This document is Addendum #4 for a Seminole County Resource Management Department solicitation for the Central Transfer Station (CTS) Extra Hazards Group (2) Fire Sprinkler System project. The addendum, dated September 21, 2022, extends the proposal due date to October 31st, 2022 at 2:00 PM (EST) and provides clarifications to potential bidders. Key questions addressed include electrical power requirements, generator compatibility, and bid submission specifications. The document indicates that the awarded contractor will be responsible for determining and addressing various technical aspects of the fire sprinkler system installation, including power feeders, circuit breakers, and potential load shed module requirements.
The solicitation seeks a qualified Fire Protection Contractor to design and install a new fire sprinkler system, with a project estimate of $792,000.00. The contract requires completion within 180 calendar days (150 days for substantial completion and 30 days for final completion). Minimum contractor qualifications include being licensed to do business in Florida, operating for at least three years, having completed four similar projects in the last three years, and possessing a State of Florida Fire Suppression Systems Contractor 1 or 2 license. The project requires work to be performed primarily outside normal business hours to minimize disruption to the facility's operations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CC-4410-22_pka6.pdf | ||
| CC-4410-22_pka5.pdf | ||
| CC-4410-22_pka3.pdf | ||
| CC-4410-22_pka2.pdf | ||
| CC-4410-22_pka1.pdf | ||
| CC-4410-22_pk.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RESOURCE MANAGEMENT DEPARTMENT
PURCHASING AND CONTRACTS DIVISION
September 21, 2022
To: PROSPECTIVE PROPOSERS AND ALL OTHERS CONCERNED
From: Michael Guild, Sr. Procurement Analyst
Subject: CC-4410-22/MAG – Central Transfer Station (CTS) Extra Hazards Group
(2) Fire Sprinkler System
Due Date: Wednesday, October 31st, 2022 at 2:00 PM (EST) via OPENGOV submittal or via email submittal to mguild@seminolecountyfl.gov
ADDENDUM # 4
Total pages: 2
The information included in this Addendum revises, clarifies, or supplements the specifications and other provisions of the contract documents and is considered part and parcel to the Package.
New Information:
1. Through the issuance of this Addendum, the Due Date for this Solicitation is hereby extended to October 31st, 2022 at 2:00 PM (EST).
Questions/Clarifications:
1. Q. Will the info provided by Duke supply us with the information needed to determine if the electric panel providing power to the fire pump is adequate?
When is the information going to be available from Duke? We feel we cannot provide and accurate proposal without this information.
Response: Seminole County intends to initiate an electrical monitoring period through a separate procurement action in order to obtain the relevant critical electrical load information to the fire pump.
2. Q. We understand that the generator is not part of this scope of work, if the feed coming from the generator is not sized correctly for the new fire pump, the pump will not work properly. Who’s scope is it to adjust the transfer switch?
Response: It will be the awarded contractor’s responsibility to adjust the transfer switch.
mailto:mguild@seminolecountyfl.gov
RESOURCE MANAGEMENT DEPARTMENT
PURCHASING AND CONTRACTS DIVISION
3. Q. In Addendum #1, Q#8 You are stating that the bid must be from a single company. The way we are reading it can come from a GC and not from a sprinkler company.
Response: Submitted bid packages must be received from a single company which meets the minimum requirements stated within the solicitation package.
4. Q. Will the existing incoming normal power feeders tapped in the switchboard accommodate the added load of increased fire pump horsepower?
Response: It will be the awarded contractor’s responsibility to determine if the feeders are adequate for the intended load as they specified and or correct the deficiency should it be deemed necessary by them.
5. Q. The circuit breaker in the generator will need to be adjusted or upgraded to allow for the larger fire pump? A site visit with Seminole County staff will be required to remove the covers of the generator breaker enclosure to verify. This is required to provide accurate pricing.
Response: An additional site visit will be coordinated to accommodate visual inspection of the generator components.
6. Q. With increase in fire pump horsepower will a load shed module need to be installed in order to give the fire pump preference over the other loads?
Response: It will be the awarded contractor’s responsibility to determine if load shed will be required and install a module to correct the deficiency should they deem it to be necessary.
Failure to acknowledge receipt of this addendum on the submittal shall result in a determination of “Non-Responsive”.
Signature on File Michael Guild
Sr. Procurement Analyst