This is a Statement of Work (SOW) for the Pike Underground Utility Upgrade project issued by the USDA Forest Service, Region 2, for Pike-San Isabel National Forests & Cimarron and Comanche National Grasslands. The project encompasses utility infrastructure upgrades at four Forest Service administrative sites located in Colorado: Lake George Work Center (South Park Ranger District), Monument Fire Center (Pikes Peak Ranger District), Fairplay Work Center (South Park Ranger District), and AG Ranch (South Platte Ranger District).
The scope of work includes: installation of new sanitary sewer service lines and pressurized septic system at Lake George; installation of new sanitary sewer service line and replacement of water hydrants at Monument Fire Center; replacement of deteriorated waterline serving the shop building at Fairplay Work Center; and replacement of septic tanks at AG Ranch. All work includes associated tasks such as mobilization, quality control, surveying and staking, utility demolition and abandonment, excavation, trenching, backfill, grading, temporary erosion control, and site surface restoration. The contractor must furnish all labor, materials, equipment, tools, transportation, supplies, and storage necessary for completion. Additional requirements include providing temporary toilet facilities, implementing a weekly trash abatement program, and delivering four key deliverables: a construction schedule due at the prework conference, material and equipment submittals during construction, quality control reports throughout construction, and as-built drawings prior to final inspection. The total period of performance extends from award until November 30, 2026, with work prohibited during frozen or saturated ground conditions anticipated October through April. Site elevations range from 7,100 feet to 9,900 feet, and the contractor must designate a Project Manager and Project Superintendent to oversee contract performance. Water and electricity will be government-furnished at the sites, and work scheduling restrictions prohibit holidays, weekends, and hours between 6 p.m. and 7 a.m.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 1240LT26Q0090_A0002_Final.pdf | ||
| 1240LT26Q0090_A0001_Final.pdf | ||
| C05_Attach 4_PUUU_Drawings.pdf | ||
| C05_Attach 1_SOI_PUUU.xlsx | XLSX spreadsheet | |
| C05_Attach 3_PUUU_Con Manual.pdf | ||
| 1240LT26Q0090_Final.pdf | ||
| C05_Attach 5_WD-CO20260019-28.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PIKE UNDERGROUND UTILITIES UPGRADE
PIKE-SAN ISABEL NATIONAL FOREST
& CIMARRON AND COMANCHE NATIONAL GRASSLANDS
UNITED STATES
DEPARTMENT OF
AGRICULTURE
FOREST SERVICE
REGION 2
PIKE - SAN ISABEL
NATIONAL FORESTS &
CIMARRON AND
COMANCHE NATIONAL
GRASSLANDS
SOUTH PARK, PIKES
PEAK, & SOUTH
PLATTE RANGER
DISTRICTS
May 1st, 2026
Pike Underground Utility
Upgrade
Statement of Work
Project
Pike Underground Utility Upgrade
Pike-San Isabel National Forests & Cimarron and Comanche National Grasslands
South Park, Pikes Peak, & South Platte Ranger Districts
General Information
1.0 Project Location
This project consists of work at “4” Forest Service administrative sites on the Pike-San Isabel National
Forests & Cimarron and Comanche National Grasslands:
a. Lake George Work Center
South Park Ranger District
140 Trail Creek Road
Lake George, CO 80827
b. Monument Fire Center
Pikes Peak Ranger District
3751 Mt. Herman Road
Monument, CO 80132
c. Fairplay Work Center
South Park Ranger District
310 2nd Street
Fairplay, CO 80440
d. AG Ranch
South Platte Ranger District
56052 S Hwy 285
Shawnee, co 80475
These sites are open and accessible year-round by highway legal vehicles. Winter conditions (freezing temperatures, snow fall, frozen ground, etc.) can be anticipated approximately October through April.
2.0 Scope of Work
The project scope of work generally consists of the following:
a. Lake George Work Center
i. Installation of new sanitary sewer service lines from the Brown House and Office buildings to new pressurized septic system.
ii. Associated and ancillary work includes mobilization, quality control, project management and coordination, utility abandonment/demolition, site demolition, excavation, trenching, backfill, and site surface restoration.
iii. Refer to the Project Manual/Specification and Construction Drawings for a full depiction of the work.
b. Monument Fire Center
i. Installation of new sanitary sewer service line from the Classroom Building to an existing sewer manhole.
ii. Removal and replacement of existing site water hydrants.
iii. Associated and ancillary work includes mobilization, quality control, project management and coordination, utility abandonment/demolition, site demolition, excavation, trenching, backfill, and site surface restoration.
PIKE-SAN ISABEL NATIONAL FOREST
& CIMARRON AND COMANCHE NATIONAL GRASSLANDS
iv. Refer to the Project Manual/Specification and Construction Drawings for a full
c. Fairplay Work Center
i. Replacement of waterline that feeds “shop” building
ii. Associated and ancillary work includes mobilization, quality control, project management and coordination, utility abandonment/demolition, site
d. AG Ranch
i. Replacement of septic tanks that service office and bunkhouse
ii. Associated and ancillary work includes mobilization, quality control, project management and coordination, utility abandonment/demolition, site
3.0 Background
a. The existing sewer line at Lake George is made of clay pipe and the joints have become offset overtime allowing for root penetration into the sewer line. This results in clogging issues that must be regularly cleaned. The existing field seems to no longer be accepting wastewater at the rate that is needed. The new sewer line and leach field will resolve this issue.
b. The existing sewer line at Monument is too shallow and generally freezes over the winter which renders the bathroom facilities in the Classroom building unusable. A new sewer line installation at a greater depth will be required to resolve this issue.
c. The existing waterline at Fairplay Work center that feeds the shop building has deteriorated and needs to be replaced.
d. The septic tanks at AG ranch are in poor condition and need to be replaced. The other components of the systems seem to be working
e. These sites are open and accessible year-round by highway legal vehicles.
f. Approximate site elevations are approximately 8,100 feet at Lake George, 7,100 feet at
Monument, 9,900 feet at Fairplay Work center, and 8,100 at AG Ranch.
g. Winter conditions (freezing temperatures, snow fall, frozen ground, etc.) can be anticipated approximately October through April.
h. Cellular phone service is generally available at all sites.
General Information
4.0 Technical Requirements / Tasks
Generally work will consist of the following tasks:
• Mobilization;
• Quality Control, Survey, and Staking;
• Construction and upgrading of utilities including sanitary sewer and water;
• Site/utility demolition and abandonment, grading, temporary erosion control, and surfacing replacement;
Construction includes furnishing all labor, materials, equipment, tools, transportation, supplies, storage, other incidentals to complete the sewer line repairs, leach field, waterlines, septic tank replacement, and all other work associated with these repairs in accordance with the approved final drawings, specifications and provisions of the contract.
PIKE-SAN ISABEL NATIONAL FOREST
& CIMARRON AND COMANCHE NATIONAL GRASSLANDS
Construction quality control includes supplying all the personnel, equipment, special inspections, tests, and reports necessary to ensure that construction is completed in compliance with the drawings, specifications, and provisions of the contract.
The Contractor shall provide temporary toilet facilities (porta-potty) at the site during all construction work.
A trash abatement program shall be initiated during pre-construction phases of the project and shall continue through the duration of the project. All construction refuse shall be removed from the site and disposed of properly on a weekly basis and upon project completion.
5.0 Government Furnished
a. Water and electricity are available at the site(s) for construction purposes.
b. The Government will provide all necessary inspections.
c. Work shall not be scheduled on holidays, weekends, and between the hours of 6pm and 7am.
d. Refer to Project Manual/Specifications for additional information.
6.0 Period of Performance
The total period of performance allowed for completion of all contracted activities shall be from the date of the award until 11/30/2026. Winter conditions which may impede utility and earthwork activities can be anticipated approximately from October to April. Work during frozen or saturated conditions will not be allowed.
7.0 Deliverables / Schedule
KEY DELIVERABLES
Item
No.
Deliverable Objective Due
1 Construction
Schedule
Defining the responsibilities, timeline, risks, and milestones of contract objectives.
No later than the date of the prework conference
2 Material and
Equipment
Submittals
All material specifications, product data, manufacturer’s instructions, and material safety data sheets
During construction according to schedule
3 Quality Control
Reports
Materials testing, construction observation, and special inspections documenting compliance with the Contract Documents.
During construction as indicated
4 As-built Drawings Drawings that recognize any changes in the plans, specifications, and/or approved submittal of equipment supplied
Prior to final inspection
PIKE-SAN ISABEL NATIONAL FOREST
& CIMARRON AND COMANCHE NATIONAL GRASSLANDS
8.0 Travel
All costs associated with travel to and from the job site, including mobilization of all equipment and materials shall be included in the Contractor’s cost proposal.
9.0 Contractor’s Key Personnel
Project Manager – individual designated by the General Contractor, serves as primary points of contact and shall have overall responsibility for managing and coordinating the performance of the Contractor’s obligations under this contract, including performance of all Subcontractors, and be authorized to act for and bind Contractor and Subcontractors in connection with all aspects of this contract.
Project Superintendent – onsite representative of the General Contractor, responsible for overall management of the project and capable of discussing technical aspects of the project. Project
Superintendent may also fill Project Manager role at the Contractor’s discretion.
The scope of this project does not require a dedicated QC person. That role may be filled by the Project
Superintendent or the Project Manager at the Contractor’s discretion.
10.0 Site Visit
The Site visit will begin at Lake George Work Center and the other locations will be available for tour based on interested parties request. See Solicitation for Site Visit Details:
11.0 Attachments
See Solicitation for attachments