CDFW_Addendum_Letter1_P2499009.pdf

PDF 174 KB Posted

Attached to
P2499009 - Crystal Lake Hatchery - HVAC & Electrical Replacement
Solicitation number
0000033727
Issued by
Shasta County, Shasta CDP, Shasta Lake City, Mount Shasta City, California

About this file

This is Addendum #1 issued by the California Department of Fish and Wildlife (CDFW) for Project P2499009, HVAC & Electrical Replacement at Crystal Lake Hatchery in Shasta County. The addendum clarifies that the pre-bid walkthrough scheduled for January 9, 2025, at 1:00 PM is mandatory, not optional as previously indicated. Key dates include: IFB available to prospective bidders (December 16, 2024), bid opening and due date (January 23, 2025 at 2:00 PM), Notice of Intent to Award (January 30, 2025), proposed award date (April 2025), and proposed start of construction (May 2025).

The project involves HVAC and electrical replacement work with an estimated cost of $300,000. The contract requires a minimum 3% Disabled Veteran Business Enterprise (DVBE) participation goal, with incentives available for exceeding this requirement. A 5% Small Business Preference is available for certified small businesses. Contractors must be licensed as either an A - General Engineering Contractor or B - General Building Contractor, and all contractors and subcontractors must be registered with the Department of Industrial Relations for this public works project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

State of California – Natural Resources Agency GAVIN NEWSOM, Governor DEPARTMENT OF FISH AND WILDLIFE CHARLTON H. BONHAM, Director Lands and Facilities Engineering Branch 1010 Riverside Parkway West Sacramento, CA 95605 Engineering@wildlife.ca.gov

Conserving California’s Wildlife Since 1870

January 6, 2025

PLAN HOLDERS

P2499009, Addendum #1 HVAC & Electrical Replacement, Crystal Lake Hatchery Shasta County, California

The Pre-bid Walkthrough on January 9, 2025, is Mandatory. Please correct the following “Bid Requirements and Information” Section C – Item 1, in the Contract Documents on page 4:

C. Bid Requirements and Information

1. Key Action Dates

Event Date

IFB available to prospective bidders

Pre-bid Walkthrough (Optional or Mandatory)

Bid Opening

Bid Due Date

Notice of Intent to Award

Proposed Award Date [See C) 9) f), Page 7]

Proposed Start of Construction Date

December 16, 2024

January 9, 2025 @ 1:00 PM

January 23, 2025 @ 2:00 PM

January 23, 2025 @ 2:00 PM

January 30, 2025

April 2025

May 2025

Please acknowledge the receipt of this addendum in the space provided on the Bid Form.

Sincerely, Katherine Miyai, Project Engineer Land and Facilities Engineering Branch Wildlife and Fisheries Division Department of Fish and Wildlife

2025-01-06T11:42:03-0800
Miyai, Katherine@Wildlife
I am the author of this document

File details come from the government source that posted it. Updated .