This Statement of Work (SOW) details a digital front-end upgrade project for the Bureau of Reclamation's Parker Dam power generation facility. The project involves replacing obsolete Basler ECS-2100 voltage regulators with current Basler DECS-2100 voltage regulators across four 30MW hydrogenating units. The contractor must provide a turnkey installation including all labor, parts, equipment, installation, commissioning, and personnel training.

The project is scheduled during the FY26 maintenance outage periods between October 2025 and February 2026, with specific annual inspection windows for each generator unit (P1-P4). Key requirements include providing a complete spare set of hardware components, using existing rectifier bridges, ensuring plug-and-play compatibility, and meeting specific technical performance criteria. The contractor must be Basler factory-trained technicians and will work at the Parker Dam Field Division in Parker, California, following strict security procedures and working primarily during normal business hours (Monday-Thursday, 7:00 a.m. to 4:30 p.m.).

View the file

Other files for this federal contract opportunity

Other files attached to PD- EXCITER DIGITAL FRONT END UPGRADE, newest first.
File Type Posted
Sol_140R3025R0012_Amd_0001.pdf PDF
Sol_140R3025R0012.pdf PDF
C05_140R3025R0012__RFP.pdf PDF
C05_Attachment_3_Bonds.pdf PDF
C05_Attachment_4_-_DI-137_Release_of_Claims.pdf PDF
B02_JOTFOC_Redacted.pdf PDF
C05_Attachment_2_Wage_Determination.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Proposal

140R3025R0012

Attachment 01

Statement of Work

Request for Proposal

140R3025R0012

This page intentionally left blank

Statement of Work

Exciter Digital Front End Upgrade Lower Colorado Dams Office

Parker Dam

This page intentionally left blank

General Information

The Bureau of Reclamation, Parker Dam and Power Plant is located at 2001 Parker Dam

Rd. Parker CA, 92267 in San Bernardino County California, Latitude: N 34° 17' 41.3844"

Longitude: W 114° 8' 24.9684".

Background

The Bureau of Reclamation (BOR) Parker Dam has 4- 30MW Francis style turbine hydrogenators equipped with Eaton/ Basler static excitation cabinets. These excitation cabinets were installed between 2005 and 2011 and require the voltage regulators on all (4) generator units to be refurbished. The current voltage regulators are Basler ECS-2100. The main processor chip on the Basler ECS-2100 is obsolete and cannot be repaired, replaced nor is it supported anymore and is a known point of failure. Reclamation is looking to replace the Basler ECS-2100 with the current Basler Regulator DECS-2100 as well as the other associated components included in the BASLER DECS-2100 digital exciter controller upgrade.

Scope of Work

Overview- Provide the retrofit of the current Basler ECS-2100 voltage regulators with current Basler DECS-2100 voltage regulators conversion kit. Vendor shall provide a turnkey installation to include all labor, parts, equipment to install, commission, and train personnel on the four 30MW hydrogenating units at Parker Dam.

Requirements

Digital front end retrofit the current Basler ECS-2100 voltage regulators to DECS-2100 voltage regulator on generator units P-1, P-2, P-3, P-4 with installation, commissioning, and training. Also provide a complete spare 5th set of all hardware components

(programmed) and cables associated with DECS-2100 Front-End Upgrade Kit programmed for future and a minimum of 1 spare Magnum DS MDS816 Exciter Breaker.

This requirement must meet the following criteria:

1. Provide the current version of Basler BESTCOMS™ Pro Controller configuration tool

2. Auto tuning of control loops

3. Must use existing rectifier bridge.

4. Plug and play replacement.

a. Compatible with existing analog to digital I/O boards

5. All equipment must fit within existing equipment footprint for all four units.

6. Research of the existing Generator Control System to finalize Installation Details.

7. The existing ECS2100 controller utilizes a throughput sampling rate of 1kHz (the code reads inputs, executes excitation system and power system stabilizer code and updates the outputs ever 1 millisecond). Any replacement controller must meet or exceed this performance requirement.

8. Removal of the existing ECS2100 control equipment and Installation of the new

Basler Electric DECS-2100 Front-End Retrofit.

9. Supply any additional cabinet wiring, which may be needed, with regard to the installation of the new Basler Electric Exciter System.

10. Provide the “Interface Design” of the new Systems including:

a. Provide all revisions to the existing Elementary System Drawing Package of the Generator Control and Voltage Regulator Systems.

b. Connection details for all new devices as supplied by contractor to be installed in the new Regulator Control Panel.

c. System Connection Drawings.

d. Wiring Lists of wires to be removed, wires to be reused and new wire to be added.

e. Interface details for direct connection of the new excitation equipment to the existing Control System and details on existing equipment to be removed from service.

f. Voltage Regulator Control System Settings.

g. Digital Documentation Package to include.

▪ a. Instruction Manuals for all equipment of the new Basler Electric

Systems.

▪ b. As Built Digital Drawings (per above in items 10a – 10f), supplied in AutoCAD (dwg format).

▪ c. Startup Report, including all Software Settings.

11. Provide On-Site Turnkey Services by Basler factory trained Technical Expert with regard to the Installation, Connection and Interconnection of the new Basler

Electric Systems.

a. Remove the ECS2100 equipment.

b. Install the new DECS-2100 Front-End retrofit in the existing exciter cabinet.

c. Interface with the existing Generator Control, Protection and Annunciator

Systems.

d. Provide System Checkout / Testing of all new equipment, devices and interconnection cables.

12. Provide System Startup Services

a. Shut-down (Unit at standstill) checks with external equipment – DCS, Remote Switches, etc.)

b. Off-Line (Rated Speed No-Load) Set-Up and Testing of the new Voltage

Regulator Control System.

c. On-Line (With Load) Set-Up and Testing of the new Voltage Regulator

Control System

13. Provide the “final” System Startup Report with regard to the commissioning of the new Basler Electric Type DECS-2100 System.

14. On-Site Commissioning Tests

a. Pre-Excitation System Checks (Unit @ Standstill)

▪ Wire Checks / Ground Checks of the new System

▪ Control I/O Testing & Sequence Testing

▪ Loss of PT Signal Transfer Testing

▪ Excitation Simulation Checks (Dummy Load Test)

▪ Current & Voltage Signal Injection

▪ Unit Annunciation Alarm Checks

▪ DCS Interface Checks

▪ System “Trip” Tests

▪ DECS Module Software Setup

b. Off-Line, Full Speed No-Load System Checks

▪ AVR “Automatic Voltage Regulator” Start Sequence

▪ FCR “Field Current Regulator” Start Sequence

▪ AVR Step Response Testing & FCR Step Response Test

▪ Off-Line OEL Overexcitation Limiter Stability Step Test

▪ Saturation Curve Testing

c. On-Line System Tests

▪ AVR Step Response Test & FCR Step Response Test

▪ On-Line OEL Overexcitation Limiter Stability Step Test

▪ UEL Under-excitation Limiter Settings & Stability Step Test

15. In addition to the retrofit also include the replacement of the following devices, for each of the 4 Generator Excitation System Upgrades:

a. Qty.2- BCM-2, 2nd Generation Bridge Control Module

b. Qty.2- IT-2, Isolation Transducer for Bridge

c. Qty.6- Conduction Monitors, phase current at input to frame bridge Part number 9427107101

d. Qty.4- DIOM-2, 2nd Generation Digital I/O Module

e. Qty.4- AIOM-2, 2nd Generation Analog I/O Module

f. Qty.4- IT-2, 2nd Generation Isolation Transducer

g. Qty.2- DXCB-2, 2nd Generation De-Excitation & Crowbar Module

h. Qty.1- FGD-2, 2nd Generation Field Ground Detector Module

i. Qty.1- BE1-FLEX Protective Relays Style: K – T3 N0 N0 N0 – W9 – E5 –

1N0 – E01N

j. Complete set of spares of all the above listed parts a.- i.

16. Include backups to all programs to include changes made during commissioning.

Prior to leaving work site at project completion.

DELIVERABLES

The Contractor shall supply the Bureau of Reclamation with As-Built drawings for all work performed. These drawings shall be AutoCAD drawings in electronic format (.dwg file extension). Drawings shall be provided prior to Contractor leaving the site at the completion of the contract.

LOCATION

Delivery and installation will be at:

Parker Dam Field Division

2001 Parker Dam Road

Parker Dam, California 92267

PERFORMANCE PERIOD

Contractor must provide lead time for all parts and estimated installation time.

Installation will occur during and align with the FY26 maintenance outages season, this schedule is below. No sooner than October 1, 2025. Installation and commissioning must be completed at least 4 days prior to the end of the outage schedule to allow for closing of outage.

FY 26 MAINTENANCE YEAR

P3 Annual Inspection 10/1/25 6:30 AM 11/14/25 5:00 PM

NERC/WECC TESTING

P4 Annual Inspection 11/17/25 6:30 AM 12/11/25 5:00 PM

P1 Annual Inspection 1/5/26 6:30 AM 1/30/26 5:00 PM

P2 Annual Inspection 2/2/26 6:30 AM 2/27/26 5:00 PM

WORK HOURS

Normal work hours are Monday through Thursday, except federal holidays, 7:00 a.m. to 4:30 p.m.

If work needs to be done outside these hours the contractor must request from the CO or COR in advance.

CLEANUP AND DISPOSAL OF WASTE MATERIAL

Any viable spare parts removed from the exciting excitation cabinets will remain property of the

Bureau of Reclamation and will be turned over prior to the project being deemed completed.

The contractor shall be responsible for all cleanup of waste materials or rubbish and will also be responsible for disposal of all waste materials that have special restrictions or considered hazardous materials if not a viable spare part. Disposal shall be in accordance with this paragraph and all applicable Federal, State, and local regulations, standards, codes and laws. Also, the requirements contained in the Bureau’s “Reclamation Safety and Health Standards” are applicable to clean up and to dispose waste materials and rubbish. In the event that there is a conflict between the requirements contained in this paragraph, the Bureau’s “Reclamation Safety and Health

Standards”, and other Federal, State, or local regulations, standards, codes, and laws, the more stringent requirements shall prevail.

SITE CONDITIONS

Contractors will have access to water, electricity, and restrooms while on site. There will be no asbestos in any of the areas where the contractors will work.

SECURITY

All service locations under this contract are within secured areas. The COR will arrange for the

Contractors entry into such areas and inform the Contractor of security procedures. The Contractor shall comply with all security procedures.

The Contractor shall supply the Bureau of Reclamation with the legal names of all employees who will be working under this contract. The Bureau of Reclamation reserves the right to run security checks on such employees. If, in the judgment of the Bureau of Reclamation, any employee fails to meet minimum security requirements or proves to be detrimental to the security of the Bureau of Reclamation facilities, the Contractor, upon request, shall remove such employee from any work under this contract.

Powerplant control room is a restricted access area and only can be entered if escorted by an authorized Reclamation employee.

CONTRACTOR QUALIFICATIONS

Must be Basler factory trained technicians to perform all work. The technicians should be able to provide Basler certifications or Basler Identification.