C04a_Att 1-SOW_12445526Q0126.pdf
PDF 222 KB Posted
- Attached to
- GMF Hapgood Pond Dam Spillway Bridge Support Federal contract opportunity
- Solicitation number
- 12445526Q0126
- Issued by
- Department of Agriculture Forest Service
About this file
This is a Statement of Work (SOW) for the US Department of Agriculture (USDA) concerning construction support services for the Hapgood Pond Dam Spillway project.
The contractor shall furnish all labor, materials, services, and equipment to build bridge supports over the Hapgood Pond Dam. Work scope includes cleaning and preparing existing concrete and wingwall surfaces, drilling and grouting rebar into existing concrete, placing rebar and forms, and placing new concrete bridge supports. The work addresses horizontal cracking identified during a recent inspection of the bridge wingwall. The contractor must perform all work in accordance with Forest Service Supplemental Specifications to the FP-24, Federal Highway FP-24 Specifications, and provided drawing plans. Completion of all work is required within 120 days of Notice to Proceed, with work to be performed after the pond is drained in fall and before it is refilled in spring. The contractor must submit a project schedule for government approval prior to receiving the Notice to Proceed. All travel expenses to the project site and during construction shall be included in mobilization and demobilization costs. The contractor must assign workers with experience in construction, specifically those with road construction and culvert installation experience. The government will not furnish any equipment, materials, or supplies. No specific security requirements apply to this project. Data rights are not applicable. Section 508 accessibility requirements apply to all project communications and documents but not to information technology supply.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| C08_QAmemo-12445526Q0126.pdf | ||
| C04d_Att 4-DBAWD_VT20260049_12445526Q0126.pdf | ||
| C04_RFQ_12445526Q0126.pdf | ||
| C04b_Att 2-Plans_12445526Q0126.pdf | ||
| C04e_Att 5-Fillable SOI_12445526Q0126.xlsx | XLSX spreadsheet | |
| C04c_Att 3-Supp Specs_12445526Q0126.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Contents Project General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards
Project Hapgood Pond Dam Spillway Support
General Information
1.0 Scope of Work
The intent of this project is to furnish all labor, materials, services and equipment to make build supports for the bridge over the Hapgood Pond Dam. The project work shall generally include, but is not limited to: cleaning and preparing the existing concrete, wingwall surface, drilling and grouting rebar into existing concrete, placing rebar and forms, and placing new concrete bridge supports.
2.0 Background
Horizontal cracking was noted during a recent inspection of the bridge over Hapgood Pond Dam at the wingwall that supports the bridge.
Contractor Requirements
3.0 Technical Requirements / Tasks
The contractor shall perform all work as described in the Forest Service Supplemental Specifications to the FP-24, the Federal Highway FP-24 Specifications, and the drawing plans.
4.0 Government Furnished
The Government will not furnish any equipment, materials or supplies for this project.
5.0 Deliverables / Schedule
• Contractor shall complete all work within 120 days of Notice to Proceed.
• The Contractor shall submit a project schedule to the government for consideration and approval prior to receiving a notice to proceed.
• The Contractor shall perform all work after the pond has been drained this fall and before it is filled in the spring.
6.0 Travel
Travel expenses to the project site and during construction shall be included in the mobilization/demobilization costs for the project.
7.0 Contractor’s Key Personnel
The Contractor shall assign workers who are experienced in construction to complete the described project. The personnel shall be experienced with road construction and culvert installation.
8.0 Security Requirements
This project does not have any specific security requirements.
9.0 Data Rights
None.
10.0 Section 508 – Electronic and Information Technology Standards Supply of Information technology is not part of this contract, so Section 508 requirements are not required for information technology. Section 508 requirements for all project communication and documents shall be followed.
| Project |
| General Information |
| 1.0 Scope of Work |
| 2.0 Background |
| Contractor Requirements |
| 3.0 Technical Requirements / Tasks |
| 4.0 Government Furnished |
| 5.0 Deliverables / Schedule |
| 6.0 Travel |
| 7.0 Contractor’s Key Personnel |
| 8.0 Security Requirements |
| 9.0 Data Rights |
| 10.0 Section 508 – Electronic and Information Technology Standards |