This is a Task Assignment Change Order Form (Change Order #2) issued by the Florida Department of Environmental Protection (FDEP) to Stantec Consulting Services Inc. for the Delnor-Wiggins Park Redevelopment project located in Delnor-Wiggins, Florida. The contract is identified as FDEP Contract No. CN222, Task Assignment No. 11, and Project No. 6I407C. Key FDEP personnel include Contract Manager Ralph Perkins and Project Manager Theresa Carron, while Stantec's representative is Chris Brockmeier, P.E. The change order was digitally signed and approved on October 25, 2023, by Bryan Bradner, FDEP Contract Authority.
The change order authorizes fixed-price consulting services totaling $64,169.19 to support post-Hurricane Ian park redevelopment efforts. Services include nine subtasks: stormwater system restoration and site plans ($11,727.72), four months of coordination calls and project management ($8,164.08 total across subtasks 19–22), three on-site meetings for project and contractor support ($8,098.29 total across subtasks 23–25), and a cultural resources assessment survey ($36,179.10). The overall task amount, including all previous change orders, is $231,507.89 with a fixed end date of February 25, 2025. Payment is contingent upon FDEP approval of deliverables for each subtask. All costs are reimbursable fixed fees with no additional reimbursable expenses. The project is funded through FLAIR code 6I407C with funding allocated to object code 131500.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
(Revised 9-26-2018) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN222 11 02 6I407C
Delnor-Wiggins Park Redevelopment
Stantec Consulting Services Inc.
Chris Brockmeier, PE 239-649-4040 chris.brockmeier@stantec.com
Ralph Perkins 850-245-2721 Ralph.Perkins@FloridaDEP.gov
Stormwater system restoration, permitting, Cultural Resource Assessment, and construction administration to support post Hurricane Ian park redevelopment efforts per the attached proposal dated 10/10/2023.
$ 500.00 $ 50,524.08 $ 51,024.08 $ 17,000.00 $ 150,338.70 $ 167,338.70
$ 64,169.19 $ 64,169.19 $ 17,000.00 $ 214,507.89 $ 231,507.89
2/8/2023
2/25/2025
2/25/2025 n/a
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.10.12 16:17:45 -04'00'
Theresa Carron T.Carron Digitally signed by T.Carron Date: 2023.10.13 08:31:20 -04'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.10.13 16:16:47 -04'00'
Chris E. Brockmeier, PE Brockmeier, Chris Digitally signed by Brockmeier, Chris Date: 2023.10.23 11:44:30 -04'00'
Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2023.10.25 14:26:37 -04'00'
6I407C FD091 37504000091 088040/23 408001 U3200 131500 PF $ 64,169.19