This document is a Task Order for trail maintenance and construction work on the Chadwick OHV Trail System located on the Ava District of the Mark Twain National Forest in Missouri. The work is organized by trail priority and consists of new trail construction and maintenance activities including clearing, grubbing, grading, crowning, drainage maintenance, brush cutting, logging out, danger tree removal, turnpike construction, aggregate surfacing, rock crib wall construction, and erosion control.

Trail #132A is the highest priority, designated as Trail Class 3 for motorized use with a native surface design. Design specifications for Trail #132A include a 50-inch tread width, 3-8% cross slope, 5-15% grade, maximum 15-30% pitch density, 6-8 foot brush cutting height, 60-72 inch brush cutting width, and 8-10 foot design turn radius. Maintenance requirements include reestablishing entrenched areas and mud-holes with compacted, suitable material; installing a minimum of 50 grade dips per mile at approximately 100-foot spacing; reclaiming and conserving on-site material; and removing danger trees within 30 feet of the trail centerline. Additional priority trails include #131, #113, and trails #101-119 designated as optional bid items. The detailed trail log specifies maintenance needs at particular benchmark locations for each trail, including lock block removal in certain sections, waterbar and grade reversal installations for drainage, social trail obliteration, and slope realignment work to meet design parameters and prevent water pooling.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment: Task Order for Chadwick Trail Maintenance and Construction

Location:

All trails are located on the Ava District of the Mark Twain National Forest in Missouri.

The following trail log is divided into two sections: the first section describes the work required for the Chadwick OHV Trail System and the second section describes the needed for trail construction within the Chadwick OHV trail system. This list will be created in order of priority preferences of work needed to be performed.

Trail Extension – Trail

Work to be performed:

The work shall consist primarily of new trail construction and trail maintenance.

The construction and maintenance work shall consist of, but not be limited to, the following:

Clearing, Grubbing, Maintenance and Restoration of Existing Trail (including grading, crowning, etc.), Drainage Maintenance (including ditching), Brush Cutting, Logging Out, Danger Tree Removal, New trail construction, Turnpike construction, Aggregate surfacing of trail tread, Rock crib wall construction, Bridge construction (optional), and Erosion Control.

A detailed trail assessment log follows.

Trail #132A

Inspection Date: 2024

Inspector Name: Connor Landeck, Jonathon Boyer

Length:

Design Class: Trail Class 3

Design Use: Motorized

Design Surface: Native

General:

Design Criteria:

The existing trail should be managed for Trail Class 3 ATV Design Parameters. The work maintenance to an existing section of the trail using design parameters for this current classification.

• Design Tread Width – 50” width.

• Design Cross Slope – 3% to 8%

• Design Grade – 5% to 15%

• Maximum pitch density: 15-30% of trail

• Brush Cutting Height – 6 ft. to 8 ft.

• Brush Cutting Width – 60”-72”

• Design Turn Radius- 8’-10’

Trail Maintenance:

Perform trail maintenance and new trail construction for trails as specified in the Trail Log and

Schedule of Items. Work shall include existing trail restoration (911.30), brush cutting (912.20), drainage maintenance (920), aggregate surfacing, logging out, and danger tree removal (912.40).

All work outlined in the trail-log for which there is no separate pay item shall be incidental to

Trail Maintenance & Construction.

Entrenched areas and mud-holes shall be drained & filled with suitable material, compacted, and graded to drain. Fill material must be well-compacted and stable with positive drainage established such that the fill material will not be washed away. Suitable soils may have migrated from the old roadbed and are often found within the disturbed corridor (e.g., in drainage ways, lead-off ditches, trail-side berms, silt traps, etc.). Drainage ways shall be cleared and these suitable soils shall be ‘pulled in’ and used in trail tread grading operations. Unsuitable material from ditches or silt traps shall be spread along trail shoulders, in depressions, or on fill slopes in a manner which will not affect watercourses and drainage from the traveled way or shoulders.

Frequent, large rolling grade dips with lead-off ditches are required. A minimum of 50 grade dips per mile is required. Install or restore grade dips (where needed and where they will be effective) at approximately 100 ft. spacing. There will be sections of trail where grade dips may need to be spaced closer together.

Suitable Material – Reclaim, conserve and use all suitable on-site material from maintenance and construction operations for specified work. Suitable on-site material shall include soil free of duff with a recognizable granular structure, having the same character as the trail surface and rock that can be accommodated in the trail structure.

Imported Suitable Material –Furnish a suitable, well-graded, compactable material which is not easily erodible and stable without confinement. Provide a sample to the COR for approval prior to delivery to site.

Obtain COR’s approval on all imported materials.

Danger Tree Removal - The Contractor shall remove trees and snags that are broken off or that are in a leaning, unstable position over the trail-way. Standing dead and danger trees within the clearing area and within 15 ft. of either side of the trail centerline shall be removed (i.e., a 30 ft.

wide corridor centered on the trail centerline).

Order of Precedence:

Any inconsistency in this solicitation or contract shall be resolved by giving precedence in the following order:

1 – The Schedule (excluding the specifications) 2 – Representations and Other Instructions 3 – Contract Clauses 4 – Other Documents, Exhibits, and Attachments

5 – The Specifications

Trail Priorities in Order

1. 132A

2. 131

3. 113

4. 101 to 119 (Option Bid Items)

5. 119 (Option Bid Items)

Trail Log References:

This trail log is for reference purposes and illustrates some of the items of work to be accomplished. The intent of the log is to give a general description of the trail. The trail log does not describe the full scope of the work nor identify every work item. For example, some items of work, such as grade dip locations, hazard tree locations, etc., are specifically called out in the trail log, however not all locations where such items are required have been called out. There will be other locations where such work items will be required. Refer to the contract instructions and specifications.

Trail 132A Maintenance Needs Notes / Photos

Trail 132A BMP 1080 Feet: Lock block is currently in trail section. Decision whether lock block will need to be removed will be needed. Cut to the left of the old trail and build an elevated berm to put on the left side of the trail.

This section of existing trail shall be maintained at 48” to 60” wide. Use on-site soil. Insert drain dip material near upper side of hill at approximately. 1500 feet.

Compact tread thoroughly and use trail restoration techniques throughout. Full bench method.

Trail 132A

BMP 1498 Feet:

Underscore within trail and tread will need to be reestablished to meet design parameters of ATV Trail Class 3.

The current side slope has a degree of +41% and will need to be cut down to meet method full bench in standard specs. 21 degrees near 100-foot section after bridge on side hill.

Build waterbars and swoops every 100 to 200’ to fit the landscape.

Put in area near bridge to reduce water within outer edge of walls.

Hazard tree removal for one tree near right section of wood side railing.

192 Feet of obliteration where trail braids. Trail closure method shown in standard drawings.

Trail 132A BMP 3578 Feet: Trail is narrow and will need to be re-established to meet Motorized Trail Class 3.

Trail 132A BMP 3904 Feet:

Contractor could unload near Highway H and bring equipment here for Trail 132A

*Segment will be used for unloading equipment* Side road near Highway H makes for easy access of trail segment. There will be a gate within the time of work conducted.

Trail 132A BMP 4304 Feet: Restore trail tread by pulling in berm, building up trail, and out sloping or constructing a crowned tread with side ditched, as terrain dictates.

Deberm right side of trail and compact to create out slope to the left. 300 feet BMP: 4304 to 4604 EMP.

Brush in braided trail on right section of trail.

Take trees near right to camouflage section. See obliteration of trails for specs.

Trail 132A BMP 4564 Feet: Lock

Block within 20-foot section of trail. Removal in sections where failing, keep lock block and repair creep where necessary.

Social trail to the right has been established intersecting section of lock block. Will need to be brushed in or camouflaged. Focus: Fix existing trails and fix water runoff where occurring while will improve naturalization of social trails.

Trail 132A BMP 5000 Feet:

Guard rail will need to be installed to the left in order to reduce tread creep. Soil compaction will need to be implemented where trail is eroding on left side of trail.

Seeding will be implemented (blackberry bushes) to stabilize soil and naturalize the side slope where failure is occurring.

Trail 132A BMP 5293 Feet: Lock block section within area. Removal may be needed based on condition of section.

Trail 132A BMP 1 Mile: 100-foot stretch of lock block within area. Build berm near lock block and have water runoff to social trails.

Trail 132A BMP 1.2 Mile: 150-foot stretch of lock block within area. Build up berm near beginning of lock block section.

Trail 131 Maintenance Needs Notes / Photos

Trail 131 BMP 299 Feet: Clean up area to prevent washouts. Tread will need to be leveled off or slightly crowned so water can runoff section of trail.

Water drainage will need to be installed at BMP 292 Feet. Build water runoff in this section.

BMP 292 to 529.5 Feet:

Shed water off through deberming method. Full bench cut. Pull organic material and compact trail tread.

Trail 131 BMP 653 Feet: Use old trail for drainage and use existing social trail as primary route of transportation.

Trail 131 BMP 830 Feet: Cut into trail and build water runoff. Deberm side of trail to crate initial out slope. Trail Restoration STDs.

Trail to the left is a better method when water is present.

Deberm and establish outslope.

Trail 131 BMP 1400 Feet: Cut into berm area and establish outslope.

Trail 131 BMP 1600 Feet to 1800 Feet: Reestablish drainage prior to left swoop.

Trail 131 BMP 1640 Feet: Social trails within area. Will need to be obliterated and camouflaged with native material. Existing trail will need to be established and social trails will need to be brushed in.

Trail 131 BMP 1882 Feet:

Drainage construction will need to occur. Trail is holding/pooling water and will need to be out sloped in order for water to keep moving.

Trail 131 BMP: 1882 Feet to intersection of 113.

Pull organic material from intersection and get water off the top of the hill to prevent channeling. Ditch will be installed on left section of 113.

Trail 113 Maintenance Needs Notes/Photos

Trail 113 BMP 0 to 400 Feet:

Construction within section will need to occur. Installing swoops, grade reversals, and water bars every 100’ in order for water runoff to occur.

Trail 113 BMP 730 Feet: Tread slope aligns in and needs to be realigned in order to have water run off in the opposite direction.

Trail 113 BMP 1008 Feet: No water control methods installed in area currently. Waterbars should be installed every 100’ to reduce pooling of water in tread.

Trail 113 BMP 2300-2500 Feet:

Deberm left side of trail to create water runoff.

Maintenance drainage intervals along entire stretch.

Trail 113 BMP 2936 Feet: No water control methods installed in area currently. Waterbars should be installed every 100’ to reduce pooling of water in tread.

Trail 113 BMP 2700 Feet:

Contractor can come in from Highway H. This could be used as a staging location.

Trail 113 BMP 3000 Feet: Reduce water flow in area and get water off the trail.

Intervals should be placed every 100 feet to reduce water pooling.

Trail 113 BMP 3200 Feet:

Camouflage right side of trail to help reestablish existing trail system tread.

Trail 113 BMP 3400 Feet: Drop off needs leveling.

Trail 113 BMP 4500 Feet: Rebuild drainage structure and level off tread.

Trail 113 BMP 5000 Feet: Take off berm and repair day use entrance.

Trail 101 to 119 Maintenance Needs Notes/Photos

Trail 101 BMP 100 Feet: Fix swoops within section for water runoff to occur.

Trail 101 BMP 689: Social Trail needs to be obliterated.

Brush in and camouflage section of illegal trail.

Trail 101 BMP 3300 Feet: Trail gullies and will need to be repacked and reestablished in order to meet Trail management Objectives.

101 and 122 intersection.

Trail 101 BMP 4074 Feet: Needs to be leveled out and limiters possibly put in place. Native material can be used to create trail limiters or barriers.

Will need to be reduced in this section in order to meet trail class 3.

Trail 101 BMP 4300 Feet: Side bar of trail is eroded. Will need to be packed in and reestablished in order for tread to be leveled to a certain slope.

Trail 101 BMP 1.2 miles:

Waterbars intervals will need to be established facing downhill slope near creek line. Water is currently pooling as well and native compaction will need to occur in order for tread restoration.

Trail 101 BMP 1.3 Miles:

need to be established facing downhill slope near the creek line.

Water is currently pooling as well and native compaction will need to occur in order for tread restoration.

Trail 101 BMP 1.4 Miles:

need to be established facing downhill slope near creek line. Water is currently pooling as well and native compaction will need to occur in order for tread restoration.

Trail 101 BMP 1.5 Miles:

need to be established facing downhill slope near creek line. Water is currently pooling as well and native compaction will need to occur in order for tread restoration.

Will need retaining wall on the outside in order to prevent erosion from continuing to occur.

Trail 101 BMP 1.6 Miles: 100-foot stretch of trail is in slopped. Water is pooled and compaction will need to occur along with slope realignment in order for trail to be sustainable.

Trail 101 BMP 1.8 Miles: Two waterbars will need to be installed approximately 30 feet apart. Grade reversals will help in area to slow riders down and provide adequate water runoff.

Trail 101 BMP 2.0 Miles: Native compaction and slope realignment needed in 20-foot section.

Install waterbar within section so water can run off.

Trail 101 BMP 2.5 Miles:

Waterbars intervals or swoops will need to be installed for 500-foot stretch. Trail junctions here and will need to be obliterated to the left.

Trail 101 BMP 2.7 Miles:

Waterbar installation and continual maintenance needed for 500-foot stretch. Tread will need to be compacted with native material in order to level out slope.

Trail 101 BMP 2.9 Miles:

Waterbar installation for 100-foot stretch.

Trail 101 BMP 3.0 Miles: 1 waterbar installation will need to occur or drainage maintenance will be needed. Trail needs to be sloped towards the left side of the trail in order for the water to stop pooling.

Limiters will need to be put into place in order to keep the trail width specs to the right class.

Trail 101 BMP 3.2 Miles: Watebar or water runoff methods will need to be implemented.

Native compaction will be needed in order to level out trail tread.

Trail 101 BMP 3.3 Miles:

Reestablish tread, compaction will be needed in order to level out trail. Redirect slop with higher side on right side of trail. This will in turn have water run off near the creek side.

Social trail on right will need to be brushed in a blocked in order to have existing trail.

Trail will also need to be narrowed and limiters in place in order to prevent the widening of the trail.

Trail 101 BMP 3.3 Miles: Swoop or waterbar installations will need to be installed.

Trail to right will need to be brushed in and closed.

Trail 101 BMP 3.5 Miles:

compaction and create higher in slope to redirect water outwards.

Trail to right will need to be closed off and brushed in.

Trail 101 BMP 3.7 Miles: Higher in slope is needed in order to have water run-off.

Trail 101 BMP 3.9 Miles: Tread establishment and compaction will be needed. Tread establishment needed with inside having higher slope to create adequate water run off methods.

Limiters or natural earth barricades will need to be installed to reduce current tread width.

Does not meet trail class 3 currently.

Trail 101 BMP 4.0 Miles: Routine maintenance needed on section. Brush in and close braiding of trails within section.

Trail 101 BMP 4.1 Miles: General maintenance is needed.

Waterbar installation sloping lower on left side towards dried creek.

Trail 101 BMP 4.5 Miles: Slope tread higher on left side of trail and lower towards creek side.

*EMP 4.8 Miles*

Trail 119 Maintenance Needs Notes/Photos

Trail 119 BMP 142 feet: Create a higher slope near the hill side to keep water off.

Native compaction will need to occur in order to prevent more rutting.

Lock block is in area (approximately 50-foot stretch) and will need to be removed.

Trail 119 BMP 972 Feet: Lock block is in trail for 150 foot section. Will need to be removed in certain areas where block has co

Trail 119 BMP 1142 Feet: 100 foot of trail needs to be out sloped and compacted to reduce water. Make crowned tread or higher slope near right side of trail.

Trail 119 BMP 1571 Feet: Lock block is in disrepair and needs to be removed. 50 foot section of lock block and first 10 feet blocks are scattered and unearthed.

Trail 119 BMP 1872 Feet:

Removal of trail bridge structure. Northern portion of trail will need to align more vertically to hit crossing more perpendicular than current crossing.

Trail 119 BMP 4895 Feet: Section of lock block within area.

Sections will need to be removed.

Trail 119 BMP 5103 Feet: Section of lock block (Approximately 50 feet) may need to be removed.