This document is a Task Assignment Change Order Form (Change Order No. 05) issued by the Florida Department of Environmental Protection (FDEP) for the St. Andrews State Park Jetty Pavilion Repairs project. The consultant is Dewberry Engineers Inc., represented by Joshua Baxley, PE, with FDEP Contract No. CN220 and Task Assignment No. TA17. The contract manager is Donald Finkbeiner of FDEP's Bureau of Design and Construction. The change order was executed on July 13, 2022 (Budget Representative), July 18, 2022 (Project Manager and Contract Manager), and July 20, 2022 (Consultant and Contract Authority).
The change order authorizes additional design and construction administration services for stainless steel bracket design and installation inspection, pavilion pile testing, and substantial and final completion inspections. The proposed work consists of five subtasks: Subtask 19 (100% Plans – Stainless Steel Bracket Design, $1,800.81), Subtask 20 (Construction Administration – Bracket Installation Inspection, $1,001.88), Subtask 21 (Construction Administration – Pile Testing, $1,001.88), Subtask 22 (Construction Administration – Substantial Completion Inspection, $1,716.00), and Subtask 23 (Construction Administration – Final Completion Inspection, $667.92). The net increase for this change order is $6,188.50 (reimbursable) with a total fixed fee component of $6,188.50. The original task end date of December 31, 2020 was extended to December 31, 2022 and further extended to June 30, 2023 (181 additional days). The cumulative task amount with all change orders totals $63,444.67, with total reimbursable costs of $600.00 and total fixed fee costs of $62,844.67.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
(Revised 9-26-2018) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN220 TA17 05 6M104C
St Andrews State Park Jetty Pavilion Repairs
Dewberry
Joshua Baxley, PE 850-354-5187 jbaxley@Dewberry.com
Donald Finkbeiner 850-245-2587 Donald.Finkbeiner@FloridaDEP.gov
Additional design and inspection services need for the Jetty Pavilion. Additional time is requested to 06/30/2023. See attached proposal dated 07/06/2022.
$ 100.00 $ 27,774.16 $ 27,874.16 $ 600.00 $ 56,656.17 $ 57,256.17 $ 0.00 $ 6,188.50 $ 6,188.50
$ 600.00 $ 62,844.67 $ 63,444.67
08/20/2019
12/31/2020
12/31/2022
06/30/2023
Diane Langston Diane Langston Digitally signed by Diane Langston Date: 2022.07.13 10:56:32 -04'00'
Don Finkbeiner David Matson Digitally signed by David Matson Date: 2022.07.18 13:02:25 -04'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2022.07.18 13:38:25 -04'00'
Joshua Baxley, PE
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2022.07.20 08:51:57 -04'00'
6M104C FD079 37501000067 080039/22 423001 U3200 131500 QK $ 6,188.50
$ 6,188.50 jbaxley Pen dizzy jbaxley Pen go jbaxley Pen 1/8/22
1 | P a g e
July 6, 2022 (Revised)
Mr. Finkbeiner Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260L, MS 520 Tallahassee, FL 32399
Dewberry Engineers Inc. 101 N. Monroe Street, Tallahassee, FL 32301
850.523.0062 www.dewberry.com
RE: FDEP Project Numbers: CN220-TA17, CO4 St. Andrews Improvement
Dear Mr. Finkbeiner, This proposal is for additional design and inspection services needed for the subject pavilion. Dewberry is providing you a proposal summary and man-hour documentation for the service tasks identified below to complete the project:
• Subtask 19 – 100% Plans – Stainless Steel Bracket Design for Pile Damage
• Subtask 20 – Construction Administration – Stainless Steel Bracket Installation Inspection
• Subtask 21 – Construction Administration – Pavilion Pile Testing
• Subtask 22 – Construction Administration – Substantial Completion Inspection
• Subtask 23 – Construction Administration – Final Completion Inspection
In addition to proposed “Subtask 18”, Dewberry is requesting a time extension to 06/30/2023.
Please review the attached proposal summary and deliverables.
Sincerely, DEWBERRY
Josh Baxley, PE Associate, Branch Manager http://www.dewberry.com/ jbaxley Pen
OZT
Matson_d Pencil
Matson_d Text Box
CO5
2 | P a g e
Project Description St. Andrews Park Improvement (Revised)
CN220-TA17, CO4
Subtask 19: 100% Plans – Stainless Steel Bracket Design for Pile Damage
Description: This task is for the additional manhours for Dewberry along with the sub consultants, who shall provide the following design services for the stainless-steel bracket design for the pile damage at the St.
Andrews Pavilion replacement. The following will be covered by this task:
o Update plans to include custom stainless-steel brackets for pile damage repair
Deliverable: Field reports will be submitted to the project manager via pdf/hard copy.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 19
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Dewberry Senior. Project Manager $131.01 1.00 $ 131.01
David Melvin Inc. Senior Project Engineer $83.49 20 $1,669.80
Total Subtask 19 $1,800.81
Subtask 20: Construction Administration – Stainless Steel Bracket Installation Inspection
Description: This task is for the additional manhours for Dewberry along with the sub consultants, who shall provide the following construction administration services for the stainless-steel bracket installation for the St. Andrews Pavilion replacement. The following will be covered by this task:
o 1 Trip to inspect bracket installation (Structural) o Prepare field reports o Review Contractor Submittals
Deliverable: Field reports will be submitted to the project manager via pdf/hard copy.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, Subtask 20
Rate
Hours Total Fixed Price Cost
David Melvin Inc. Senior Project Engineer $83.49 12 $1,001.88
Total Subtask 20 $1,001.88
Matson_d Pencil
Matson_d Text Box
CO5
3 | P a g e
Subtask 21: Construction Administration – Stainless Steel Bracket Installation Inspection
Description: This task is for the additional manhours for Dewberry along with the sub consultants, who shall provide the following construction administration services for the pile installation for the St. Andrews Pavilion replacement. Please note that additional hours may be required based on the test results. The following will be covered by this task:
o 1 Trip to perform pile testing (Structural) o Prepare test results report
Deliverable: Field reports and test results will be submitted to the project manager via pdf/hard copy.
Subtask 21
Rate
Hours Total Fixed Price Cost
David Melvin Inc. Senior Project Engineer $83.49 12 $1,001.88
Total Subtask 21 $1,001.88
Subtask 22: Construction Administration – Substantial Completion Inspection
Description: This task is for the additional manhours for Dewberry along with the sub consultants, who shall provide the following construction administration services for the substantial completion inspection for the St. Andrews Pavilion replacement. Please note that additional hours may be required based on the test results. The following will be covered by this task:
o 1 Trip to perform project walkthrough (Structural) o 1 Trip to perform project walkthrough (Civil)
Subtask 22
Rate
Hours Total Fixed Price Cost
Dewberry Senior. Project Manager $131.01 8 $ 1,048.08
David Melvin Inc. Senior Project Engineer $83.49 8 $667.92
Total Subtask 22 $1,716.00
4 | P a g e
Subtask 23: Construction Administration – Final Completion Inspection
Description: This task is for the additional manhours for Dewberry along with the sub consultants, who shall provide the following construction administration services for the final completion inspection for the St.
Andrews Pavilion replacement. Please note that additional hours may be required based on the test results.
The following will be covered by this task:
o 1 Trip to perform project walkthrough (Structural)
Subtask 23
Rate
Hours Total Fixed Price Cost
David Melvin Inc. Senior Project Engineer $83.49 8 $667.92
Total Subtask 23 $667.92
Project Schedule:
Activity Duration (Calendar Days) Dates
Subtask 1 & 11: Project Initiation & Project Documentation
14 days after Agreement Execution
FDEP Review 14 days after submittal of subtask 1
Subtask 2 & 12: Survey 28 days after Agreement Execution
Subtask 3 & 13: Geotechnical Engineering 28 days after submittal of subtask 2
Subtask 4 & 14: 60% Plans 21 days after Task3
FDEP Review 14 days after submittal of subtask4
Subtask 5: Permitting Northwest Florida Water Management District
30 days after Subtask 4
Subtask 6 & 15: 100% plans 21 days after FDEP Review
FDEP Review 14 days after submittal of subtask 5
Subtask 7: Bid Phase TBD
Subtask 8 & 16: Construction Administration:
Pre-Construction Meeting
TBD
Subtask 9 & 17: Construction Administration:
Site Visits and Completion
TBD
Subtask 10: Permitting-FDEP CCCL Permitting
45 days after Task 4
Summary of Fees:
5 | P a g e
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
ORIGINAL PROPOSAL
Subtask 1:Project Initiation & Project Documentation $1,435.92
Subtask 2: Survey $4,011.48
Subtask 3: Geotechnical Engineering $0.00
Subtask 4: 60% Plans $4,919.62
Subtask 5: Permitting Northwest Florida Water Management District $1,048.08
$100
Subtask 6: 100% plans $4,364.82
Subtask 7: Bid Phase $1,048.08
Subtask 8: Construction Administration:
Pre-Construction Meeting:
$2,131.98
Subtask 9: Construction Administration:
Site Visits and Completion
0.00
Subtask 9A: $1,086.57
Subtask 9B: $693.54
Subtask 9C: $1,959.96
CO 1
Subtask 10: Permitting-FDEP CCCL Permitting
$2,096.16 $500.00
Subtask 11: Project Initiation & Project Documentation
$1,366.17
Subtask 12: Survey (CCCL)
$1,371.63
Subtask 13: Geotechnical Engineering $19,878.82
Subtask 14: 60% Plans $3,464.07
Subtask 15: 100% Plans $2,778.05
Subtask 16: Pre-Construction Meeting $500.94
Subtask 17: Construction Administration $1,335.84
Subtask 18: 100% Plans - Update $1,164.45
Subtask 19: 100% Plans – Stainless Steel Bracket Design for Pile Damage
$1,800.81
Subtask 20: Construction Administration
– Stainless Steel Bracket Installation Inspection
$1,001.88
Subtask 21: Construction Administration – Stainless Steel Bracket Installation Inspection
$1,001.88
Subtask 22: Construction Administration
– Substantial Completion Inspection
$1,716.00
Subtask 23: Construction Administration
– Final Completion Inspection
$667.92
6 | P a g e
Total Reimbursable Cost: $ 600.00
Overall Total Cost: $63,444.67
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Figure 1
From: Finkbeiner, Donald To: Baxley, Joshua; Jamie Graham Cc: Rowe, Richard J.; Chang, Laura D Subject: St Andrews CN220 TA17 CO4 Jetty pavilion Date: Tuesday, June 28, 2022 3:09:00 PM Attachments: image001.png
Good afternoon Josh, Jamie, CN220 TA17, CO4
Remaining subtasks
Subtask 9A - Site visit civil, 02/28/22, Travis Sanders, paid last invoice
Subtask 9B - Site visit civil (5 hours) Subtask 9C - Substantial site visit civil (8 hours), structural (10 hours)
Subtask 17 - Site visit structural, submittals, RFI (16 hours)
I have used (3) site visits for Jamie to straighten out our contractors issues at St Andrews Jetty pavilions.
-02/28/22 site visit to review the pavilion footings -04/19/22, emergency visit to review the damaged Gun mount pavilion roof and to provide a repair design -06/07/22, Site visit to review damaged Gun mount pavilion roof and pavilions in progress
I am not sure of the hours that have been used and I still need (1) site visit after the repairs are finished, (1) substantial completion visit and (1) final completion visit. I also need to add the pile inspection, review and possible solution if the piles have been damaged.
Can you provide a proposal for this additional work and split the tasks as much as possible? This will be change order 5 and I think we should extend to 06/30/2023.
Please give me a call if you have any questions.
Thank you Don
Donald Finkbeiner Construction Project Consultant II Bureau of Design and Construction Division of Recreation and Parks Department of Environmental Protection Donald.Finkbeiner@FloridaDEP.gov Office: 850.245.2587 Cell: 850.510.8028
This communication does not constitute an authorization for any increase in the scope of work, cost, or time for the project being discussed. All changes to services, cost, or time must be accomplished in accordance with the formal process outlined in the contract. The DEP objects to, and shall not be responsible for, any changes to services, costs, or additional time not authorized by an executed Contract Amendment, Task Assignment Change Order, Construction Change Order, or Construction Change Directive, as appropriate for this contract.
mailto:Donald.Finkbeiner@FloridaDEP.gov mailto:jbaxley@Dewberry.com mailto:jamiegraham@melvineng.com mailto:Richard.J.Rowe@dep.state.fl.us mailto:Laura.D.Chang@FloridaDEP.gov
| CN220 TA17 CO5 St. Andrews State Park - Jetty Pavilion |
| CN205 TA7 CO3 Weeki Wachee Springs State Park - Water Slide Inspection |
| CN205 TA7 CO3 Weeki Wachee Springs State Park - Waterslide Engineering Inspections |
2022 06 29 Fee Proposal Letter (002)
File details come from the government source that posted it. Updated .