C08_QAmemo-12445526Q0126.pdf

PDF 293 KB Posted

Attached to
GMF Hapgood Pond Dam Spillway Bridge Support Federal contract opportunity
Solicitation number
12445526Q0126
Issued by
Department of Agriculture Forest Service

About this file

This is a Questions and Answers memorandum for RFQ 12445526Q0126 issued by the United States Forest Service Procurement Operations (PROPS) East Zone Team 3 Construction on 27 August 2026. The document addresses four clarifying questions from prospective contractors regarding a construction project involving work on a pond and bridge structure.

The document provides key project logistics and contractor responsibilities. The pond will be drained on or around 13 October and refilled in mid-May, with the pond remaining fully drained during the construction period. A Notice to Proceed will be issued as soon as practicable following award, with projected performance start dates included in the Solicitation. Water will continue to flow through a gate but will not affect the construction area, eliminating the need for bypass pumping, diversion, or dewatering. Site access is limited to an approximately 5-foot-wide hard pack trail with staging available in a parking lot at the trail's beginning. Concrete pump trucks cannot access the site, requiring contractors to either carry concrete along the trail with appropriately sized equipment or mix concrete on site. Contractors are responsible for all concrete sampling, test cylinders, laboratory testing, and associated costs. The document was signed by Matthew L. Killian, Contracting Officer for USFS PROPS EZ 3 CONS.

View the file

Other files for this federal contract opportunity

Other files attached to GMF Hapgood Pond Dam Spillway Bridge Support, newest first.
File Type Posted
C04c_Att 3-Supp Specs_12445526Q0126.pdf PDF
C04d_Att 4-DBAWD_VT20260049_12445526Q0126.pdf PDF
C04e_Att 5-Fillable SOI_12445526Q0126.xlsx XLSX spreadsheet
C04_RFQ_12445526Q0126.pdf PDF
C04a_Att 1-SOW_12445526Q0126.pdf PDF
C04b_Att 2-Plans_12445526Q0126.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNITED STATES FOREST SERVICE

PROCUREMENT OPERATIONS (PROPS)

EAST ZONE (EZ) TEAM 3 CONSTRUCTION (CONS)

27 August 2026

MEMORANDUM FOR RFQ 12445526Q0126

FROM USFS PROPS EZ 3 CONS

SUBJECT: RFQ 12445526Q0126 Questions & Answers

1. Question: “Please provide the anticipated dates for pond drawdown, Notice to Proceed, and spring refill. Will the pond remain fully drained throughout the construction period?”

Answer: “Pond is expected to be drained on or around October 13th and will be refilled in mid-May.

A Notice to Proceed is expected to be issued as soon as practicable, following award. Projected Period of Performance start dates are included in the Solicitation. The pond can remain fully drained during construction.”

2. Question: “Should the contractor anticipate residual water flow through the spillway? If so, please provide the anticipated flow and clarify whether bypass pumping, diversion, or dewatering is required.”

Answer: “Water will continue to flow through the gate but will not affect the construction area.”

3. Question: “What equipment-access and staging areas will be available? Can a concrete pump truck be positioned on or immediately adjacent to the bridge?”

Answer: “Site access is by an approximately 5 foot wide hard pack trail. Staging can occur in the parking lot at the beginning of the trail. A pump truck will not be able to access the site and concrete will either need to be carried to the location along the trail with appropriately sized equipment or mixed on site.”

4. Question: “Who is responsible for concrete sampling, test cylinders, laboratory testing, and associated costs?”

Answer: “Concrete sampling and testing is the responsibility of the contractor.”

MATTHEW L KILLIAN

Contracting Officer

USFS PROPS EZ 3 CONS