Summary: Schedule of Items for Durkee and Town Gulch Fence Repair/Construction

This document is a Schedule of Items for solicitation 1240BH26Q0024, issued by the Wallowa Whitman National Forest (Whitman Ranger District, Baker County, Oregon). The contract requires fence repair and construction services across two project areas: Town Gulch and Durkee. The work encompasses post-fire material cleanup, right-of-way preparation and clearing, and construction of range fences and aspen enclosures. Specific deliverables include 3-strand and 4-strand range fence construction measured in miles, and buck-and-pole fence construction for aspen enclosures measured in linear feet. The base contract (Contract Line Item 0001) includes 11 prioritized work items totaling approximately 28.68 miles of range fence and 4,228 linear feet of enclosure fencing. Optional items (Contract Line Item 1001) involve installation of reflective fence markers on 9.9 miles of Durkee range fences, with two alternatives offered (with or without reflective tape).

Contractors must provide unit pricing for each line item, with payment based on actual work performed as verified through on-the-ground GPS measurement rather than estimated distances. A Bid Bond of 20 percent is required if the total offer exceeds $150,000, and Performance and Payment Bonds of 100 percent each are required for individual awards exceeding $150,000. All construction materials consisting wholly or predominantly of iron or steel must contain less than five percent foreign content by cost, supported by manufacturer certifications. Prospective awardees must be registered and active in the System for Award Management (SAM) database at the time of offer submission, award, and through final payment. Additionally, contractors must provide their UEI Number and email address with their proposals.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Durkee and Town Gulch Fence Repair/Construction

1240BH26Q0024

SCHEDULE OF ITEMS

Wallowa Whitman National Forest

Whitman Ranger District (Baker County, Oregon)

Contract Line Item 0001 (Base)

Item Number Description Pay

Unit Est

Qty‡ Unit Price Total Price

Town Gulch - Priority 1 - Cow/Bear Bernard Interior Fence -3 strand

1.1 Post-fire material cleanup, removal and ROW

preparation and clearing Miles 3.5 $ $

1.2 3-Strand Range Fence Construction Miles 3.5 $ $ Town Gulch - Priority 1 - South Boundary Exterior Fence - 4 strand

2.1 Post-fire material cleanup, removal and ROW

preparation and clearing Miles 0.72 $ $

2.2 4-Strand Range Fence Construction Miles 0.72 $ $ Town Gulch - Priority 2 - Cow/Bear Bernard Interior - 3 strand

3.1 Post-fire material cleanup, removal and ROW

preparation and clearing Miles 1.48 $ $

3.2 3-Strand Range Fence Construction Miles 1.48 $ $ Town Gulch- Priority 2 - South Boundary Exterior Fence - 4 strand

4.1 Post-fire material cleanup, removal and ROW

preparation and clearing Miles 2.04 $ $

4.2 4-Strand Range Fence Construction Miles 2.04 $ $ Town Gulch- Priority 3 - East Boundary Exterior Fence - 4 strand

5.1 Post-fire material cleanup, removal and ROW

preparation and clearing Miles 2.3 $ $

5.2 4-Strand Range Fence Construction Miles 2.3 $ $ Durkee - Priority 1 - SE Boundary/N Boundary Exterior Fence- 4 strand

6.1 Post-fire material cleanup, removal and ROW

preparation and clearing Miles 4.3 $ $

6.2 4-Strand Range Fence Construction Miles 4.3 $ $ Durkee - Priority 2 - Dark Canyon/French Interior Fence - 3 strand

7.1 Post-fire material cleanup, removal and ROW

preparation and clearing Miles 5.6 $ $

7.2 3-Strand Range Fence Construction Miles 5.6 $ $ Town Gulch Aspen Enclosures - Priority 1 - Skull Creek

8.1 Post-fire material cleanup, removal and ROW

preparation and clearing

Feet 1,055 $ $

8.2 Buck and Pole Construction Feet 1,055 $ $

Town Gulch Aspen Enclosures - Priority 2 -Aspen Rd 77111

9.1 Post-fire material cleanup, removal and ROW preparation and clearing

Feet 1,068 $ $

9.2 Buck and Pole Construction Feet 1,068 $ $

Durkee and Town Gulch Fence Repair/Construction

1240BH26Q0024

Town Gulch Aspen Enclosures - Priority 3 - Aspen Summit Creek Road

10.1 Post-fire material cleanup, removal and ROW preparation and clearing

Feet 565 $ $

10.2 Buck and Pole Construction Feet 565 $ $

Town Gulch Aspen Enclosures - Priority 3 - Aspen Rd 7741

11.1 Post-fire material cleanup, removal and ROW preparation and clearing

Feet 1,072 $ $

11.2 Buck and Pole Construction Feet 1,072 $ $

Contract Line Item 1001 (Options) (Applies only to Durkee range fences)

12.1* Reflective fence markers "Vinyl Undersill Trim" with reflective tape Mile 9.9* $ $

13.1* Reflective fence markers "Vinyl Undersill Trim" without reflective tape Mile 9.9* $ $

* Vinyl undersill trim may be substituted with alternative material upon approval by the Contracting Officer. The sole distinction between Items 12.1 and 13.1 is the additional cost associated with the application or installation of the reflective tape. Only one of the optional items will be selected for award.

‡ Units of measure (miles and feet) are reported as estimated by GIS database information. Actual payment of distances will be based on actual distance installed through on-the-ground GPS verification.

SCHEDULE NOTES

1. Payment will be made on actual work performed as described in the Schedule of Items. Contractors should include all labor, materials, and supplies needed to perform the work described under its corresponding unit price.

2. Payment for bond premiums in accordance with AGAR 452.232-71, Progress Payments for Commercial Construction Contracts, shall not be in addition to the contract price.

3. A Bid Bond of (20%) will be required of offer whose total price exceeds $150,000. Performance and Payment Bonds (100% each) will be required for all individual awards that exceed $150,000.

4. The Contractor shall ensure that any construction material consisting wholly or predominantly of iron or steel, or a combination of both, contains less than five (5) percent foreign iron and steel by cost, based on the total cost of all components used (see the definition of ‘foreign iron and steel’ at FAR 25.003). The awardee shall furnish manufacturers’ certifications verifying the origin of the domestic materials to the Contracting Officer and the Contracting Officer’s Representative. Attachment 15 may be used at the awardee’s discretion; however, submission of the certification of material origin remains mandatory.

Please provide the following information:

Vendor UEI Number: __________________

Vendor Email: _________________________

NOTE: Prospective awardee shall be registered and active in the System for Award Management (SAM) database when submitting an offer, and shall be registered at time of award, during performance, and through final payment of a contract resulting from this solicitation. Information on registration may be obtained via the internet at: http://www.sam.gov. All contractors and vendors must complete the electronic version of the Representations and Certifications in the SAM system. If at the time of receipt of offers, an Offeror is not actively and successfully registered in the SAM database, the Offeror will not be considered for award.