CN-370000-CN220-T20CO4.pdf
PDF 5 MB Posted
- Contract number
- CN220
- Issued by
- Florida
About this file
This is a Task Assignment Change Order Form (Change Order No. 04) issued by the Florida Department of Environmental Protection (FDEP) for Contract No. CN220, Task Assignment No. 20. The project involves the T.H. Stone St Joseph Peninsula State Park Redevelopment, located at T.H. Stone St Joseph Peninsula State Park in Florida. The consultant performing the work is Dewberry, represented by Clifford D. Wilson, P.E., with FDEP Contract Manager Jeffrey Whitfield overseeing the engagement.
This change order constitutes a time extension only, with no adjustment to the contract amount. The original task execution date was January 24, 2020, with an original end date of January 23, 2021. The present task end date was extended from July 1, 2022, to a new task end date of December 31, 2023, representing a net increase of 548 days. The total task amount remains $461,596.96, comprised of $12,420.00 in reimbursable expenses and $449,176.96 in fixed fees. The change order was signed and approved by all required parties between May 6 and June 27, 2022.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
(Revised 9-26-2018) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN220 20 04 6M113C
T.H. Stone St Joseph Peninsula State Park Redevelopment
Dewberry
Clifford D. Wilson, P.E. 850-571-1204 cwilson@dewberry.com
Jeffrey Whitfield 850-245-2630 jeffrey.whitfield@FloridaDEP.gov
Time extension only change order. Please see attached request dated 05/02/2022.
$ 27,354.42 $ 27,354.42 $ 12,420.00 $ 449,176.96 $ 461,596.96
$ 0.00 $ 0.00 $ 12,420.00 $ 449,176.96 $ 461,596.96
1/24/2020
01/23/2021
07/01/2022
12/31/2023
Diane Langston Diane Langston Digitally signed by Diane Langston Date: 2022.05.06 09:18:54 -04'00'
Donald Finkbeiner Donald J. Finkbeiner Digitally signed by Donald J.
Finkbeiner Date: 2022.05.06 09:25:08 -04'00'
Jeffrey Whitfield Jeffrey Whitfield Digitally signed by Jeffrey Whitfield Date: 2022.05.09 13:26:25 -04'00'
Clifford D. Wilson, P.E. Clifford Wilson III Digitally signed by Clifford Wilson
III
Date: 2022.06.21 11:17:03 -04'00'
Mara Gambineri Mara Gambineri Digitally signed by Mara Gambineri Date: 2022.06.27 15:13:25 -04'00'
$ 0.00
| CN220 TA20 CO4 - Time Extension -T.H. Stone St Joseph Peninsula State Park - Redevelopment.pdf |
| CN220 TA 20 CO4 Time Extension request 05022022.pdf |