Cannon_County_Road_Widening_Specifications_Final_Part1.pdf

PDF 152 KB Posted

Attached to
40100-State Route 53 Widening, Cannon Co.
Solicitation number
Event 40100-13902
Issued by
Carter County, Tennessee

About this file

Summary

This is a Specifications document from the Tennessee Department of Transportation (TDOT) for the widening of State Route 53 in Cannon County at lane mile 13.002. The scope of work requires a single contractor to provide all labor, equipment, traffic control, and materials to complete highway widening services including traffic control implementation, asphalt sawcutting and removal, excavation to specified depths, placement of compacted pug base stone in two or more lifts to 100% density, site restoration including demobilization and seeding of disturbed areas. Materials must be sourced exclusively from TDOT's Qualified Producer List or the Department of Transportation's Qualified Products List. Written questions and comments are due by May 15, 2026, at 2:00 p.m. Central Time, with all bids due by May 28, 2026. Mandatory on-site inspections are required prior to bid submission to take exact measurements and examine site conditions, with no allowances for quotation errors due to failure to visit the site. No specific contract award date or term duration is stated in this specifications document. TDOT will perform all subsequent paving work after completion of the dirt work.

Prior experience with similar projects is not required as a qualification criterion. Subcontracting is permitted provided respondents submit a complete list of subcontractors at the time of bid. Award will be made on a lowest-cost basis to the responsive and responsible bidder meeting all requirements. Respondents must be properly licensed as Tennessee contractors, comply with prevailing wage rate requirements, carry minimum insurance coverage of one million dollars per occurrence for workers' compensation, commercial general liability, and automobile liability, and provide a payment bond equal to 25 percent of maximum liability. No contract award value or budget range is disclosed in the available solicitation documents. The contract is subject to appropriation and availability of state or federal funds.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

State Route 53 Widening in Cannon County

Specifications

The Tennessee Department of Transportation (TDOT) is seeking a Contractor to widen State Route 53 in Cannon County at lane mile 13.002 as detailed by Attachment 1. All work shall be completed in accordance with the specifications outlined below. One Contractor will be selected to perform the full scope of services described in this document.

1. Scope of Work

The Contractor shall provide all labor, equipment, traffic control, and material necessary to perform all services and to complete the following tasks, using Attachment 1 for guidance.

A. Traffic Control

• Provide all necessary traffic control devices, signage, and personnel required to safely perform work on an active State route.

• Ensure all work zones remain protected for the duration of operations at each site and adhere to TDOT Standard Drawings (available in the Standard Specifications for Road and Bridge Construction (January 1, 2021), found below) and Manual on Uniform Traffic Control Devices (MUTCD) Standards.

B. Excavation

• Sawcut a clean joint the full depth of the asphalt along the current eastern edge of the road on the white line, and remove and dispose of all asphalt beyond the sawcut.

• Excavate material to a depth to accommodate 6.25 inches of asphalt and 10 inches of compacted base stone.

C. Widen the Road

• Place compacted pug base stone, 10 inches thick, in no fewer than two lifts, compacting to 100% density between lifts, and after the final lift, to accommodate the planned widening of the road, as shown in Attachment 1.

D. Site Restoration

• Demobilize and remove all debris from the site.

• Seed and straw all disturbed areas.

E. Materials

• All materials incorporated into the final product shall be: (i) Sourced from the State of Tennessee, Department of Transportation’s Qualified Producer list, and/or (ii) listed on the Department of Transportation’s Qualified Products List.

https://www.tn.gov/tdot/materials-and-tests/producer-list.html https://www.tn.gov/tdot/materials-and-tests/research---product-evaluation-and-qualified-products-list.html

By submitting bids for this work, the bidder represents that it has:

• Carefully examined the site of the work described herein.

• Is familiar with local conditions and the character and extent of the work.

• Has carefully examined the Plan images and the Standard Specifications for Road and Bridge Construction (January 1, 2021) adopted by the State of Tennessee, Department of Transportation and recognizes and attests that all work will be conducted in accordance with these plans and standards.

2. Contractor Qualifications:

i. Contractors do not have to submit any evidence of experience completing similar projects.

ii. Contractors may subcontract the work; however, respondent must submit a list of subcontractors at the time of bid.

3. Exclusions: The following items are excluded from the Contractor’s scope of work and will be performed by TDOT.

A. Paving: TDOT forces will pave the road after the dirt work is completed.

4. Project Logistics and Coordination

A. Project Location: Cannon County on SR-53, at Lane Mile 13.002 in alignment with drawings in Attachment 1.

B. Allowable Work Hours: The Contractor may perform work at any time. However, lane closures will be subject to TDOT’s traffic control schedule and must comply with the time restrictions outlined in the Standard Specifications for Road and Bridge Construction (January 1, 2021).

C. Coordination: The Contractor shall coordinate with TDOT’s designated project representative. The Contractor shall keep TDOT informed of progress and provide timely updates to ensure TDOT can begin paving immediately upon completion of the dirt work.

D. Inspection and approval: TDOT shall serve as the final authority in determining whether the work meets the required specifications. Any work deemed deficient shall be corrected by the Contractor at the Contractor’s expense, including rework, material replacement, and/or regrading as necessary.