C007124 - Division 1 - Project Specifications r1.docx

DOCX document 639 KB Posted

Attached to
Traffic Signals Replacement
Solicitation number
147530
Issued by
Polk County, Florida

About this file

This is a Project Specifications document for the 2027 Traffic Signals Replacement project issued by the Central Florida Tourism Oversight District (CFTOD) under Contract C007124, dated October 14, 2026. The project involves comprehensive traffic signal improvements including maintenance of traffic/lane closures, erosion and sedimentation control, traffic signal removal and replacement, drilled shafts, traffic control cabinet removal and replacement, video detection system installation, and tree removal. The work encompasses protective coatings for carbon steel light poles and mast arms, directional boring/jack and bore operations, landscape work including sod and irrigation systems, and associated site preparation and restoration. The contractor must provide dedicated staffing including a part-time project manager, full-time superintendent, and foreman for maintenance of traffic and stormwater pollution prevention. Key requirements include obtaining permits, submitting a Project Specific Safety Plan prior to commencement, completing survey verification within fourteen days of receiving a Limited Notice to Proceed, and maintaining daily erosion control inspections. The contract requires adherence to Florida Department of Transportation standards, compliance with the 2024 EPCOT Building Code, and coordination with multiple utility owners including Reedy Creek Energy Services, Smart City Telecom, and others.

The contract is awarded to the lowest responsive and responsible bidder as determined by CFTOD, with the District reserving the right to reject any or all bids or award to the next lowest bidder if the selected bidder cannot successfully execute. The contractor assumes full responsibility for all owner-furnished products from the point of origin through final completion and must secure all required permits at its own expense, including SWPPP permits, CFTOD building permits, haul permits, and RCES dig permits. The contractor is responsible for costs associated with implementation of the Severe Weather Preparedness Plan and all premium costs for work performed outside normal hours (7:00 AM to 4:00 PM Monday through Friday) or on weekends and holidays, which require approval at least seventy-two hours in advance. The Owner retains the right to make direct purchases of materials valued at $25,000 or more, with the contractor responsible for coordinating delivery and validating receipt of such owner-purchased products. No sales tax applies to owner direct purchases due to CFTOD's exemption as a public entity. The document does not identify a specific contract award date, contract term, or pricing information in the specifications provided.

View the file

Other files

File Type Posted
SA-06 - Traffic Signal Improvements Design FY26_GeotechReport.pdf PDF
Compliance with FL Statutes Affidavit (1).pdf PDF
EXHIBIT B- Schedule of Unit Rates.pdf PDF
SA-07 - Traffic Signal Improvements Design FY26_MastArmCalcs.pdf PDF
Div 2 and 3 CFTOD Specifications - Signal Design. r1.pdf PDF
SA-01 - RCES Underground Construction Rules (REV 7).pdf PDF
Exhibit C - Project - Client Reference Form v.12.25 (1).pdf PDF
SA-03 - District Traffic Equipment Standards - 11-12-2025.pdf PDF
EXHIBIT F-Warranty Offered Form (1).pdf PDF
Affidavit of Eligibility Form - Opportunity Zone Program v.12.25.pdf PDF
CFTOD Erosion Control Notes.pdf PDF
Affidavit of Eligibility Form - Buy Local or Veteran Small Business Program 12.25.pdf PDF
SA-04 - 2026 CFTOD Storm Preparation Procedures for Contractors Revised 2026.04 (1).rtf RTF text file
EXHIBIT A- Scope of Services.pdf PDF
IFB_Traffic Signal Improvements Design FY26 Victory Way Buena Vista Drive.pdf PDF
RCES Lock Out Tag Out.pdf PDF
EXHIBIT E-Emergency Response Form (1).pdf PDF
EXHIBIT D-Subcontractor List v.12.25 (3).pdf PDF
SA-05 - MA 1-6 Utility Locates - For Reference Only.pdf PDF
ATTACHMENTS 1-6.pdf PDF
Bidder Requirements Checklist v.4SM.pdf PDF
RCES Confined Space.pdf PDF
SA-02 - CFTOD Insurance Requirements REV 02.27.25.pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CENTRAL FLORIDA TOURISM OVERSIGHT DISTRICTSection 09870
2027 Traffic Signals ReplacementProtective Coatings for Carbon Steel Light Poles and Mast Arms
Contract: C007124October 14, 2026

SECTION 00850

LIST OF DRAWINGS AND SPECIFICATIONS

The following list of drawings and specifications, all prepared as noted, shall form a part of the Project Manual:

Project Manual

Entitled: 2027 Traffic Signals Replacement

Dated: October 14, 2026

DRAWINGS:

The following list of drawings/materials is applicable to the foregoing.

LIST OF DRAWINGS / MATERIALS:

DRAWING NO.
DRAWING TITLE
ISSUE DATE
EOR

Traffif Signal Improvements Design FY26

T-1
Title and Index of Drawings
8/21/2026
HNTB Corporation
T-2
Signature Sheet
8/21/2026
HNTB Corporation
T-3
General Notes & Summary of Pay Items
8/21/2026
HNTB Corporation
T-4
General Notes & Summary of Pay Items
8/21/2026
HNTB Corporation
T-5
General Notes & Summary of Pay Items
8/21/2026
HNTB Corporation
T-6
Project Layout
8/21/2026
HNTB Corporation
T-7
Signal Plan Sheet
8/21/2026
HNTB Corporation
T-8
Signal Plan Sheet
8/21/2026
HNTB Corporation
T-9
Directional Bore Details (1)
8/21/2026
HNTB Corporation
T-10
Directional Bore Details (2)
8/21/2026
HNTB Corporation
T-11
Directional Bore Details (3)
8/21/2026
HNTB Corporation
T-12
Directional Bore Details (4)
8/21/2026
HNTB Corporation
T-13
Mast Arm Tabulation Sheet
8/21/2026
HNTB Corporation
T-14
Standard Mast Arm Assemblies Data Table
8/21/2026
HNTB Corporation
T-15
Report of Core Borings
8/21/2026
Intertek PSI, Inc.
T-16
Report of Core Borings
8/21/2026
Intertek PSI, Inc.
T-17
Detour Plan (1)
8/21/2026
HNTB Corporation
T-18
Detour Plan (2)
8/21/2026
HNTB Corporation
T-19
Detour Plan (3)
8/21/2026
HNTB Corporation
T-20
Detour Plan (4)
8/21/2026
HNTB Corporation

SUPPLEMENTAL ATTACHMENTS:

The following list of supplemental attachments is applicable to the foregoing.

ATTACHMENT NO.
SUPPLEMENTAL ATTACHMENT
ISSUE DATE
ISSUER
SA-01
RCES Underground Construction Rules in the Vicinity of CFTOD Electrical Utilities (REV 7)
2/04/2025
RCES
SA-02
2025 CFTOD Insurance Requirements
2/27/2025
CFTOD
SA-03
District Traffic Signal Equipment Standards
11/12/2025
CFTOD
SA-04
CFTOD Storm Preparation Procedures (Rev 04.26)
4/27/2026
CFTOD
SA-05
MA 1-6 Utility Locates - For Reference Only
5/19/2026
SSMC
SA-06
Traffic Signal Improvements Design FY26_GeotechReport
8/20/2026
Professional Service Industries, Inc.
SA-07
Traffic Signal Improvements Design FY26_MastArmCalcs
8/2026
HNTB

SPECIFICATIONS:

The following list of specifications is applicable to the foregoing.

SECTION NO.
SECTION TITLE
ISSUE DATE
STATUS

DIVISION 00 – CONTRACT & BIDDING DOCUMENTS

00850
List of Drawings and Specifications
10/14/2026

DIVISION 01 – GENERAL REQUIREMENTS

01009
Project Specific Safety Plan Requirements
10/14/2026
01010
Summary of Work
10/14/2026
01018
Owner Furnished Products
10/14/2026
01019
Owner Purchased Products
10/14/2026
01019A
Owner Direct Purchase Routing Procedures
10/14/2026
01019B
Contractor’s Vendor Invoice Affirmation Letter
10/14/2026
01019C
Owner’s Vendor Invoice Affirmation Letter
10/14/2026
01020
Electronic Document Processing Service
10/14/2026
01021
Allowances
10/14/2026
01041
Project Coordination
10/14/2026
01045
Cutting and Patching
10/14/2026
01050
Field Engineering
10/14/2026
01100
Alternates
10/14/2026
AS NEEDED
01202
Progress Meetings
10/14/2026
01310
Construction Schedule
10/14/2026
01315
Contract Time, Sequencing and Timing of Work
10/14/2026
01325
Scheduling of Work
10/14/2026
01330
Submittal Procedures
10/14/2026
01340
Shop Drawings, Product Data and Samples
10/14/2026
01370
Schedule of Values
10/14/2026
01410
Regulatory Requirements
10/14/2026
01420
References
10/14/2026
01430
Soils Investigation
10/14/2026
01440
Quality Assurance and Quality Control
10/14/2026
01455
Testing and Inspection Services
10/14/2026
01500
Temporary Construction Facilities
10/14/2026
01560
Erosion Control and Dewatering
10/14/2026
01560A
SFWMD Dewatering Permit Notification
10/14/2026
AS NEEDED
01560B
Turbidity Monitoring Plan Requirements
10/14/2026
AS NEEDED
01630
Substitutions and Product Options
10/14/2026
01640
Product Handling and Protection
10/14/2026
01700
Project Closeout
10/14/2026
01710
Cleaning
10/14/2026
01720
Project Record Documents
10/14/2026
01730
Execution
10/14/2026
09870
Protective Coatings for Carbon Steel Light Poles and Mast Arms
10/14/2026

DIVISION 02 & 03 – ROADWAY SPECIFICATIONS

FDOT Specifications Reference and Modifications
10/20/2026
CFTOD 334
Specification for Asphalt Pavement
10/20/2026
CFTOD 528
Specification for Portland Cement Concrete Sidewalk
10/20/2026
Section 02240
Supplemental Specifications - Dewatering
10/20/2026
Dust Control
10/20/2026

END OF SECTION 00850

CENTRAL FLORIDA TOURISM OVERSIGHT DISTRICTSection 00850
2027 Traffic Signals ReplacementList of Drawings and Specifications
Contract: C007124October 14, 2026

00850-1

SECTION 01009

PROJECT SPECIFIC SAFETY PLAN REQUIREMENTS

PART 1 – GENERAL

1.01 INTRODUCTION

A Project Specific Safety Plan (PSSP) is a communication tool between contractors and the Owner. Used correctly, the PSSP ensures that relevant project/site-specific safety information is identified, monitored and communicated to all involved with the project.

1.02 PURPOSE

The PSSP will allow all those involved with the project to easily identify the existing and potential hazards associated with the scope of work and what methods the contractor shall utilize to mitigate the hazards to an acceptable level.

This should not be an overly complex document. It should be easily referenced by all those working on the project. The document should be able to be used as part of the daily pre task planning and for onsite safety meetings (toolbox talks).

The PSSP should not be a version of the company safety plan. It is Project / Site / Task specific. The PSSP shall include the applicable information commensurate with the size, complexity and risk level of the project.

The PSSP shall make it clear that everyone on the project has the right to report hazards and unsafe practices without fear of reprisal.

Contractor shall submit a PSSP to the Owner for review prior to project commencement with appropriate time for review. The Owner reserves the right to ask the Contractor to resubmit the PSSP if safety critical items related to the project are missing or incomplete.

The submittal of the PSSP does not relieve the Contractor from any other submittals required by the Contract Documents, including but not limited to:

· Construction & Demolition Safety Plan

· Crane Critical Lift Plan

· Hazardous Materials Disposal Plan

· Maintenance of Traffic (MOT) Plan / Temporary Traffic Control (TTC) Plan

· Hurricane / Weather Contingency Plan

1.03 FORMAT

The Owner will not dictate the exact format of the PSSP. However, there are four critical components of the PSSP:

· Responsibilities / Contacts

· Scope of work

· Job Safety Analysis (JSA)

· Pre-Task / Daily Safety Planning

A. RESPONSIBILITIES / CONTACTS

This section shall simply and clearly define the duties and responsibilities of the Contractor’s personnel regarding the work to be completed and safety and health program implementation. It should also include means to contact those listed (i.e. phone, email, etc.)

· Contractor’s President/Owner (of company)

· Contractor’s Project Manager

· Contractor’s Safety Manager (if applicable)

· Contractor’s Field Supervision/ Superintendent

· All of Contractor’s Subcontractors and Sub-Subcontractors (if any)

B. SCOPE OF WORK

The Scope of Work shall include translating the contract scope of work into a specific detailed work plan. It shall identify location(s), means and methods of accomplishing the plan, anticipated sequence of events, equipment to be used, etc. Please note that this includes all work to be performed by the Contractor and Subcontractors of every tier.

The scope shall also identify the following:

· Maximum height and depth of work activities

· Industrial hygiene issues

· Exposure to high hazard areas including but not limited to:

· Water Ways

· Diving

· Crane Lifts

· Energized Electrical Systems

· Confined Spaces

· Maintenance Of Traffic (“MOT”) / Temporary Traffic Control (“TTC”)

· Guest Areas

C. JOB SAFETY ANALYSIS (JSA)

The JSA is a task/operation-driven document to ensure that the job task or operation receives proper safety planning prior to beginning work. In actuality, the JSA is a written work plan that incorporates safety procedures into the work practices The JSA should be prepared far enough in advance of the task or activity to ensure that changes or revisions will not affect the scheduled execution of the task or activity. A JSA is to be developed by the Contractor or Subcontractors for any high-hazard or high-risk activity as identified by the Owner in its sole and absolute discretion, the Contractor or all Subcontractors of every tier.

The specific format of the JSA is to be determined by the Contractor, however, it must include the following information:

· A breakdown of the job into successive steps involved with the work activity.

· Identification of the hazards and the potential incidents associated with each work activity.

· Identification of methods to reduce or eliminate the hazards and potential incidents.

D. PRE-TASK PLANNING

Pre-task Planning is an activity that occurs at the start of each day, prior to beginning any work shift during which work is to be performed by the Contractor or any Sub-contractor of any tier, as well as any time the daily cope of the work changes. It helps everyone involved in performing, supervising and overseeing the work to align the objectives to be accomplished before the day of work begins. A Pre-task Planning form is required to be completed and a meeting is required to be held with the crew by the supervisor prior to the start of each work shift. At a minimum, the supervisor will include the following in the Pre-task Planning:

· Identify the specific actions and work methods required to perform the work.

· Identify the specific hazards associated with the performance of the work and the measures necessary to eliminate or minimize the workers’ exposure to the hazard.

· Provide the necessary training needed to safely perform the work.

· Identify and provide the necessary tools, equipment, and PPE required to protect the workers from the hazards.

· Review any items that may be applicable to their work activity previously identified on the JSA.

The Pre-Task Plan will be documented and kept in the work location for the duration of the shift or activity. As acknowledgment of its contents, the Pre-Task Plan must be signed by all members of the work crew and its supervisor, and others identified by, and in the sole and absolute discretion of, the Owner.

Pre-Task Planning is not something that is to be submitted with the PSSP however it must be maintained on the jobsite throughout the project duration for review by the Owner and, at the request of the Owner, must be provided to the Owner as part of the Contract Close- out documentation.

END OF SECTION 01009

CENTRAL FLORIDA TOURISM OVERSIGHT DISTRICTSection 01009
2027 Traffic Signals ReplacementProject Specific Safety Plan Requirements
Contract: C007124October 14, 2026

01009-3

SECTION 01010

SUMMARY OF WORK

PART 1 – WORK COVERED BY CONTRACT DOCUMENTS

1.01 General

A. The Scope of Work for the 2027 Traffic Signals Replacement project is described by the Project Manual entitled 2027 Traffic Signal Replacements. Specific elements of the Scope of Work are generally summarized below but this Summary of the Work is not intended to be complete descriptions of the Work. Any quantities or measurements, if included in the summaries, are approximate and are not to be used in estimating the Work.

B. It is the intent of the Owner that the Contractor will perform all of the Work of any kind and nature shown on the drawings and/or described in the specifications, which is within the Contractor's Scope of Work unless specifically excluded or indicated as Owner-furnished and/or installed. Any Work not specifically indicated on the drawings and/or described in the specifications but required to fulfill the intent of a "complete job" for the Contractor's Scope of Work will be considered to be included in the Contract.

1.02 General Summary

The scope of work for the 2027 Traffic Signals Replacement project includes, but is not limited to; Maintenance of Traffic/ Lane Closures, Erosion and Sedimentation Control, Traffic Signal Removal and Replacement, Drilled Shafts, Traffic Control Cabinet Removal/Replacement and Activation, Video Detection System Installation and Tree Removal.

1.03 Detailed Scope of Work

A. Mobilization and General Conditions:

1. The Contractor shall provide a minimum dedicated full-time staff for the duration of the Contract Time including but not limited to the following staff positions:

a. Part time dedicated project manager.

b. Full time dedicated general superintendent.

c. Foreman and crew dedicated to Maintenance of Traffic (MOT)/Temporary Traffic Control (TTC) and SWPPP only.

B. Permitting:

1. The Contractor shall apply for a SWPPP permit during the pre-construction phase. The Contractor shall prepare and submit the NOI to the Central Florida Tourism Oversight District prior to submitting to the FDEP during the pre-construction phase. In addition, the Contractor shall apply for any and all permits that are required by CFTOD Building and Safety during the pre-construction period.

2. Work must meet all requirements of the 2024 EPCOT Building Code or other most current supplement thereof in effect at the time of the effective Contract date.

3. Work must meet all requirements of the Land Development Regulations in effect at the time of the effective Contract date.

4. The Contractor shall provide all building permits. Because the project is owned by the same entity as that which will issue the building permits, the permitting fees normally applicable are waived. It is necessary, however, for any contractor applying for building permits through CFTOD to request exemption from payment of the permitting fees for the reason stipulated herein.

C. Maintenance of Traffic (MOT) / Temporary Traffic Control (TTC):

1. The Contractor shall follow the Traffic Control Plans (TCPs) provided for the Project. Contractor is required to adhere to FDOT Standard Plans (Standard Design Index) 102-600 series and associated indexes for items not detailed in the TCPs. Contractor is required to submit for approval proposed MOT/TTC details when certain activities (i.e., structure component deliveries, excavations adjacent to traffic, overhead installations, etc.) require detailed operations to control traffic flow. Contractor shall include all such activities within their bid and expect to attend regular MOT/TTC Coordination meetings to discuss proposed operations. Should the Contractor request to deviate from the TCPs or request an alternate/additional detour or subphase, the Contractor shall hire a professional engineer licensed to do business in the State of Florida to provide a certified Maintenance of Traffic (MOT) / Temporary Traffic Control (TTC) individual plan prior to applying for the required permits from CFTOD Planning & Engineering. The MOT/TTC plans shall be in compliance with the Manual for Uniform Traffic Control Devices and applicable FDOT Standards. The Contractor shall maintain his traffic control devices for the entire duration of the project until the Owner certifies that the Punch List is complete.

2. The Contractor shall provide a qualified traffic control crew to provide continuous maintenance of all traffic control systems at its expense, whenever traffic conditions warrant such control and whenever directed to provide such maintenance or adjustments by the CFTOD Construction Project Manager. This requirement shall also apply to all events requiring a vehicle to back up on a lane maintained for traffic or any other situation considered by the CFTOD Construction Project Manager to be dangerous.

3. The Contractor shall provide a qualified traffic control crew at its expense to inspect all traffic control systems in the presence of the Owner at the beginning and end of each work shift for a minimum of one hour after the start of the shift and a minimum of one hour before the end of the shift. The Contractor’s crew shall make immediate corrections or adjustments to the MOT/TTC systems as required to conform them to the approved MOT/TTC plans or as directed by the CFTOD Construction Project Manager.

4. All MOT/TTC devices shall be like new. They shall be freshly painted and free of scratches, dents, dirt, and debris, and stains. The Contractor shall replace any MOT/TTC device that becomes damaged with a new device.

D. Lay Down Yard/Employee Parking Construction:

1. The designated lay down yard and employee parking area is anticipated to be in the vicinity of the Project Site. The Contractor shall contain all trade parking, inclusive of the Contractor itself, to designated contractor parking areas. Staging and construction laydown is very limited within project limits. The Contractor shall contain all trade parking, inclusive of the Contractor itself, to designated contractor parking areas. Contractor is responsible to maintain cleanliness of their assigned/approved area(s). No POV shall be parked within project limits.

2. Contractor Employees shall be transported from assigned parking areas to work areas by means provided by Contractor.

E. Erosion and Sedimentation Control:

1. The Contractor shall design, furnish, install and maintain, at its expense, all necessary erosion control and wetland protection systems, such as silt fences, temporary retention basins, silt screens, synthetic hay bales, floating turbidity barriers, inlet protection systems, filter fabric, sandbags, sheet piling or other approved devices per the Land Development Regulations and Owner as required to prevent erosion and to protect the storm water systems and receiving waters. The Contractor shall be responsible for repairing and/or replacing any and all damage to the erosion protection devices. The Contractor shall maintain all erosion control systems until the Owner certifies that the punch list is complete.

2. The Contractor shall prepare the Storm Water Pollution Prevention Plan utilizing the forms included in the Specification Section 01560. The Contractor shall submit a completed SWPPP to CFTOD Planning and Engineering for review and the Contractor shall make all modifications and refinements to the plan requested by CFTOD Planning and Engineering. Contractor shall be advised CFTOD Planning and Engineering has 30 days to review SWPPP submittals, including both initial submittal and any request for additional information submittal. Contractors shall plan accordingly. Once all of the modifications have been made to the satisfaction of CFTOD Planning and Engineering, then the Contractor shall sign and certify the SWPPP as the operator and implement the structural erosion control devices.

3. The Contractor shall prepare and submit the NOI (when required) to CFTOD Planning and Engineering for review. Only after CFTOD Planning and Engineering has reviewed and approved the draft NOI, shall the Contractor submit the NOI to FDEP and pay all filing fees and secure a permit authorization letter from the EPA and fully comply with all record keeping requirements.

4. The Contractor shall prepare and submit a Turbidity Control Plan if working within an active waterbody or within 15 feet of the top of slope (a.k.a the low maintenance zone) of an active waterbody (including lakes, canals, etc.). The Contractor shall be required to create a Turbidity Control Plan providing detailed information regarding means and methods and best management practices to prevent, contain and treat turbidity as may be encountered and generated during the course of work. This can also include items such as sheet pile/cofferdam information, bypass pumping, etc. that may be required to manage flow during course of work. Contractor shall be advised CFTOD Planning and Engineering has 30 days to review Turbidity Control Plan submittals, including both initial submittal and any request for additional information submittal. Contractors shall plan accordingly.

5. The Contractor shall provide a qualified and dedicated erosion and sedimentation control team to inspect and maintain the erosion control and wetland protection systems on a daily basis. The Contractor acknowledges that daily inspection and maintenance requirement is more stringent than the periodic inspections required by the FDEP. The Owner requires more stringent daily inspection and maintenance by a dedicated crew. The Contractor shall remove all erosion and sediment control systems at the conclusion of its Work when authorized to do so by the Owner and upon approval by CFTOD Planning and Engineering.

6. The Contractor will be required to maintain at all times, a clear, orderly construction site and ensure the implementation of good housekeeping practices as described in these Contract Documents within the Storm Water Pollution Prevention Plans (SWPPP).

7. The Contractor shall submit any chemical products/treatment methods for turbidity to the Owner and CFTOD Planning and Engineering for approval prior to use. Contractor shall be aware certain products may not be allowed due to risks of environmental degradation.

8. The Contractor shall maintain a power broom on site at all times throughout the Contract Time and sweep the roadways on a daily basis whenever its construction traffic cause dirt or debris to be deposited on the roads or whenever directed to sweep the roads by the Owner.

9. The Contractor shall provide and maintain a water truck at all time during the Contract Time to provide dust control when conditions warrant or as directed by the Owner.

10. The Contractor shall utilize lined trucks to haul muck or saturated soils off site.

11. The water quality within the various bodies of water located on the Owner’s property is regularly monitored and compliance with environmental standards is rigidly enforced. The Contractor is advised that should any of the Owner’s ponds, lakes or canals, (or those of adjacent landowner’s) become contaminated due to the Contractor’s actions or inaction, the cost to flocculate, or clean by any means as may be required, shall be paid for by the Contractor.

F. Survey and Lay-Out:

1. The Contractor shall perform all survey and lay out as required to complete the work within the specified tolerances.

2. After award of the contract and within fourteen (14) days of receiving a Limited Notice to Proceed, the Contractor shall complete all survey work required to verify and accept the accuracy of the grades noted as existing on the bid drawings. At the end of the fourteen-day discovery period, the Contractor shall provide written acceptance of the existing grades or provide written documentation of any material deviation it has discovered between the existing conditions and the conditions noted as existing on the bid drawings. All claims shall be made in strict accord with Article 13 of the General Conditions of the Contract for Construction. Failure to give such notice or to provide substantiation thereof shall constitute a waiver of the claim and acceptance of the existing grades.

3. Refer to the Drawings for information regarding bench mark datum and coordinate system.

4. The Contractor shall preserve and protect all existing survey monuments within the limits of construction.

5. The Contractor shall provide the following specific survey tasks:

a. All surveying, engineering and layout required for the Work including but not limited to: (i) the limits of standard clearing and grubbing and (ii) drainage structure, utilities, roadway layout, etc.

b. All “rough” and “finish” grade stakes as required to perform the Work. Any re-staking required due to his or any other contractor damaging, or removing original stakes shall be performed by the Contractor and will not be the responsibility of the Owner.

c. Coordination with the Owner’s survey consultant for verification of the Contractor’s survey including, but not limited to, Contractor’s field notes and temporary horizontal and vertical control points.

6. It is the responsibility of the Contractor to generate survey control, layout, and as-built information as required in the contract documents. At no time will the project CAD design files be given to the Contractor.

G. Clearing:

1. The Contractor shall provide all clearing and grubbing as needed in performance of the work. Tree pruning, as required, is to be performed/supervised by an approved certified arborist as deemed necessary by the Owner.

2. No burning will be allowed on site. The Contractor shall remove all cleared vegetation (grasses, plants, bushes, shrubs, trees, etc) from the site and dispose of it legally off site. Existing grasses/sod removed (strippings), as required for construction, shall be disposed of off-site at the contractor’s expense and not utilized for embankment, backfill, or prepared soil layer of any kind unless approved by the Owner.

3. The Contractor shall remove all irrigation systems within the limits of the Work as required for the construction of the improvements. The Contractor will be required to retain the services of a CFTOD approved irrigation company to make any repairs and adjustments due to the Contractor’s construction activities as directed by the CFTOD Construction Project Manager.

4. The following contractors have worked within the boundaries of Central Florida Tourism Oversight District (CFTOD) property in the past. By providing this list, CFTOD does not make or imply any qualifications or statements as to the performance or standing of these firms and the bidder is at their own risk while contracting or working with them:

a. BrightView LLC

b. Commercial Landscape and Irrigation Inc.

c. Cepra Landscape LLC

d. Down To Earth Landscape and Irrigation LLC

e. Newberg Irrigation Inc.

H. Utilities:

1. The Contractor, with guidance from the Owner shall coordinate all utility construction efforts with the utility owners – Reedy Creek Energy Services (RCES) RCES requires coordination for inspections of their new and existing utilities. RCES will also require 72-hour notice and planning when working around their existing utilities. Other utility owners may include, but are not limited to, Smart City Telecom (data and communications fiber optic and wire), CFTOD (traffic fiber optic), and WDW Telecom (Disney fiber optic), Spectrum, Duke, Summit Broadband, TECO, & AT&T.

2. The Contractor shall identify and protect all existing utilities within the limits of the work.

3. Except as otherwise explicitly indicated on Drawings or called for in the Specifications, do not cut, alter, remove or otherwise disturb any existing improvement or construction or disturb any existing utilities without the approval of the CFTOD Construction Project Manager.

4. The Contractor shall immediately restore to service and repair any damage caused by it to any existing utilities which are not scheduled for removal, discontinuance or abandonment, or which have not been released by the Owner and jurisdictional agencies for removal, discontinuance or abandonment, even if so scheduled.

5. Temporary Supports for existing Utilities: The Contractor shall provide all necessary temporary supports required to protect any and all existing utilities prior to commencing Work. Any damage to existing in-service utilities during construction will be repaired at the Contractor’s expense. Temporary supports shall be reviewed by representatives of RCES or appropriate utility company prior to installation by the Contractor.

6. The Contractor shall strictly adhere to utility notice and excavation permit provisions specified in Section 2.13 of Section 01010 of the project manual. The RCES Utility Locate Office will locate primary utility services. It will not locate secondary services. Secondary services include roadway lighting systems, irrigation systems, and electrical power systems for the existing lift station. All such services shall be maintained and/or relocated without interruption to existing services. The Contractor shall hire a private utility locate service to identify and locate all secondary utilities within the limits of the Work

7. Locating services provided by the RCES Locating Services Office10T13T, Sunshine 811 and by any private secondary locating technician are confined to surface markings and flagging only. The Contractor shall hand dig and soft dig as required to determine the depths of all utilities. All such hand digging and soft digging shall be included in the Lump Sum Contract amount.

8. In the case of a conflict between the RCES specifications and the CFTOD specifications, generally the CFTOD specifications shall supersede the RCES specifications. The final determination shall be made by the CFTOD Construction Project Manager. This is not withstanding provisions contained elsewhere in the general conditions.

9. Any temporary or permanent utility (potable water, reclaimed water, sanitary water, gas, chilled water, etc.) connection to existing facilities will require advance coordination between Contractor, Owner, and RCES in all cases.

10. Contractor is strictly prohibited from adjusting, closing, or opening any mechanical valves on RCES, CFTOD or Resort utility systems. Utilization/adjustment of valves for any reason requires advance coordination between Contractor, Owner, Resort Owner, and RCES in all cases. The utility Owner(s) must be present to supervise/perform any and all valve operations.

11. Contractor should be aware that there is a 69kV power line present and strictly adhere to all safety protocols. See Supplemental Attachment SA-01.

I. Construction:

1. The Contractor shall construct all areas as shown on the drawings.

J. Directional Boring/Jack and Bore:

1. Before any Boring operation can commence, all known utilities and underground infrastructure within the proposed path must be located with positive identification.

2. A proposed bore path profile showing all identified infrastructure and their locations is to be submitted for approval prior to proceeding with installation.

K. Soil Amendment:

1. Contractor shall engage the services of a qualified agricultural soils testing laboratory to perform soil testing services of all typical areas to be planted as stated. The Contractor shall pay for all costs and fees associated with the soils testing.

2. The Contractor is responsible for all costs to amend the soil based upon the application rates.

L. Landscape Work:

1. The Contractor shall guarantee all Work for a period of one (1) year after the Owner certifies that the Punch List is complete.

2. When the Contractor has completed the Work as indicated on the drawings the Contractor shall notify the Owner and request its review. The Owner will provide art direction regarding the final adjustments of the landscaping, which may require additional plantings or relocations of plantings by the Contractor until the Owner is satisfied with the aesthetic appearance of the final landscape. The Contractor shall include reasonable equipment and man-power time to make field adjustments as specified by the Owner.

3. The Contractor shall provide all trees, palms, shrubs, ground cover and sod shown on the drawings.

4. The Contractor shall treat all of the soil with fertilizer as specified.

5. The Contractor shall remove all weeds and undesirable vegetation from the landscaping areas. The Contractor shall keep the landscaped areas weed free until the project reaches final completion.

6. The Contractor shall remove all rocks and small debris from the planter areas prior to planting landscaping.

7. The Contractor shall schedule inspections at plant nurseries with the Owner prior to delivery (if applicable). The Owner shall determine the condition of the shrubs and trees. Inferior quality or non-compliant material shall not be installed. If installed, removal of such material will be performed at the Contractor’s expense.

8. The Contractor shall field stake the location of all plant material and bed outlines prior to initiating installation for the review and approval of the Owner.

9. The Contractor shall guarantee all landscaping, including grasses, sod, trees, palms, shrubs, and aquatics, to be alive and in satisfactory growth at the end of the maintenance period.

10. The Contractor shall dig test holes in all planting beds prior to plant installation. The Contractor will verify the soil conditions and accept sole responsibility for all plant material installed.

11. The Contractor shall bear all costs of soils, testing and amendments etc. associated with the Work and included in the Specifications. Prior to commencement of the landscape planting Work the Contractor shall provide complete soil tests as required.

12. The Contractor shall field-adjust plant material as necessary to avoid damage to all existing underground utilities and/or existing above ground hardscape elements, roadway lighting, traffic signal poles and equipment, regulatory signs, and other elements of the infrastructure. All such changes required shall be completed at the Contractor’s expense and shall be coordinated with the Owner.

13. The Contractor shall promptly provide all photo documentation, certificates, samples and other submittal data required by the Contract Documents and in accordance with the Milestone Schedule. The Contractor shall schedule inspections of the nurseries with the nurseries and with the Owner. The Contractor shall accompany the Owner to each nursery to assist in tagging the trees selected to be delivered to the site. In addition, the Contractor shall provide 48 hours advance notice to the Owner of each delivery from the nurseries and afford the Owner the opportunity to inspect the trees prior to their installation. All trees shall be subject to approval by the Owner before they are planted by the Contractor.

M. Sod:

1. Contractor shall replace all sod, with like kind, if damaged by its operations.

2. Contractors shall include all sod-related costs with the site sabilization (fine grading & sodding) line item in the bid tabulation.

N. Irrigation:

1. The Contractor shall provide all irrigation systems as indicated on the Drawings.

2. The Contractor shall locate the existing main line and existing points of connection if any are existing at the beginning of its Work.

3. The Contractor shall tap into the existing irrigation main and construct the new points of connection as shown on the Drawings.

4. The Contractor shall provide electrical power and communication wire to all irrigation controllers. The Contractor shall provide the meter cans and electrical panels for all of the controllers. The Contractor shall extend all power wiring from the distribution panels to the irrigation controllers.

5. The Contractor shall install all tree irrigation as shown on the Drawings.

6. The Contractor shall install new sleeves as noted on the drawings. Where directional boring is required, the Contractor shall hire an experienced driller and licensed underground utility contractor to perform the directional bore work. The Contractor shall submit all bore logs upon completion of each bore and submit a final bore log package to go along with the as-builts at the completion of the project.

7. The Contractor shall repair and restore to new condition any and all grades, landscaping, sod, utilities, or sleeves that are damaged during the installation of the irrigation system. The Contractor shall coordinate its activities with the Separate Contractors to ensure all sleeves are installed in a timely manner consistent with the schedule provided by the Separate Contractors.

8. No landscape planting shall commence prior to the Contractor having the ability to adequately water such plantings either by hand or through the use of an irrigation system. The Contractor shall be responsible for watering all plantings if the irrigation system is not operational.

9. The Contractor shall be responsible to maintain the irrigation system in such a manner to prevent plant stress due to lack of water. Planted material that becomes stressed beyond recovery, shall be replaced by the Contractor at no additional charge. If temporary irrigation systems are required to meet the Milestone Schedule, the Contractor shall provide such temporary systems.

10. Contractor shall coordinate all planting work with irrigation work and shall be responsible for all hand watering as required to supplement irrigation watering and rainfall. The Contractor shall be responsible for supplemental hand watering in all planting areas, regardless of the status of the irrigation.

11. All irrigation pipe and control wire must be inspected by the Owner prior to backfilling on a daily basis. The irrigation mains shall be tested according to the Specifications and the Owner must witness all pressure tests.

12. Refer to Allowance No. 2 – Irrigation & Landscape (Excluding Sod), which may be utilized for the reestablishment of existing landscape areas. All use of the allowance shall be coordinated with the CFTOD Construction Project Manager prior to implementation. (See Section 01021.)

PART 2 – GENERAL INSTRUCTIONS & STANDARDS FOR THE CONSTRUCTION WORK

2.01 General Requirements

A. The Contractor shall provide all services and necessary items of expense, including but not limited to, labor, material, trucking, transportation, equipment, hoisting, scaffolding, power, supervision, appliances, layout and all other services and items of expense required for the complete performance of all Work in accordance with the Contract Documents.

B. Cost Loaded Schedule

1. The Contractor shall cost load their monthly progress CPM schedule submittals, in order to provide projected monthly cash flows to the Owner.

C. Proposed Staffing Plan

1. Contractor shall submit with its Bid Proposal a staffing plan which clearly illustrates the key elements of the organizational structure proposed to accomplish the management, field work, and administrative services required. The Contractor shall identify the key person to be placed in responsible charge of the work. The CFTOD Construction Project Manager and key personnel within each discipline shall be identified and past experience of each, as it relates to this Project, shall be discussed. Other items to be included in the discussion of the staffing plan are:

a. Work force capabilities of the firm.

b. Work force commitment for the Project.

c. Key staff resumes.

2.02 Job Site Access / Use of Job Site

A. A haul route will have to be provided by the Contractor for CFTOD Planning and Engineering review and approval. For each and every occurrence that the Contractor or its Subcontractor(s) utilize a haul route that is not prescribed by, or otherwise expressly approved by, the Owner shall deduct from the Contract Sum, the sum of $500.00 a day.

B. Vehicular traffic to the Job Site is limited to vehicles required to deliver labor and materials. On-site parking for vehicles shall be limited to those areas designated by the Owner and shall be limited to company work vehicles actively working on site. Vehicles not actively supporting Job Site operations are not permitted to remain on site. The designated lay down yard and employee parking area is anticipated to be in the vicinity of the Project Site. When it is designated, the Contractor shall create an engineered plan for review by the Owner that demonstrates how it will safely access the work zone and storage areas and how it will egress from the work zone and storage area.

C. The Contractor is responsible for the routing of all construction personnel and traffic required in the performance of the Work and shall ensure compliance with any special instructions pertaining to such routing as established by the CFTOD Construction Project Manager.

D. Lunch and break areas are confined to the immediate job site area, within the limits of construction.

E. The Contractor shall confine its use of the job site to those activities directly relating to the performance of the Work. No other use of the job site will be permitted without the express written approval of the CFTOD Construction Project Manager.

F. The Contractor shall provide all necessary flagmen, barricades, and MOT/TTC devices necessary for safe and proper traffic control. The Contractor is advised that it is responsible for all construction personnel and traffic routing logistics required in the performance of its work.

2.03 Coordination

A. The Contractor shall coordinate with the CFTOD Construction Project Manager to allow for all materials testing. The Owner shall pay for costs associated with the initial testing but the Contractor shall be liable for costs associated with retesting as a result of initial test failure due to deficiencies in the Contractor's work efforts.

B. The Contractor shall coordinate its work with the CFTOD Construction Project Manager and with the Owner’s Separate Contractors. The Contractor shall sequence its Work, as required by the CFTOD Construction Project Manager, with the work of the Owner’s Separate Contractors at no additional cost to the Owner.

C. The Contractor is required to coordinate with the delivery of any and all Owner Furnish, Owner or Contractor installed items.

D. The Contractor shall coordinate with the CFTOD Construction Project Manager for site access/control for The District Fire Department.

E. The Owner, reserve the right of access to any part of the job site, at any time, for the purpose of observation, or to install other work, either with its own forces of with other contractors.

2.04 Worker Conduct and Clothing

A. The Contractor is responsible at all times for the proper conduct of its personnel and that of its subcontractors and suppliers. The Contractor shall restrict its personnel to the job site and immediate vicinity thereof and shall endeavor to prevent discordant relationships between its personnel and that of any adjacent property owner or resident.

B. The Contractor shall enforce strict discipline and good order among employees and other workers related to the performance of the Work. Under no circumstances will behavior offensive to building occupants or the general public be tolerated, and Contractor shall immediately remove and further ban from the job site any persons failing to comply with this standard.

C. The Contractor shall ensure its personnel are properly dressed with O.S.H.A. approved clothing and safety gear, including but not limited to, hard hats, work shoes, shirts and long pants, as appropriate for the performance of the Work. Shorts, sleeveless shirts (tank tops) or clothing bearing offensive marks or wording are not permitted to be worn on the job site. The Owner shall solely determine whether any such clothing is or is not permissible.

2.05 Surveying

A. Refer to Specification Section 01050 – Field Engineering, contained in the Project Manual, for specifications governing field engineering and surveying.

B. The Contractor shall inspect the site, observe the existing conditions and grades, and make reasonable measurements to verify existing conditions prior to its bid.

C. After award of the contract and within fourteen (14) days of receiving a Limited Notice to Proceed, the Contractor shall complete all survey work required to verify and accept the accuracy of the grades noted as existing on the bid drawings and the accuracy the as-built drawings provided by the Owner’s Separate Contractor. At the end of the fourteen-day discovery period, the Contractor shall provide written acceptance of the existing grades or provide written documentation of any material deviation it has discovered between the existing conditions and the conditions noted as existing on the bid drawings and as-built drawings. All claims shall be made in strict accord with Article 13 of the General Conditions of the Contract for Construction. Failure to give such notice or to provide substantiation thereof shall constitute a waiver of the claim and acceptance of the existing grades.

D. The Contractor shall verify forms prior to pouring, or placing, critical components of structures.

E. It is the responsibility of the Contractor to generate survey control, layout, and as-built information as required in the contract documents. At no time will the project CAD design files be given to the Contractor.

F. The Contractor verify the location of all existing utilities or obscured existing improvements or construction indicated on Drawings to be proximate to or affected by the Work prior to commencement of excavation or demolition in any given area.

2.06 Testing and Inspection

A. Refer to Specification Section 01455 – Testing & Inspection Services, contained in the Project Manual, for specifications governing soils and materials testing and inspection. The Owner reserves the right to re-test and approve or disapprove the results of the Testing and Inspection.

B. The project specifications utilize Florida Department of Transportation specifications governing acceptance of materials used in the performance of the Work. Because the Owner has no affiliation with the Florida Department of Transportation’s materials testing laboratories where such materials are deemed acceptable, the Owner has developed an alternative Materials Acceptance Criteria Matrix governing the manner in which materials will be accepted on the project.

2.07 Surface Water Management and Environmental Controls

A. The Contractor shall provide and maintain all necessary erosion control in accordance with paragraph 1.3.5 above, the plans, and Specification Section 01560, entitled Erosion Control and Dewatering, contained in the Project Manual.

B. The Contractor shall submit for approval any and all Erosion and Sedimentation control measures necessary/required to remedy waterway conditions negatively impacted by or resulting from contractor operations. Contractor will implement such approved measures at no additional cost to the owner.

2.08 Temporary Fencing

A. Geogrid Fencing and Silt Barriers:

1. When required by the Contract Documents, geogrid fencing and silt barriers shall be provided and maintained along the boundaries of all designated tree preservation and protected wetland areas. The Contractor shall not disturb the trees or vegetation within such areas unless directed otherwise by the Owner.

2. Geogrid fencing shall be provided and maintained along jurisdictional wetland buffers excluding those wetlands (if any) to be removed under this Contract. Silt barrier shall be provided and maintained along areas designated on Drawings.

3. The Contractor shall inspect all geogrid fences and silt barriers daily and shall immediately make necessary repairs to any damaged or improperly functioning geogrid fences and/or silt barriers.

2.09 Permits and Permit Fees

A. All Permits required for any part of the Contractor’s Work (except those permits obtained directly by the Owner, as further enumerated below) shall be procured and paid for by the Contractor. This shall apply also to those permits required to be obtained by the Contractor in the name of the Owner for the Owner’s own temporary construction office facilities, if any. The costs for the required permits (except those permits obtained directly by the Owner) are included in the Contract Sum. Before applying for any permit, the Contractor shall present a draft application to the Owner for review.

B. The Contractor shall apply for a de-watering permit during the pre-construction phase. The Contractor shall prepare and submit the NOI to the Owner prior to submitting to the FDEP during the pre-construction phase. In addition, the Contractor shall apply for any and all permits that are required by CFTOD Building and Safety and CFTOD Planning and Engineering during the pre-construction period.

C. The Contractor shall obtain, secure and pay for the following permits:

1. NOI NPDES – EPA Environmental Permit

2. County Recorded NOC

3. SWPPP, Turbidity Control Plan and Dewatering Permit (see Specification Section 01560)

4. CFTOD Building Permit and all applicable sub permits

5. CFTOD Haul Permit and any required Right of Way Permit

6. RCES Dig permit

D. The Owner shall provide to the Contractor the following:

1. N/A

E. The Contractor shall submit to the Owner a copy of ALL permits required to be obtained by this Contractor, which are required for the performance of this Work.

2.010 Job Site Cleanliness, Construction Operations Upon and Affecting the Use of the Project Site

A. Refer to Specification Section 01710 – Cleaning, contained in the Project Manual, for specifications governing cleaning and job site cleanliness.

B. The Contractor shall cause no dirt or debris to be deposited on any public or private roadways and must clean up same in an expeditious manner if such dirt or debris occurs due to this Contractor's operation. If the Contractor fails to perform, clean-up will be performed by others and all costs for same will be deducted from monies due or owing the Contractor.

C. The Contractor shall clean the tires of all vehicles as they exit the job site and enter onto the public roadway or private driveways. The Contractor shall provide rotary power broom equipment on site for daily sweeping as needed and as requested by the Owner.

D. The Contractor shall use "whisperized" construction equipment. Noise levels shall be within those levels acceptable by the authorities having jurisdiction.

E. Material deliveries shall generally be made during normal working hours. Where special deliveries must be made at other times Contractor shall request approval of same. If such request is approved Contractor shall arrange for the proper labor force to receive and unload materials promptly.

F. The Contractor shall be responsible to consolidate and secure all equipment and materials at the job site. The Owner will not provide any security for material and equipment stored on site for contractors working at the Project site.

G. On site storage of fuel will not be permitted without prior written approval of the Owner and approval from all appropriate local, state, and federal agencies having jurisdiction.

H. Any and all damage to property resulting directly or indirectly by the Contractor's…