This is a Statement of Work (SOW) for asbestos mitigation work at three Rio Grande National Forest facilities in Colorado.
The contractor shall remove approximately 2,900 square feet of asbestos-containing building materials from ceilings, walls, windows, and flooring at the River Springs Office Apartment (Antonito, CO), Creede Assistant Ranger Dwelling (Creede, CO), and South Fork Bunkhouse Cabin (South Fork, CO). Work must be completed between October 30, 2026, and December 30, 2026. The specific asbestos locations include: South Fork bathroom flooring (60 sq ft); River Springs drywall texture (1,000 sq ft), popcorn ceiling (250 sq ft), drywall walls (250 sq ft), compound patches (25 sq ft), and window glaze on 10 exterior windows (25 sq ft); and Creede drywall walls and ceilings (1,250 sq ft combined). The contractor must hire an independent third-party to conduct air clearance testing post-abatement. Removed materials shall be replaced with drywall (Level 4 finish per Gypsum Association GA-214 Standards) for walls and ceilings, tongue-and-groove or engineered wood flooring for floors, and non-asbestos glaze for windows, all to match existing conditions. The contractor must be a Colorado-Certified General Abatement Contractor with a Colorado-Certified Competent Person overseeing all asbestos work, and all workers must be EPA and OSHA certified per 40 CFR Part 61 Subpart M and 29 CFR 1910.1001. The contractor is responsible for obtaining all State of Colorado permits, selecting a licensed landfill for asbestos disposal, and paying all associated fees. Deliverables include a detailed project schedule with day-by-day breakdowns, copies of permits and employee certifications, landfill location and disposal receipts, and air clearance testing reports. The Government shall provide asbestos testing reports and building access during work.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Amendment 0001
Contents Project General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards Attachment
Project Rio Grande National Forest Bunkhouse Asbestos Mitigation
General Information
1.0 Scope of Work
This project will involve the removal of approximately 2,900 square-feet of asbestos-containing building materials from ceilings, walls, windows, and flooring at three separate facility locations, cleaning the area of asbestos fibers, and the replacement of those building materials to include finishing and painting work. Work should be accomplished between the 30th of October and the 30th of December of 2026.
Contractor shall hire independent third-party to conduct air clearance after asbestos abatement activities before renovation work.
Additionally, the contractor shall paint the entirety of the existing interior walls and ceilings to match the existing color and condition.
Contractor shall build a schedule and complete the requirements in a logical order to prevent unsafe asbestos work and avoid repeat renovation work.
Contractor shall follow all laws and regulations governing asbestos work regardless if they are mentioned in the requirements.
2.0 Background
In January of 2026, an asbestos identification and testing contract was completed that confirmed the presence of asbestos in bunkhouses located on the Rio Grande National Forest. The Forest Service uses these bunkhouses for housing of seasonal and permanent employees. Due to the extensive use of some of these bunkhouses, there is a need to remove the asbestos-containing building materials in these facilities.
This project will require the removal of the identified asbestos-containing materials in a manner consistent with all laws and regulations governing the removal of asbestos. Additionally, the project will require the replacement of the walls, flooring, ceilings, etc. with suitable building material, i.e., drywall and wood flooring, and then the painting of replaced ceilings and walls.
Contractor Requirements
3.0 Technical Requirements / Tasks
The Contractor shall be required to remove the asbestos-containing building materials in the following Forest Service facilities:
Locations:
River Springs Office Apartment located at 24110 State Highway 17, Antonito, CO 81120 Creede Assistant Ranger Dwelling located at 505 Capital Ave., Creede, CO 81130 South Fork Bunkhouse Cabin located at 1243 County RD. 20, South Fork, CO 81154
Requirements:
Any building materials that will be disturbed or moved during the asbestos remediation process shall be prepared, removed, and/or replaced once asbestos remediation work is complete.
The Contractor shall only permanently remove the asbestos containing materials as listed in the provided Asbestos Testing Reports.
The Contractor shall remove and dispose of all asbestos-containing materials in a landfill licensed to accept and dispose of the asbestos-containing materials as required by 6 CCR 1007-2 Part 1, Section 5, The Colorado Solid and Hazardous Waste Commission’s Regulations Pertaining to Solid Waste disposal Sites and Facilities. The Contractor shall be responsible for choosing this site.
The Contractor and its employees must be licensed and accredited to remove the asbestos-containing materials as by the Environmental Protection Agency (EPA) and Occupational Safety and Health Administration (OSHA) as defined in 40 CFR Part 61, Subpart M, National Emission Standard for Asbestos and in 29 CFR 1910.1001, Asbestos.
The Contractor shall make all required notifications and obtain necessary permits required by the State of Colorado prior to starting work. The Contractor is responsible for all fees for permits and disposal of asbestos-containing materials.
The Contractor shall field-measure the removed areas of material and prepare the area for a suitable replacement building material.
The Contractor shall replace the removed building materials with a suitable replacement. In cases where wall or ceiling material is removed, the contractor shall replace with a drywall product and apply a Level 4 drywall finish as defined in the Gypsum Association’s GA-214 Standards. The texture of these areas shall be made to match as close as possible the existing texture on nearby walls/ceilings, unless otherwise directed by the COR.
Where asbestos-containing floor material is removed, the Contractor shall prepare the existing substrate to accept a tongue and groove plank wood or engineered wood flooring system. The system shall be installed according to manufacturers’ specifications to include any required underlayment or leveling system. The contractor shall field-verify the amount of material and, as closely as possible, match the existing plank size and color present in the facility. The Contractor shall obtain approval from the COR for the flooring planks before installation.
o If a wood flooring system is discovered under the asbestos-containing flooring materials, the Contractor shall instead refinish the existing wood flooring system to match the existing wood flooring materials.
Where Asbestos is removed from windowpane glazes, a suitable replacement shall be used and painted to match the existing conditions.
The Contractor shall hire an independent third-party to conduct final air clearance testing to confirm Asbestos fibers are not present.
The Contractor shall paint the new and existing wall and ceiling construction to match the existing colors. Paint shall be standard interior latex acrylic paint.
The Contractor shall reinstall or replace any non-asbestos-containing building materials that were removed or damaged in the location they were removed from.
Contractor shall be responsible for replacing and/or disposing of non-asbestos items that are damaged during demolition or renovation work.
Asbestos Amounts and Locations:
The Contractor shall only remove the Asbestos from the locations specified to contain asbestos as shown in the Testing Reports, any other materials that need to be temporarily removed or otherwise become damaged, shall be replaced after asbestos remediation is complete.
Asbestos Testing Reports have confirmed the presence of Asbestos-Containing materials in the following locations:
South Fork Bunkhouse Cabin – Bathroom Flooring – Two layers of vinyl flooring – approximately 60 square feet o Note: This is the only flooring requiring abatement.
River Springs Office Apartment – Drywall Texture Throughout Structure – 1000 square feet Kitchen and Bedroom Popcorn Ceiling – 250 square feet Kitchen and Bedroom Drywall Walls – 250 square feet Kitchen wall and ceiling compound patches – 25 square feet Window Glaze on Exterior Structure Windows -25 square feet o Note: Historic Exterior Requirements – Windows are multiple pane glass and are held with the Asbestos containing glaze, glaze must be removed and replaced with a non-asbestos glaze to preserve the look of the windows. There are 10 windows. The square footage is not of the windows themselves but the amount of glaze associated with the total number of windows. The windows are all reachable by a standard folding ladder and the tops of the windows are not more than 10 feet from the ground, possibly not more than 8 feet. There are 4 windows on the front of the building and 2 on each of the remaining 3 sides. (Amend 0001)
Creede Assistant Ranger Dwelling – Kitchen/Dining Room, Bedroom #1 and #2 Drywall Walls and Ceilings – 1000 square feet Bathroom Drywall walls and ceilings – 250 square feet
Contractor shall confirm locations and amounts through field measurements and the use of the plan-view maps in the asbestos testing reports.
4.0 Government Furnished
The Government shall provide the Asbestos Testing Reports that locate each instance of asbestos-containing materials in each facility.
5.0 Deliverables / Schedule
Contractor shall deliver the following:
1. A project schedule detailing the estimated completion dates for each stage of the project. i.e., When the first building asbestos cleanup setup is complete, when the asbestos removal is completed, when the renovations start, etc. This schedule should include day-by-day breakdowns of specific work. The timeframe should fall between the dates of the 30th of October and the 30th of December 2026.
2. Copies of all Permits required by the State of Colorado to do asbestos removal/renovation work.
3. Copies of all certifications of employees doing Asbestos removal work as evidence of competence.
4. The location of the licensed landfill and copies of disposal receipts.
5. Reports or receipts of air clearance testing requirements.
6.0 Travel
Locations:
River Springs Office Apartment located at 24110 State Highway 17, Antonito, CO 81120 Creede Assistant Ranger Dwelling located at 505 Capital Ave., Creede, CO 81130 South Fork Bunkhouse Cabin located at 1243 County RD. 20, South Fork, CO 81154
Driving times vary from 30 minutes between sites and accommodations to 1.5 hours to the nearest accommodations within local towns.
7.0 Contractor’s Key Personnel
Contractor must be a Colorado-Certified General Abatement Contractor (GAC) or must employ a sub-contractor certified as a Colorado-Certified General Abatement Contractor. The Contractor must prove that all workers doing Asbestos abatement work are certified by providing paperwork/credentials for each employee doing asbestos remediation work.
The Contractor shall have a Colorado-Certified Competent Person overseeing and managing all Asbestos related work.
8.0 Security Requirements
The COR will provide access to buildings during demolition and renovation.
9.0 Data Rights
N/A
10.0 Section 508 – Electronic and Information Technology Standards
N/A
Attachments
Attachments:
Asbestos Testing Reports for each facility