CGC YERED Sewage and Grey water clean SOW.pdf

PDF 764 KB Posted

Attached to
Sewage and Grey Water System, clean and inspect for the USCGC Robert Yered
Solicitation number
52050PR260000256
Issued by

About this file

Summary: USCGC ROBERT YERED (WPC-154) SPECIFICATION FOR DOCKSIDE REPAIRS FY2026

This document is a Coast Guard specification for dockside maintenance and repair work on a Sentinel-class patrol coastal ship during fiscal year 2026. The specification covers two primary work items: Work Item 6 (Sewage and Grey Water System, Clean and Inspect) as a definite requirement, and Work Item 7 (Grey Water Tank, Preserve) as an optional item.

Work Item 6 requires comprehensive cleaning and inspection of the sewage and grey water systems, including tanks, piping, pumps, valves, and related components. The contractor must submit a detailed cleaning plan within seven days of arrival conference for COR approval, specifying qualified personnel, Safety Data Sheets for all chemicals, step-by-step procedures, and locations for "before and after" inspections at minimum three separate sewage and three separate grey water clean-out points. Chemical cleaning using commercially available biodegradable descalers is recommended for sewage piping, while mechanical cleaning methods (waterjetting, pressure washing, or flexible auger) may be required for grey water piping. The contractor must renew zinc anodes exceeding 50% material loss using government-furnished property, perform pre- and post-repair operational testing, conduct leak testing with specific pressure parameters, and handle all waste disposal in compliance with federal, state, and local regulations. The contractor may utilize Coast Guard sewage and grey water disposal facilities if authorized. Work Item 7 addresses preservation of the grey water tank interior surfaces, assuming approximately 35% (180 square feet) of internal coatings have failed, requiring mechanical preparation and recoating of failed surfaces per Coast Guard preservation standards, with final pricing subject to modification based on actual tank condition assessment.

View the file

Other files

File Type Posted
SF_30- Amendment to Solicitation 001.pdf PDF
154-WPC_633_301_1_-_C.pdf PDF
154-WPC_506_301_1_-_-.pdf PDF
154-WPC_631_301_1_-_D.pdf PDF
154-WPC_593_301_1_-_C.pdf PDF
154-WPC_601_302_1_-_D.pdf PDF
154-WPC_593_303_1_-_A.pdf PDF
154-WPC_593_201_1_-_F.pdf PDF
154-WPC_528_301_1_-_B.pdf PDF
154-WPC_506_201_1_A_-.pdf PDF
Synopsis Solicitation.pdf PDF
CGC YERED Sewage and Grey water clean SOW.pdf PDF
Synopsis Solicitation.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC ROBERT YERED (WPC 1104)

SPECIFICATION FOR DOCKSIDE REPAIRS

FY2026

Developed By: Michael R Hardy

(Rev-0, 19 November 2025)

USCGC ROBERT YERED (WPC-154) DOCKSIDE AVAILABILITY FY2026

33 (Rev-0)

59301_JLW_0523_154WPC

WORK ITEM 6: Sewage and Grey Water System, Clean and Inspect

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean the sewage and grey water system (e.g. tanks, piping, etc.).

TABLE 1

USE OF COAST GUARD SEWAGE AND GREY WATER DISPOSAL FACILITIES

(PARA 3.3.5.2)

NO

1.2 Government-furnished property.

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

N **Sewage Tank Zinc Anode NIIN: 014474686 2 142.19

*Government-loaned property, which must be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT Service Center.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 154 WPC 127-302, Rev C, Potable Water & Sewage Tank Fabrication Details

Coast Guard Drawing 154 WPC 506-201, Rev A, Fills Vents, Sounds, and Overflows

Coast Guard Drawing 154 WPC 506-301, Rev -, Fills, Vents, Sounds, Overflows Diagram

Coast Guard Drawing 154 WPC 528-301, Rev B, Grey Water System Diagram

Coast Guard Drawing 154 WPC 593-201, Rev F, Sewage System Arrangement

Coast Guard Drawing 154 WPC 593-301, Rev C, Sewage System Diagram

Coast Guard Drawing 154 WPC 593-303, Rev A, Sewage Control System

Coast Guard Drawing 154 WPC 601-302, Rev D, General Arrangement

Coast Guard Drawing 154 WPC 633-301, Rev C, Cathodic Protection System

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

34 (Rev-0)

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures

OTHER REFERENCES

ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):

3.2.1 Inspection of Grey Water Tank.

3.1.2 Tech Rep.

None.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.1.5 Temporary Sanitary and Sewage Facilities. Whenever sewage or grey water collection service is disrupted due to Contractor repairs, the Contractor must provide temporary facilities in accordance with SFLC Standard Spec 0000 par 3.2.11.

3.1.6 Temporary HVAC. If the Contractor’s proposed cleaning plan will degrade continuous operation of the ship’s HVAC system then the Contractor must provide temporary ventilation to all impacted areas equivalent to the normal zonal ventilation rating for those spaces (i.e. maintain existing climate control) for the duration of work as described in SFLC Std Spec 0000.

3.1.7 Refer to all references beneath section 2 above, as applicable.

NOTE

Be aware that the grey water system has few isolation valves and many openings that must be plugged or blanked to contain cleaning media.

Be aware that AC condensate drains into the Grey Water Tank at 8 separate locations. Any temporary disruption or degradation of climate control must be fully addressed by the cleaning plan.

For these reasons, based on lessons learned, it is suggested that chemical cleaning be used on sewage piping and grey water system piping be cleaned mechanically (e.g. waterjetting, etc.)

3.1.8 Cleaning Plan. No later than 7 days after the arrival conference, and prior to the start of cleaning work, the Contractor must submit a cleaning plan CFR that contains the following:

35 (Rev-0)

A list of qualified personnel who will disassemble machinery or handle chemicals.

An SDS for every chemical proposed for use.

A step by step description of the procedures and methods that will be used to clean the systems

A list of locations in the sewage and grey water piping system where piping lines will be opened and components will be removed. At a minimum the piping must be opened at 3 separate sewage system clean-out locations and 3 separate grey water system clean-out locations for “before and after” inspections to determine the extent of cleaning required and to verify cleaning was adequately performed. These locations must be pre-approved by the COR and included in the cleaning plan CFR.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.2 Operational test and inspection - initial. Prior to commencement of cleaning work, the Contractor must witness Coast Guard personnel perform an operational pre-test of all items and shipboard devices to be disturbed, used, repaired, or altered, (e.g. TLIs, pumps, etc.) to demonstrate existing operational condition and to determine a more precise scope of cleaning required. Submit a CFR detailing any required growth work or repairs identified during the operational test based on the observed condition of the systems. Use the most economical methods for accomplishing the work.

3.2.1 Inspection of Grey Water Tank. Open and inspect the grey water tank to determine the condition of the grey water tank coating system to the greatest extent practicable, pre-cleaning. Submit a CIR detailing the condition of the grey water tank coating system and any noted discrepancies, include an estimated square footage of failed coating in the CIR.

3.3 Cleaning and Inspection Requirements. After the COR approves the “Cleaning Plan” the Contractor must clean the piping and tanks and in accordance with the approved “Cleaning Plan”, and as described below. Clean, in their entirety, all sewage and grey water system interior surfaces (e.g. sewage and grey water ppg interiors, pump interiors, valve interiors, all sewage and grey water tank vent lines interiors, sewage vacuum switch manifold interiors, fire main sprinkler pipe interiors and spray hole interiors in main sewage tank used to flush sewage tank, overboard/to shore connection discharge pump and all related valve and pipe interiors, etc.) that may come in contact with sewage or grey-water, by removing all obstructions, clogs, uric scale, and waste build-up on piping and component interiors, ensuring subsequent free unobstructed flow of waste solids and fluids.

NOTE

Depending on the condition of the system at the contract start date, chemical cleaning may not adequately remove all obstructions, scale, and build-up present. More intrusive cleaning methods, such as pressure washing, flexible auger cleaning, or other mechanical means of cleaning, may be required to remove all obstructions, scale, etc. These more intrusive methods are in scope of this work item and the Contractor may be required to use one or more them, in the appropriate quantities, to achieve minimum cleaning requirements.

36 (Rev-0)

NOTE

Before filling a system with descaler ensure all openings below the fill point are blanked off or plugged.

3.3.1 Chemical Cleaning of Piping. When chemically cleaning piping and component interiors use a commercially available biodegradable sewage/grey-water system descaler (e.g. SEW CLEAN, etc.) safe for use on stainless steel. Fill the systems with descaler and hold for a long enough period to clean the systems as described above. After cleaning is complete drain and dispose of all sewage and grey water system contents.

3.3.2 Tank Cleaning. Interior surfaces of the Grey Water Tank 3-17-0-W, Sewage Holding Tank 2-4-0- W, and sewage vacuum accumulation tank must be cleaned until free of all foreign materials, sediment, and sludge. Remove all persistent residues, residual wash media, and moisture with clean lint-free cloths.

Remove, clean, and re-install all tank interior components (e.g. TLIs, limit switches, eductors, etc.).

Renew all sewage tank and grey water tank zinc anodes that have lost more than 50% of their material using Government-furnished property, otherwise reuse the existing zinc anodes. Remove and dispose of all sewage system contents and collect, contain, and dispose of all wash media and cleaning materials in accordance with all applicable Federal, state, and local regulations. Remove all unused chemicals from USCG property immediately upon completion of work item.

3.3.3 Inspections. After cleaning, inspect the piping interior at the locations specified in the “Cleaning Plan” using a borescope in the presence of the COR, verify that all solid deposits, visible to the unmagnified eye, have been removed. Visually inspect all system components (e.g. TLIs, limit switches, pressure switches, tank interior surfaces, fasteners, gasket seating surfaces, manhole cover surfaces, etc.)

for excessive wear, damage, and all other notable discrepancies. Open and vacuum-clean the control panel assembly and inspect for any indications of overheating or loose wiring or connections. Submit a

CFR.

3.3.4 Miscellaneous. Do not drain any fluids (e.g. sewage, grey water, fresh water, etc.) into any space, bilge, or exterior location. Take all precautions required to prevent contamination of personnel and spaces in accordance with all applicable Federal, state, and local regulations. Renew all disturbed soft components (e.g. seals, gaskets, o-rings, etc.). Do not use the sewage pump installed in the system to offload sewage system contents.

3.3.4.1 Plug log. Plug all unattended openings in the system. Plugs must be fitted with a lanyard, ring or other device to prevent loss of the plug inside the system. Create and maintain a written log of each plug that specifies the location of each. Remove and dispose of all plugs upon completion of work. Furnish the plug log to the Coast Guard Inspector during the performance of close-out inspections.

3.3.4.2 Use of Coast Guard Sewage and Grey Water Disposal Facilities. If “YES” is denoted in Table 1 – (Use of Coast Guard Sewage and Grey Water Disposal Facilities), beneath paragraph 1.1 (Intent), the Contractor may offload and dispose sewage and grey water system contents into the Coast Guard pier facility tanks in lieu of a Contractor furnished tank truck, otherwise the Contractor must dispose of all waste using the Contractor’s disposal facilities.

3.4 Closing tanks. The Contractor must notify the COR at least 24 hours prior to closing the tank. After completion of all authorized repairs and after the COR inspects all work performed, close the tanks.

37 (Rev-0)

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.5 Operational test – post repairs. After completion of work, the Contractor must thoroughly test all disturbed components and systems and accomplish the following tasks in conjunction with each other as appropriate, in the presence of the Coast Guard Inspector, and submit a CFR:

3.5.1 Adjust the set point on each of the vacuum pressure switches (as applicable) to the set points noted previously.

3.5.2 Verify operation of the low and high level switches/alarms and that the pumps cycle from lead to lag status during operation. Demonstrate proper operation of tank TLIs to prove satisfactory operating condition.

3.5.3 Leak test. After all system components are reinstalled, the Contractor must test all disturbed piping for leaks, as follows:

Run water down all disturbed grey water system piping runs for 5 minutes.

Ensure the system holds vacuum without cycling for at least 20 mins.

Place both vacuumarator selection switches in the "RUN" position. Allow vacuumarator pump to run until system operating pressure of -0.40 to -0.55 bar is reached. Observe vacuum tank pressure gauge. Place both vacuumarator selection switches in the "OFF" position. (NOTE: A vacuum loss of more than 0.14 bar indicates an air leak exists in the system.) Verify vacuum system pressure remains between -0.40 to -0.55 bar for 20 minutes.

Record pressure value and include in the CFR.

Perform smoke leak test on vacuum portions of the sewage system where the Contractor has disturbed a mechanical joint.

Closely monitor the systems for leaks. Repair all leaks detected. Repeat test and inspection tasks until no leaks are detected.

3.5.4 Upon completion of testing and, in the presence of the Coast Guard Inspector, pump tanks to the limit of the ship’s installed pumps.

4. NOTES

This section is not applicable to this work item.

38 (Rev-0)

59302_JLW_0523_154WPC

WORK ITEM 7: Grey Water Tank, Preserve (Opt)

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to prepare and preserve the grey water tank while waterborne.

NOTE

This item is written to be used as an “Option” item, in conjunction with the “Definite” “Sewage and Grey Water System, Clean and Inspect” work item.

Requirements for tank opening and closing, content disposal, and inspection are covered in the “Sewage and Grey Water System, Clean and Inspect” work item and pricing for that work must be associated with that CLIN.

The actual condition of tank coatings is unknown at this time. To establish pricing assume 180 sqft (approx. 35%) of the tank’s internal coatings have failed.

After activation of this item by modification, final pricing of this item must 1) be adjusted via modification to the contract, as required, pending actual conditions of the tank 2) be in appropriate proportion to the award price of renewal of 180 sqft of coatings.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 154 WPC 506-201, Rev A, Fills Vents, Sounds, and Overflows

Coast Guard Drawing 154 WPC 528-301, Rev B, Grey Water System Diagram

Coast Guard Drawing 154 WPC 631-301, Rev D, Paint and Preservation Schedule

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures

OTHER REFERENCES

None

39 (Rev-0)

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor must furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor must remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 Surface preservation. The Contractor must, referring to all references in Section 2 References, mechanically prepare and coat all failed interior surfaces of the tank, as described in SFLC Std Spec 6310 paragraph 3.1.13 “Touch-ups and minor coating repairs”. Assume up to 35% of the tank’s surface area has failed, where failure is mechanical damage extending into the substrate. Select finish/top coat color to match existing adjacent surfaces. Only renew failed coatings, do not overcoat existing satisfactory coatings except as required for proper feathering of new coatings into existing.

3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces). Surfaces being preserved are considered “critical-coated surfaces”.

4. NOTES

This section is not applicable to this work item.