This is a 50 Divisions Construction Cost Estimate template in CSI (Construction Specifications Institute) format, designed for the Juniper Springs Boardwalk Replacement project located at Juniper Springs Recreational Area in Silver Springs, Florida. The spreadsheet template is structured to facilitate contractor cost estimation across 50 construction divisions, with prefilled division sheets for specific work elements related to the boardwalk project. Key cost categories include Division 01 (General Requirements), Division 02 (Existing Conditions/Demolition), Division 03 (Concrete), Division 05 (Metals—structural steel and railings), Division 06 (Wood, Plastics and Composites—wood decking and finish carpentry), Division 10 (Specialties—foundation pier pins), Division 31 (Earthwork/Excavation and Fill), Division 32 (Exterior Improvements/Plants and Pruning), and Division 35 (Waterways and Marine Construction—Fern Hammock Pedestrian Bridge and Juniper Creek Kayak Launch). The template includes line items for labor and material costs separated by unit, with automatic calculation functionality for subcontractor overhead and profit percentages, Florida State sales tax (6%), and risk/bonding adjustments.

The spreadsheet accommodates multiple cost scenarios through prefilled funding categories (Funding A and Funding B) for certain divisions and allows contractors to add missing items or additional divisions as needed without deleting prefilled elements. The template provides fields for project number, estimator name, design basis code selection (ranging from no design to final design), and summary-level inputs for general contractor overhead and profit percentages that automatically populate across all division tabs. A secondary worksheet includes haul distance calculations for aggregate material transport costs using variables for truck type, speed, road segments, and quantity. Instructions emphasize that all shaded cells contain formulas and linked data, requiring users to save copies before editing to prevent formula corruption.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions Use the information from the prefilled division sheets below to complete the 50 Divisions Cost Estimate CSI* Format tool to build your proposal. The information from the prefilled division sheets may not be all inclusive. The contractor is allowed to include any missing items from each division and is allowed to fill in other divisions that are not listed in the prefilled division sheets. If there is a disagreement with the prefilled division sheets, the contractor should not delete the element(s), but instead leave it blank and then include their suggested element(s) at the bottom of that division tab. Please note that on the summary page there is a place to fill in overhead and profit percentages for both the prime and the subcontractor that will self-populate the summary page and all the division tabs.

Exceptions:

(1) if each subcontractor has a different overhead and profit rates than the percentage placed on the summary page, an adjustment will have to be made to that specific division page. The spreadsheet will still calculate correctly.

(2) If the prime is self-performing the work for that division then the profit and overhead will need to be zeroed for that particular division, because the primes overhead and profit is already captured on the summary page.

The ktr is required to complete the areas marked "Fill Here" in the summary tab. The rest of the information in the summary tab will automatically tabulate from the individual division tabs except for the few exceptions listed above.

Divisions 1, 2, and 3 show sample inputs to illustrate how the spreadsheet works.

* CSI = Construction Specifications Institute

$107,536.00
$96,655.60
$81,126.60
$65,597.60
$65,597.60
$65,597.60
$80,472.40
$80,472.40
$40,236.20
$72,384.00
$41,708.00
$797,384.00

&"Verdana,Bold"Construction Cost Estimate

&P of &N

Summary Schedule of Items DATE: Date:

COMPANY
USDA FOREST SERVICE - National Forests of Florida

PROJECT FILL IN AS REQUIRED (this will link to the entire document) davisjam: davisjam:

Percentages listed are place fillers. Please complete as required

Juniper Springs Boardwalk Replacement
LOCATIONPROJECT NO.Fill Here
Juniper Springs Recreational Area- 26701 FL-40, Silver Springs, FL 34488
DIVISIONSUB-DIVISIONSDESCRIPTIONUNITSUNIT MEASURECOSTTOTAL COST% by
DivisionDivision Total
DIVISION 01GENERAL REQUIREMENTS$0.00GC Overhead
01 40 00QUALITY REQUIREMENTSGC Profit
01 45 00QUALITY CONTROL1LS$0.00Sub Overhead
01 45 00 aQUALITY CONTROL - FUNDING A1LSSub Profit
01 45 00 bQUALITY CONTROL - FUNDING B1LSSales Tax
01 50 00TEMPORARY FACILITIES AND CONTROLSRisk/Bonding
01 56 23TEMPORARY BARRICADES & FENCING1LS$0.00
01 56 23TEMPORARY BARRICADES & FENCING - FUNDING A1LSThis spreadsheet contains many formulas... please save a copy prior to editting in case you make a mistake. All shaded areas are either linked or contain formulas
01 56 23TEMPORARY BARRICADES & FENCING - FUNDING B1LS
01 57 13TEMPORARY SEDIMENT & EROSION CONTROL1LS$0.00
01 57 13TEMPORARY SEDIMENT & EROSION CONTROL - FUNDING A1LS
01 57 13TEMPORARY SEDIMENT & EROSION CONTROL - FUNDING B1LS
DIVISION 02EXISTING CONDITIONS- 0
02 20 00ASSESSMENT- 0
02 21 13SITE SURVEY1LS
02 41 00DEMOLITION AND STRUCTURE MOVING$0.00
02 41 13SELECTIVE SITE DEMOLITION1LS
02 41 19SELECTIVE DEMOLITION, DISPOSAL1LS
DIVISION 03CONCRETE$ - 0
03 11 00CONCRETE FORMING- 0
03 11 13STRUCTURAL CAST-IN-PLACE CONCRETE - AUGURED PILES1LS
03 30 00CAST-IN-PLACE CONCRETE- 0
03 30 53MISCELLANEOUS CAST-IN-PLACE CONCRETE - FREESTANDING POSTS1LS
DIVISION 04MASONRY
DIVISION 05METALS$ - 0
05 12 00STRUCTURAL STEEL FRAMING- 0
05 12 23.17COLUMNS, STRUCTURAL - STEEL POSTS ON PIER PINS1LS
05 12 23.20CURB EDGING - KICKPLATE @ GENERAL / RAILING LOCATIONS1LS
05 12 23.40LIGHTWEIGHT FRAMING - DECK FRAME1LS
05 50 00STEEL FABRICATION- 0
05 50 59METAL SPECIALTIES - ALL STL MATERIALS FABRICATED1LS
05 73 00DECORATIVE METAL RAILINGS$0.00
05 73 23RAILINGS - ARCHITECTURAL1LS
DIVISION 06WOOD, PLASTICS AND COMPOSITES1LS$ - 0
06 15 00WOOD DECKING- 0
06 15 13WOOD FLOOR DECKING - CUMARU WOOD DECK1LS
06 20 00FINISH CARPENTRY- 0
06 20 13EXTERIOR FINISH CARPENTRY - HANDRAIL1LS
DIVISION 07THERMAL AND MOISTURE PROTECTION
DIVISION 08OPENINGS
DIVISION 09FINISHES
DIVISION 10SPECIALTIES$ - 0
10 70 00EXTERIOR SPECIALTIES- 0
10 74 00MANUFACTURED EXTERIOR SPECIALTIES - FOUNDATION PIER PINS1LS
DIVISION 11EQUIPMENT
DIVISION 12FURNISHINGS
DIVISION 13SPECIAL CONSTRUCTION
DIVISION 14CONVEYING EQUIPMENT
DIVISION 15RESERVED
DIVISION 16RESERVED
DIVISION 20RESERVED
DIVISION 21FIRE SUPRESSION
DIVISION 22PLUMBING
DIVISION 23HEATING, VENTILATING AND A/C
DIVISION 24RESERVED
DIVISION 25INTEGRATED AUTOMATION
DIVISION 26ELECTRICAL
DIVISION 27COMMUNICATIONS
DIVISION 28ELECTRONIC SAFETY AND SECURITY
DIVISION 29RESERVED
DIVISION 30RESERVED
DIVISION 31EARTHWORK$ - 0
31 20 00EARTH MOVING- 0
31 23 00EXCAVATION & FILL1LS
DIVISION 32EXTERIOR IMPROVEMENTS$ - 0
31 93 00PLANTS- 0
32 93 43TREES - PRUNING -WITHIN CONSTRUCTION ZONE1LS
DIVISION 33UTILITIES
DIVISION 34TRANSPORTATION
DIVISION 35WATERWAYS AND MARINE CONSTRUCTION$ - 0
35 05 00COMMON WORK RESULTS FOR WATERWAY & MARINE CONSTRUCTION
35 05 40COMMON WORK RESULTS FOR WATERWAY CONSTRUCTION- 0
35 05 40.1FERN HAMMOCK PEDESTRIAN BRIDGE - TRUSS BRIDGE1LS
35 05 40.2JUNIPER CREEK KAYAK LAUNCH - INCLUSIVE OF ACCESSORIES1LS
DIVISION 36RESERVED
DIVISION 37RESERVED
DIVISION 38RESERVED
DIVISION 39RESERVED
DIVISION 40PROCESS INTEGRATION
DIVISION 41MATERIAL PROCESING AND HANDLING EQUIPMENT
DIVISION 42PROCESS HEATING, COOLING AND DRYING EQUIPMENT
DIVISION 43PROCESS GAS & LIQUID HANDLING, PURIFICATION AND STORAGE EQUIPMENT
DIVISION 44POLLUTION CONTROL EQUIPMENT
DIVISION 45INDUSTRY-SPECIFIC MANUFACTURING EQUIPMENT
DIVISION 46RESERVED
DIVISION 47RESERVED
DIVISION 48ELECTRICAL POWER GENERATION
DIVISION 49RESERVED
HARD COST TOTAL$0.00

&"Verdana,Bold"Construction Cost Estimate

Div1

CONSTRUCTION COST ESTIMATE DATE

PROJECTBASIS FOR ESTIMATE
Juniper Springs Boardwalk ReplacementCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
Juniper Springs Recreational Area Silver Springs, FloridaCODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
USDA Forest Service - National Forests of FloridaXXXXXXXXX
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
DIVISION 1 - GENERAL REQUIREMENTS
01 45 00 Summary- 0$0.00$0.00
01 45 00 Quality ControlLS- 0$0.00$0.00
01 56 00 Temporary Facilities & Controls- 0$0.00$0.00
01 56 23 Temporary Barricades & FencingLS- 0$0.00$0.00
01 57 00 Temporary Controls
01 57 13 Temporary Sediment and Erosion ControlLS
- 0$0.00$0.00
- 0$0.00$0.00
- 0$0.00$0.00
- 0$0.00$0.00
- 0$0.00$0.00
- 0$0.00$0.00
- 0$0.00$0.00
- 0$0.00$0.00
- 0$0.00$0.00
- 0$0.00$0.00
TOTAL LABOR/MATERIALS- 0$0.00$0.00
SUBTOTAL- 0$0.00
Sub-Contractor's Overhead- 0$0.00
Sub-Contractor's Profit- 0$0.00
FL State Sales Tax- 0$0.00
TOTAL- 0$0.00

&"Verdana,Bold"Construction Cost Estimate

Div2

CONSTRUCTION COST ESTIMATEDATE
December 31, 1899
PROJECTBASIS FOR ESTIMATE
Juniper Springs Boardwalk ReplacementCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
Juniper Springs Recreational Area Silver Springs, FloridaCODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
USDA Forest Service - National Forests of FloridaXXXXXXXXX
DRAWING NO.ESTIMATORCHECKED BY
0
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
DIVISION 2 - EXISTING CONDITIONS
02 41 00 DEMOLITION$0.00$0.00$0.00
02 41 13 SELECTIVE SITE DEMOLITION$0.00$0.00$0.00
$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
02 41 19 SELECTIVE DEMOLITION, DISPOSAL$0.00$0.00$0.00
$0.00$0.00
$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
TOTAL LABOR/MATERIALS$0.00$0.00$0.00
SUBTOTAL$0.00
Sub-Contractor's Overhead$0.00
Sub-Contractor's Profit$0.00
FL State Sales Tax$0.00
TOTAL$0.00

&"Verdana,Bold"Construction Cost Estimate

Div3

CONSTRUCTION COST ESTIMATEDATE
December 31, 1899
PROJECTBASIS FOR ESTIMATE
Juniper Springs Boardwalk ReplacementCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
Juniper Springs Recreational Area Silver Springs, FloridaCODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
USDA Forest Service - National Forests of FloridaXXXXXXXXX
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
DIVISION 3 - CONCRETE
CONCRETE WORK
03 11 13 STRUCTURAL CAST-IN-PLACE CONCRETE - AUGURED PILES
$0.00
03 30 00 CAST-IN-PLACE CONCRETE
$0.00
TOTAL LABOR/MATERIALS
SUBTOTAL
Sub-Contractor's Overhead
Sub-Contractor's Profit
FL State Sales Tax
TOTAL

&"Verdana,Bold"Construction Cost Estimate

Div4

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
MASONRY
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL$ - 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div5

CONSTRUCTION COST ESTIMATEDATE
12/31/99
PROJECTBASIS FOR ESTIMATE
Juniper Springs Boardwalk ReplacementCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
Juniper Springs Recreational Area Silver Springs, FloridaCODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
USDA Forest Service - National Forests of FloridaXXXXXXXXX
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTAL**PER UNITTOTALTOTAL COST
DIVISION 5 - METALS
METALS - Weathering Steel, General: ASTM A588
05 12 00 STRUCTURAL STEEL FRAMING
05 12 23.17 COLUMNS, STRUCTURAL
05 12 23.20 CURB EDGING
05 12 23.40 LIGHTWEIGHT FRAMING & INSTALL
05 50 00 STEEL FABRICATION
05 73 23 RAILINGS - ARCHITECTURAL
- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL$0.00$0.00
Sub-Contractor's Overhead$0.00
Sub-Contractor's Profit$0.00
FL State Sales Tax$0.00
TOTAL- 0

&"Verdana,Bold"Construction Cost Estimate

Div6

CONSTRUCTION COST ESTIMATEDATE
December 31, 1899
PROJECTBASIS FOR ESTIMATE
Juniper Springs Boardwalk ReplacementCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
Juniper Springs Recreational Area Silver Springs, FloridaCODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
USDA Forest Service - National Forests of FloridaXXXXXXXXX
DRAWING NO.ESTIMATORCHECKED BY
0
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
DIVISION 6 - WOOD, PLASTICS AND COMPOSITES
06 15 00 WOOD DECKING
06 20 00 FINISH CARPENTRY
TOTAL LABOR/MATERIALS
SUBTOTAL
Sub-Contractor's Overhead
Sub-Contractor's Profit
FL State Sales Tax
TOTAL

&"Verdana,Bold"Construction Cost Estimate

Div7

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
THERMAL AND MOISTURE PROTECTION
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL- 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div8

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
OPENINGS
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL- 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div9

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
FINISHES
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL$ - 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div10

CONSTRUCTION COST ESTIMATEDATE
December 31, 1899
PROJECTBASIS FOR ESTIMATE
Juniper Springs Boardwalk ReplacementCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
Juniper Springs Recreational Area Silver Springs, FloridaCODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
USDA Forest Service - National Forests of FloridaXXXXXXXXX
DRAWING NO.ESTIMATORCHECKED BY
0
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
DIVISION 10 - SPECIALTIES
10 70 00 EXTERIOR SPECIALTIES
TOTAL LABOR/MATERIALS
SUBTOTAL
Sub-Contractor's Overhead
Sub-Contractor's Profit
FL State Sales Tax
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div11

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
EQUIPMENT
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL- 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div12

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
FURNISHINGS
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL- 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div13

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
SPECIAL CONSTRUCTION
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL- 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div14

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
CONVEYING EQUIPMENT
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL$ - 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div15

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
RESERVED
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL$ - 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div16

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
RESERVED
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL- 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div20

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
RESERVED
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL- 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div21

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
FIRE SUPRESSION
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL- 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div22

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
PLUMBING
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL$ - 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div23

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
HEATING, VENTILATING AND A/C
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL$ - 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div24

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
RESERVED
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL$ - 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div25

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
INTEGRATED AUTOMATION
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL$ - 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div26

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
ELECTRICAL
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL- 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div27

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
COMMUNICATIONS
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL- 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div28

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
ELECTRONIC SAFETY AND SECURITY
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL- 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div29

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
RESERVED
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL$ - 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div30

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
RESERVED
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL$ - 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div31

CONSTRUCTION COST ESTIMATEDATE
December 31, 1899
PROJECTBASIS FOR ESTIMATE
Juniper Springs Boardwalk ReplacementCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
Juniper Springs Recreational Area Silver Springs, FloridaCODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
USDA Forest Service - National Forests of FloridaXXXXXXXXX
DRAWING NO.ESTIMATORCHECKED BY
0
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
DIVISION 31 - EARTHWORK
31 23 00 EXCAVATION & FILL
TOTAL LABOR/MATERIALS
SUBTOTAL
Sub-Contractor's Overhead
Sub-Contractor's Profit
FL State Sales Tax
TOTAL

&"Verdana,Bold"Construction Cost Estimate

Div32

CONSTRUCTION COST ESTIMATEDATE
December 31, 1899
PROJECTBASIS FOR ESTIMATE
Juniper Springs Boardwalk ReplacementCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
Juniper Springs Recreational Area Silver Springs, FloridaCODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
USDA Forest Service - National Forests of FloridaXXXXXXXXX
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 93 00 PLANTS
TOTAL LABOR/MATERIALS
SUBTOTAL
Sub-Contractor's Overhead
Sub-Contractor's Profit
FL State Sales Tax
TOTAL

&"Verdana,Bold"Construction Cost Estimate

Div33

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
UTILITIES
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL- 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div34

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
TRANSPORTATION
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL$ - 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div35

CONSTRUCTION COST ESTIMATEDATE
December 31, 1899
PROJECTBASIS FOR ESTIMATE
Juniper Springs Boardwalk ReplacementCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
Juniper Springs Recreational Area Silver Springs, FloridaCODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
USDA Forest Service - National Forests of FloridaXXXXXXXXX
DRAWING NO.ESTIMATORCHECKED BY
0
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
DIVISION 35 - WATERWAYS AND MARINE CONSTRUCTION
Fern Hammock Pedestrian Bridge - Existing Wood Bridge
Equipment Operator (Crane)
Crane
Fern Hammock Pedestrian Bridge - Weathering Steel
Pedestrian Truss Bridge Erection - Allowance
Juniper Creek Kayak Launch - Allowance
Juniper Creek Kayak Launch - Erection Allowance
INSTALLATION
Equipment Operator (Crane)
Crane
TOTAL LABOR/MATERIALS
SUBTOTAL
Sub-Contractor's Overhead
Sub-Contractor's Profit
FL State Sales Tax
RESERVED$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div36

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
RESERVED
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL$ - 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div37

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
RESERVED
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL$ - 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div38

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
RESERVED
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL$ - 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div39

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
RESERVED
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL- 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div40

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
PROCESS INTEGRATION
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL- 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div41

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
MATERIAL PROCESING AND HANDLING EQUIPMENT
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL- 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div42

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
PROCESS HEATING, COOLING AND DRYING EQUIPMENT
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL$ - 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div43

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
PROCESS GAS & LIQUID HANDLING, PURIFICATION AND STORAGE EQUIPMENT
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL$ - 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div44

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)
EGLIN AIR FORCE BASE, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
Fill HereFill Here
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
POLLUTION CONTROL EQUIPMENT
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL- 0
Sub-Contractor's Overhead5.00%- 0
Sub-Contractor's Profit11.00%- 0
FL State Sales Tax6.00%- 0
TOTAL$ - 0

&"Verdana,Bold"Construction Cost Estimate

Div45

CONSTRUCTION COST ESTIMATEDATE
Fill Here
PROJECTBASIS FOR ESTIMATE
Fill HereCODE A (No design completed)
LOCATIONCODE B (Preliminary design)

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .