This is a Schedule of Items (SOI) for the Chadwick Motorized Trails Maintenance contract covering the period from September 1, 2026, to September 1, 2027. The document outlines five primary line items for existing trail restoration work across multiple trails within the Chadwick trail system, with work measured in linear feet (LF).
The contract requires tread resurfacing and maintenance of motorized trails to a 50-inch tread width across all line items, including clearing, waterbar installation, drainage maintenance or installation, hazard tree removal, berm maintenance, and drain dip work. Specific line items include: Trail 132A (5,888 LF), Trail 131 (4,922 LF), Trail 113 junction from 131 (5,000 LF), Trail 101 (Option Bid Items A, 25,344 LF), and Trail 119 (Option Bid Items B, 5,103 LF). Each line item references applicable work codes (912.40 for hazard tree removal, 920 for drainage, 922 for waterbars, 926 for maintenance, and 927 for drain dips) and includes cross-references to a Trail Log and Statement of Work (SOW) for detailed specifications. The SOI structure includes provisions for four option years beyond the initial contract period, with empty Unit Price columns indicating that pricing will be provided separately during the solicitation process.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Schedule of Items (SOI)- Chadwick Motorized Trails Maintenance 09/01/2026-09/01/2027
Line Item Description Trail Name Trail No. Unit Quantity Unit
Price Comments
Trail 132A
Existing Trail
Restoration- Tread
Resurfacing and 50” tread width, clearing, hazard tree removal
(912.40), waterbar
(922), Drainage (920).
Chadwick 132A 21-132A LF 5888
Existing trail restoration along entire stretch of trail. See Trail log for specifications on work items needed.
Option Year 1
Option Year 2
Option Year 3
Option Year 4
Trail 131
Existing Trail
Restoration- Tread
Resurfacing and 50” tread width, clearing, waterbar (922) and drainage (920).
Chadwick 131 21-131 LF 4922
See Trail Log for specifications on tread leveling, deberming, and general maintenance needs.
Waterbar, ditch, and drain dip fall within existing trail restoration.
Option Year 1
Option Year 2
Option Year 3
Option Year 4
Trail 113 (Junction from 131)
Existing Trail
Restoration- Tread
Resurfacing and 50” tread width, clearing, waterbar (922), Berm
Chadwick 113 21-113 LF 5000
Existing trail restoration along entire stretch of trail. See Trail Log for reference. Drain dips, waterbar, and berm
Maintenance (926), and drain dip (927).
maintenance will be included line item. See
SOW and Trail log for specifications.
Option Year 1
Option Year 2
Option Year 3
Option Year 4
Option Bid Items A- Trail 101 to 119
Existing Trail
Restoration- Tread
Resurfacing and 50” tread width, clearing, drainage (920), and waterbar (922)
Chadwick 101 21-101 LF 25344
Existing trail restoration along entire stretch of trail. See SOW and Trail log for specifications.
Option Year 1
Option Year 2
Option Year 3
Option Year 4
Option Bid Items B- Trail 119 to 115
Existing Trail
Restoration- Tread
Resurfacing and 50” tread width, clearing, drainage maintenance/installation
(920).
Chadwick 119 21-119 LF 5103
Existing trail restoration along entire stretch of trail.