by Collier County�s Building Plan Review and Inspection Department, are included. It is assumed that the permit application fee and submission to the permitting department will be paid by the Building Contractor. The final approved permit submittal will serve as the contractor�s construction documents.
Deliverable: SCSI will submit a PDF plan, 22� x 34�, of the architectural permit drawings for the maintenance/shop structure, including the permit drawings for structural, mechanical, electrical, and plumbing.
One (1) PDF Document � Signed and Sealed Plans
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
All construction permits will be the responsibility of the contractor.
Fixed Price Cost: $4,292.15 Subtask 37E - Maintenance/Shop � Permit Drawings / Construction Documents Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost
SCSI (Civil) Senior Project Engineer (PE) $166.05 10 $1,660.50 $1,660.50
Dodstone Architects Principal Architect $168.00 1 $168.00 Dodstone Architects Registered Architect $133.00 3 $399.00 Dodstone Architects Graduate Architect $88.00 2 $176.00 Dodstone Architects CADD Operator $60.00 2 $120.00 Dodstone Architects Clerical / Staff Support $48.41 1 $48.41 $911.41 McGinniss & Fleming Principal Engineer/PE $125.73 6 $754.38 McGinniss & Fleming Engineer II $90.35 2 $180.70 McGinniss & Fleming Technician $47.70 2 $95.40 $1,030.48 Bliss & Nyitray Principal $178.77 2 $357.54 Bliss & Nyitray Project Engineer $119.18 2 $238.36 Bliss & Nyitray CADD Operator $93.86 1 $93.86 $689.76 $4,292.15 Total for Subtask 37E: $4,292.15
Subtask 38A: Administrative/Support Building � Schematic Design Description: SCSI�s subconsultants will utilize the Administrative/Support Building plans, dated 05/10/17 and designed by others, to perform a preliminary code search to identify any areas of the plan that may need to be revised based on the latest adopted codes. SCSI will provide one architectural schematic floor plan and exterior elevations of the proposed structure. Ramp and stair will be included to a schematic level.
Deliverable: SCSI will submit a PDF plan, 22� x 34�, of the architectural schematic floor plans and exterior elevations for the administrative/support building.
Design Assumptions and/or Exceptions:
An order of magnitude cost projection will be based upon square foot only and will be provided via email.
Fixed Price Cost: $11,810.26 Subtask 38A - Administrative/Support Building � Schematic Design Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost
SCSI (Civil) Senior Project Engineer (PE) $166.05 8 $1,328.40 $1,328.40
Dodstone Architects Principal Architect $168.00 2 $336.00 Dodstone Architects Registered Architect $133.00 26 $3,458.00 Dodstone Architects Graduate Architect $88.00 53 $4,664.00 Dodstone Architects CADD Operator $60.00 24 $1,440.00 Dodstone Architects Clerical / Staff Support $48.41 5 $242.05 $10,140.05 McGinniss & Fleming Principal Engineer/PE $125.73 2 $251.46 McGinniss & Fleming Engineer II $90.35 1 $90.35 McGinniss & Fleming Engineer I $75.16 $0.00 McGinniss & Fleming Technician $47.70 $0.00 $341.81 $11,810.26 Total for Subtask 38A: $11,810.26
Subtask 38B: Administrative/Support Building � 60% Design Development Description: SCSI�s subconsultants will develop the schematic design of the Administrative/Support Building to a 60% Construction Document level, incorporating any prior comments received from FDEP.
Deliverables will include an architectural floor plan, ceiling plan, life safety plan, restroom interior elevations, and roof plan; exterior elevations; and the start of finish, door, and window schedules.
Structural, mechanical and electrical plans will be developed to a 60% Construction Document level. Ramp and stairs will be developed to a 60% Construction Document level.
Deliverable: SCSI will submit a PDF file of the architectural 60% design floor plans and exterior elevations for the administrative/support building.
One (1) PDF Document � 60% Design Plans
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost: $27,821.46 Subtask 38B - Administrative/Support Building � 60% Design Development Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost
SCSI (Civil) Senior Project Engineer (PE) $166.05 8 $1,328.40 $1,328.40
Dodstone Architects Principal Architect $168.00 2 $336.00 Dodstone Architects Registered Architect $133.00 35 $4,655.00 Dodstone Architects Graduate Architect $88.00 60 $5,280.00 Dodstone Architects CADD Operator $60.00 55 $3,300.00 Dodstone Architects Clerical / Staff Support $48.41 6 $290.46 $13,861.46 McGinniss & Fleming Principal Engineer/PE $125.73 22 $2,766.06 McGinniss & Fleming Engineer II $90.35 10 $903.50 McGinniss & Fleming Engineer I $75.16 8 $601.28 McGinniss & Fleming Technician $47.70 6 $286.20 $4,557.04 Bliss & Nyitray Principal $178.77 8 $1,430.16 Bliss & Nyitray Project Engineer $119.18 40 $4,767.20 Bliss & Nyitray CADD Operator $93.86 20 $1,877.20 $8,074.56 $27,821.46 Total for Subtask 38B: $27,821.46
Subtask 38C: Administrative/Support Building � Architectural 100% Design Documents Description: SCSI�s subconsultants will develop the previous set to a 100% Construction Document level, incorporating any prior comments received from the FDEP. Specifications will be included either on the drawings or in booklet form at the discretion of the design team. The package will be marked �NOT FOR CONSTRUCTION� but would otherwise be sufficient for bidding and permitting purposes. The previous cost projection will be updated to reflect any design changes.
Deliverable: SCSI will submit a PDF plan, 22� x 34�, of the architectural 100% design floor plans and exterior elevations for the administrative/support building.
Order of magnitude cost projection.
Fixed Price Cost: $30,079.64 Subtask 38C - Administrative/Support Building � 100% Design Documents Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost
SCSI (Civil) Senior Project Engineer (PE) $166.05 8 $1,328.40 $1,328.40
Dodstone Architects Principal Architect $168.00 4 $672.00 Dodstone Architects Registered Architect $133.00 42 $5,586.00 Dodstone Architects Graduate Architect $88.00 59 $5,192.00 Dodstone Architects CADD Operator $60.00 58 $3,480.00 Dodstone Architects Clerical / Staff Support $48.41 8 $387.28 $15,317.28 McGinniss & Fleming Principal Engineer/PE $125.73 20 $2,514.60 McGinniss & Fleming Engineer II $90.35 20 $1,807.00 McGinniss & Fleming Engineer I $75.16 10 $751.60 McGinniss & Fleming Technician $47.70 6 $286.20 $5,359.40 Bliss & Nyitray Principal $178.77 8 $1,430.16 Bliss & Nyitray Project Engineer $119.18 40 $4,767.20 Bliss & Nyitray CADD Operator $93.86 20 $1,877.20 $8,074.56 $30,079.64 Total for Subtask 38C: $30,079.64
Subtask 38D: Administrative/Support Building � Final Bid Documents Description: SCSI�s subconsultants will incorporate any final comments from the FDEP and prepare final signed and sealed bid sets for use by FDEP in acquiring bids from contractors. The cost projection will be updated to reflect any drawing changes. The note �NOT FOR CONSTRUCTION� will be removed from the set.
Deliverable: SCSI will submit a PDF plan, 22� x 34�, of the architectural final bid documents for the administrative/support building, including the final bid documents for structural, mechanical, electrical, and plumbing.
Fixed Price Cost: $7,796.08 Subtask 38D - Administrative/Support Building � Final Bid Documents Firm Name Position Classification Hourly
Rate Hours Total Fixed
Dodstone Architects Principal Architect $168.00 1 $168.00 Dodstone Architects Registered Architect $133.00 8 $1,064.00 Dodstone Architects Graduate Architect $88.00 5 $440.00 Dodstone Architects CADD Operator $60.00 5 $300.00 Dodstone Architects Clerical / Staff Support $48.41 4 $193.64 $2,165.64 McGinniss & Fleming Principal Engineer/PE $125.73 6 $754.38 McGinniss & Fleming Engineer II $90.35 2 $180.70 McGinniss & Fleming Technician $47.70 2 $95.40 $1,030.48 Bliss & Nyitray Principal $178.77 4 $715.08 Bliss & Nyitray Project Engineer $119.18 12 $1,430.16 Bliss & Nyitray CADD Operator $93.86 12 $1,126.32 $3,271.56 $7,796.08 Total for Subtask 38D: $7,796.08
Subtask 38E: Administrative/Support Building � Permit Drawings / Construction Documents Description: SCSI�s subconsultants will prepare permit drawings for FDEP�s use in acquiring a building permit. Responses to one round of comments, as issued by Collier County�s Building Plan Review and Inspection Department, are included. It is assumed that the permit application fee and submission to the permitting department will be paid by the Building Contractor. The final approved permit submittal will serve as the contractor�s construction documents.
Deliverable: SCSI will submit a PDF plan, 22� x 34�, of the architectural permit drawings for the administrative/support building, including the permit drawings for structural, mechanical, electrical, and plumbing.
One (1) PDF Document � Signed and Sealed Plans
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Design Assumptions and/or Exceptions:
All construction permits will be the responsibility of the contractor.
Fixed Price Cost: $5,266.97 Subtask 38E - Administrative/Support Building � Permit Drawings / Construction Documents Firm Name Position Classification Hourly
Rate Hours Total Fixed
SCSI (Civil) Senior Project Engineer (PE) $166.05 10 $1,660.50
Dodstone Architects Graduate Architect $88.00 5 $440.00 Dodstone Architects CADD Operator $60.00 5 $300.00 Dodstone Architects Clerical / Staff Support $48.41 3 $145.23 $1,886.23 McGinniss & Fleming Principal Engineer/PE $125.73 6 $754.38 McGinniss & Fleming Engineer II $90.35 2 $180.70 McGinniss & Fleming Engineer I $75.16 $0.00 McGinniss & Fleming Technician $47.70 2 $95.40 $1,030.48 Bliss & Nyitray Principal $178.77 2 $357.54 Bliss & Nyitray Project Engineer $119.18 2 $238.36 Bliss & Nyitray CADD Operator $93.86 1 $93.86 $689.76 $5,266.97 Total for Subtask 38E: $5,266.97
Subtask 39: Hydraulic Analysis Report � Restrooms Description: This project falls seaward of the Coastal Construction Control Line and per FBC Section 3109, site specific flood design information will be required for permitting. A site-specific Hydraulic Analysis Report will be provided by a qualified registered design professional. The report will include five (5) elevated restrooms. SCSI�s subconsultant will prepare a hydraulic analysis to evaluate the waves, flow, scour and hydrodynamic load at each structure location (VE Flood Zone) utilizing topographic data, along with plan view CAD drawings.
Deliverable: SCSI will submit a PDF file of the hydraulic analysis report for the five (5) restrooms.
One (1) Signed and Sealed PDF Document � Hydraulic Analysis Report Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Design Assumptions and/or Exceptions:
Any additional coastal evaluations, such as a sea-level rise evaluation (Collier County LDC 3.03.05), is not included.
Fixed Price Cost: $20,328.40 Subtask 39 - Hydraulic Analysis Report � Restrooms Firm Name Description Total Fixed
Humiston & Moore Hydraulic Analysis Report $19,000.00 $20,328.40 Total for Subtask 39: $20,328.40
Subtask 40A: Park Layout, Site Plan & Utilities � Civil Schematic Design Description: SCSI will prepare a civil design schematic plan to include the existing conditions and horizontal layout of the parking lots, five (5) elevated Restrooms, one (1) Maintenance/Shop building, one (1) Administrative/Support Building, pad-mounted payment/collection kiosk (3 options), building access ramps, five (5) interpretive kiosks, five (5) beach at-grade access boardwalks/mobi mats, and manual gates. Food truck locations shall have gravel pads, electrical service, potable water, but no wastewater connections are proposed. The civil plans will be prepared in AutoCAD and will consist of the following components produced on 22 in. x 34 in. plan sheets in accordance with FDEP CAD Standards where applicable:
Cover Sheet Aerial / Existing Conditions Plan Schematic Level Site Layout of the Park Features
SCSI will coordinate the design goals of the consultant team and owner and provide a common understanding of design solutions. Schematic design level services may consist of the following:
Conduct preliminary grading surrounding the proposed structures to provide ADA access from the parking lot to each building (access ramp), to associated water fountain, shower and one
(1) picnic table and an at-grade boardwalk/mobi mat.
Conduct a review and analysis of the new structures footprints for stormwater and the previously prepared wastewater model (part of the original Task Assignment), to include preliminary information of all building systems to ensure the design requirements can be achieved.
Review and provide potable water system connections to each of the proposed structures.
(assumption has been made that no upgrades within park are required, currently operational).
Prepare schematic layouts and narrative for review by the Client and subconsultant team.
Deliverable: SCSI will submit a PDF file of the civil schematic plans for the park layout.
One (1) PDF Document � Civil Schematic Layout and Narrative
Design Assumptions and/or Exceptions:
Only one (1) beach access at-grade boardwalk is proposed per restroom under this scope. (five total).
No telecommunication is proposed at the restrooms.
Fixed Price Cost: $69,494.67 Subtask 40A - Park Layout, Site Plan & Utilities � Civil Schematic Design Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost
SCSI (Civil) Principal Engineer $232.11 9 $2,088.99 SCSI (Civil) Senior Project Engineer (PE) $166.05 32 $5,313.60 SCSI (Civil) Project Engineer (PE) $118.68 203 $24,092.04 SCSI (Civil) Staff Engineer (EI) $87.78 165 $14,483.70 SCSI (Civil) CADD Designer $64.50 283 $18,253.50 SCSI (Civil) Administrative Assistant $53.16 99 $5,262.84 $69,494.67 Total for Subtask 40A: $69,494.67
Subtask 40B: Park Layout, Site Plan & Utilities � Civil 60% Design Development Description: Based on comments received during the schematic design phase, SCSI will begin designing and preparing the construction plans up to the 60% design development phase, at which time the plans shall be submitted for review and approval. The 60% civil permitting and construction documents will be prepared in AutoCAD and will consist of the following components produced on 22 in. x 34 in. plan sheets in accordance with FDEP CAD Standards where applicable:
Cover Sheet Aerial / Existing Conditions Plan Site Layout Plans Paving Repairs, Grading & Drainage Plan Utility Plan and Profiles (New Grinder Wastewater Lift Stations) Cross Sections Drainage Details
Paving Details Erosion Control Plans
SCSI will attend up to one (1) design meeting, via teleconference, to review the 60% FDEP review comments. Subsequently, SCSI will submit copies of the 60% design development plans to utility providers and other consultant team members to finalize their design and service planning.
Deliverable: SCSI will submit a PDF file of the civil 60% design development plans for the park layout, site plan and utilities.
One (1) PDF Document � 60% Design Plans
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost: $99,485.13 Subtask 40B - Park Layout, Site Plan & Utilities � Civil 60% Design Development Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost
SCSI (Civil) Principal Engineer $232.11 14 $3,249.54 SCSI (Civil) Senior Project Engineer (PE) $166.05 45 $7,472.25 SCSI (Civil) Project Engineer (PE) $118.68 307 $36,434.76 SCSI (Civil) Staff Engineer (EI) $87.78 233 $20,452.74 SCSI (Civil) CADD Designer $64.50 392 $25,284.00 SCSI (Civil) Administrative Assistant $53.16 124 $6,591.84 $99,485.13 Total for Subtask 40B: $99,485.13
Subtask 40C: Park Layout, Site Plan & Utilities � Civil 100% Design Documents Description: SCSI will review the FDEP comments/findings/required adjustments and make the requested changes in response to the 60% review comments. SCSI will prepare a revised civil design plan at 100% design level, including applicable civil specifications.
Deliverable: SCSI will submit a PDF file of the civil plans and specifications for the park layout, site plan and utilities.
One (1) PDF Document � 100% Design Plans and specifications.
Fixed Price Cost: $84,345.75 Subtask 40C - Park Layout, Site Plan & Utilities � Civil 100% Design Documents Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost
SCSI (Civil) Principal Engineer $232.11 14 $3,249.54 SCSI (Civil) Senior Project Engineer (PE) $166.05 45 $7,472.25 SCSI (Civil) Project Engineer (PE) $118.68 263 $31,212.84 SCSI (Civil) Staff Engineer (EI) $87.78 182 $15,975.96 SCSI (Civil) CADD Designer $64.50 306 $19,737.00 SCSI (Civil) Administrative Assistant $53.16 126 $6,698.16 $84,345.75 Total for Subtask 40C: $84,345.75
Subtask 40D: Park Layout, Site Plan & Utilities � Civil Final Bid Documents Description: SCSI will prepare the final bid documents for distribution to FDEP. The submittal will include the final signed and sealed civil plan set, and an Opinion of Probable Construction Cost (OPCC). The OPCC will be developed from the Project's estimated quantities, and prices will be generated from the use of the FDOT unit price averages for the Project area and other sources, as needed.
Deliverable: SCSI will submit a PDF file of the civil final bid documents for the park layout, site plan and utilities connection to the proposed structures.
One (1) PDF Document � Final Bid Plans and Supporting Documents
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Design Assumptions and/or Exceptions:
The Consultant has no control over the cost of labor, materials, equipment, or over the construction contractor�s methods of determining prices or over competitive bidding or market conditions.
OPCCs provided herein are based on the information known to Consultant at the time the OPCC is prepared and represent only the Consultant's judgment as a design professional familiar with the construction industry. The Consultant cannot and does not guarantee that proposals, bids, or actual construction costs will not vary from its OPCCs.
Additional services, including bidding assistance and construction administration services, are not currently provided under this scope.
Fixed Price Cost: $29,369.91 Subtask 40D - Park Layout, Site Plan & Utilities � Civil Final Bid Documents Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost
SCSI (Civil) Principal Engineer $232.11 5 $1,160.55 SCSI (Civil) Senior Project Engineer (PE) $166.05 16 $2,656.80 SCSI (Civil) Project Engineer (PE) $118.68 86 $10,206.48 SCSI (Civil) Staff Engineer (EI) $87.78 58 $5,091.24 SCSI (Civil) CADD Designer $64.50 98 $6,321.00 SCSI (Civil) Administrative Assistant $53.16 74 $3,933.84 $29,369.91 Total for Subtask 40D: $29,369.91
Subtask 41: Geotechnical Services Description: With regards to structural design recommendations, a Geotechnical Investigation must be conducted by a registered Geotechnical Engineer in accordance with local Code to establish site specific soil properties, structural foundation recommendations and soil preparation requirements. Soil classification shall be based upon observations and any necessary testing of materials disclosed by borings, test pits or other subsurface exploration made in appropriate locations.
The Final Geotechnical Report will include recommendations for structural support of 1-story buildings and structures in a coastal region subjected to high wind and flood conditions. Five (5) Elevated Restrooms will likely be supported by concrete piles extended with reinforced concrete columns up to the underside of a concrete podium which supports load bearing CMU walls and pre-engineered wood trusses. Stairs and ramp structures will likely be wood-framed and supported by wood piles but may also require concrete piles. The report will provide recommendations for deep foundations (such as, but not limited to, wood piles, auger cast concrete piles, or similar of various diameters), shallow foundations (such as concrete footings), and structural slab on grade requirements. The Geotechnical Engineer will provide recommendations that are consistent with standard construction practices in the subject work area and provide guidance for scour, pile installation (driven vs augured/encased, for example), pile type (concrete vs wood) or other relevant information for consideration in the final construction documents.
Preliminary Boring Quantities: The following minimum boring quantities are proposed to assess the structural foundation systems and roadways, as follows:
Staking the boring locations in the field based on GPS coordinates and/or measured or estimated distances from existing landmarks. Perform limited access hand clearing (if necessary).
Performing 10 Standard Penetration Test (SPT) borings to depths of 30 feet below the ground surface
(BGS) within the footprint of the proposed restroom buildings (two borings per building).
Performing 5 SPT borings to depths of 20 feet BGS within the proposed boardwalk/access ramps areas
(one boring near each restroom building).
Performing 3 SPT borings to depths of 30 feet BGS within the proposed administration building/access ramp footprint.
Performing 2 SPT borings to depths of 30 feet BGS within the proposed maintenance building footprint.
Performing 20 SPT borings to depths of 10 feet BGS within the proposed roadways and parking areas.
Grouting the test borings in accordance with regulatory requirements.
Visually classifying the soil samples recovered from the test borings.
Deliverables: SCSI will provide a final signed and sealed Geotechnical Investigation Report in pdf format.
accurate, and timely.
Fixed Price Cost: $32,526.71 Subtask 41 - Geotechnical Services Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost
SCSI (Civil) Principal Engineer $232.11 0 $0.00 SCSI (Civil) Senior Project Engineer (PE) $166.05 3 $498.15 SCSI (Civil) Staff Engineer (EI) $87.78 2 $175.56 SCSI (Civil) CADD Designer $64.50 6 $387.00 SCSI (Civil) Administrative Assistant $53.16 3 $159.48 $1,220.19 Velocity Engineering Principal Engineer $230.76 16 $3,692.16 Velocity Engineering Project Manager $144.21 56 $8,075.76 Velocity Engineering Project Engineer $115.38 40 $4,615.20 Velocity Engineering Staff Engineer $86.55 28 $2,423.40 $18,806.52 Unit Rate Each Total Cost
Velocity Engineering Mobilization/Demobilization of Truck Mounted Drill Rig $500.00 1 $500.00
Unit Rate Feet Total Cost
Velocity Engineering Drilling of SPT Borings (0-50 ft) $12.00 750 $9,000.00
Velocity Engineering Grouting per Regulatory Requirements $4.00 750 $3,000.00
$12,000.00…