This document is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for Contract No. CN217, Task Assignment No. 22, dated February 9, 2021. The contract involves JGP Structural Group, Inc., a structural engineering firm based in Tallahassee, Florida, with Jeffrey G. Parzych, PE, serving as the consultant representative. The FDEP Contract Manager is Alyssa Skehan. The project is located at Big Lagoon State Park and involves building and structure repairs. The change order was approved by authorized FDEP personnel including Budget Representative Greg Turral, Project Manager Wayne Thomas, Contract Manager Alyssa Skehan, and Contract Authority Michael W. Foster Jr., PE.
The scope of work encompasses six primary subtasks: (1) Review of Existing Conditions—initial and successive site visits to assess structural conditions of buildings and structures, completed with deliverables within four weeks; (2) 60% Design Documents—preparation of repair drawings and specifications for West Area structures, East Area structures, and East Area boardwalks, delivered within eight weeks; (3) Final Design Documents—completion of final drawings and specifications, delivered within four weeks of 60% review comments; (4) Permitting Services—limited permitting for boardwalk repairs and coordination with FDEP Beaches and Coastal Division and Escambia County, with estimated permit costs of $200.00; (5) Bidding Support—written clarifications and responses to bidder questions; and (6) Construction Administration Services—up to five site visits to review conditions, respond to contractor requests, and provide observation reports. The original task amount was $12,829.73, and this change order increases the total task amount by $48,866.15 to a total of $61,695.88. The total fixed price cost is $46,680.00 and reimbursable costs are $2,186.15. The task execution date is December 4, 2020, with an end date of June 30, 2022. Payment will be made upon FDEP approval of deliverables for each subtask.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
(Revised 9-26-2018) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN217 22 1 6S102C
Big Lagoon State Park Building/Structure Repairs
JGP Structural Group, Inc
Jefferey G. Parzych PE 850 574 2888 jeff@jgpstructural.com
Alyssa Skehan 850.245.2781 Alyssa.Skehan@FloridaDEP.gov
Consultant to perform additional site visits at the project location in order to provide design and permitting services for the repair of building/structures at the park, per proposal dated 2/9/2021.
$ 574.05 $ 12,255.68 $ 12,829.73 $ 574.05 $ 12,255.68 $ 12,829.73
$ 2,186.15 $ 46,680.00 $ 48,866.15 $ 2,760.20 $ 58,935.68 $ 61,695.88
12/04/2020
6/30/2022
6/30/2022
6/30/2022
Greg Turral Gregory Turral Digitally signed by Gregory Turral Date: 2021.02.09 15:49:30 -05'00'
Wayne Thomas Wayne Thomas Digitally signed by Wayne Thomas Date: 2021.02.09 16:54:57 -05'00'
Alyssa Skehan Alyssa Skehan Digitally signed by Alyssa Skehan Date: 2021.02.10 08:24:00 -05'00'
Jefferey G. Parzych PE Jeffrey Parzych Digitally signed by Jeffrey Parzych Date: 2021.02.15 08:41:07 -05'00'
Michael W. Foster Jr. PE Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2021.02.15 13:38:41 -05'00'
6S102C FD084 37501000128 088130/21 675002 U3200 131500 XR $ 48,866.15