About this file
This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for a project in Walton County, FL. The document modifies an existing contract (CN220) between FDEP and the consulting firm Dewberry/Preble-Rish. The change order is numbered 2 and pertains to Task Assignment 3 for Project N3203, titled "Walton County Beach Access Improvements." Key personnel involved include Debra Preble-Rish as the consultant representative and Mae Roth as the FDEP Contract Manager.
The change order extends the task completion date from the original end date of December 31, 2016 to August 31, 2017, representing a net increase of 153 days with no additional cost to the contract. The original task amount of $69,899.79 remains unchanged, with the total fixed fee maintaining at $73,854.63 across all change orders. According to the supporting justification email, the time extension was requested due to three primary factors: inadequate time allowance in a previous change order for design revisions required by permit requirements (add 1.5 months), insufficient planning by FDEP for bid processing and contract execution (add 1.5 months), and additional time needed for extended construction management services due to potential change orders (add 2.0 months). The change order was approved on February 20, 2017.
View the file
Other files
Show 40 more
Latest 50 of 76 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOOP-Carr-P17033011390 CN220 TA3 CO2 Executed 3 30 17