BP3 Bidding Schedule 6.10.2026.pdf
PDF 215 KB Posted
- Attached to
- Building Construction & Renovation State and local contract opportunity
- Solicitation number
- RFP MAT 260000002260 2
- Issued by
- Van Buren County, Michigan
About this file
This is a bidding schedule document for BP3 (Building, Planning, and Procurement) related to a building construction and renovation project in Michigan. The document outlines the timeline and critical dates for the solicitation process, establishing a structured approach to vendor engagement and bid submission. The schedule specifies key milestones including the release date, pre-bid meeting or site visit opportunities, the deadline for submission of questions or requests for clarification, the bid opening date, and the anticipated award date. These dates are designed to provide potential bidders with adequate notice and opportunity to prepare competitive proposals while maintaining an organized procurement process. The contract term and any renewal options would be defined in the associated solicitation documents and bid specifications.
The bidding schedule serves as a procedural roadmap for all parties involved in the construction and renovation project, ensuring transparency and consistent application of timelines across the procurement process. Specific pricing terms, set-aside provisions for disadvantaged or minority-owned businesses, details regarding incumbent contractors, and funding sources and amounts would be documented in the primary solicitation package and related exhibits. Bidders should reference the complete solicitation documents and any addenda issued to understand all requirements, specifications, and evaluation criteria applicable to this Michigan building construction and renovation opportunity.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| BP3 Phasing Plan 6.10.2026.pdf | ||
| Bid location.pdf | ||
| Builder's Sites Advertisement for Bids BP3 - MCS Addit & Renov.pdf | ||
| 1. AVB 00 0000 MCS Bidders Instructions & Req BP3 MCS MS Addit & Renov.pdf | ||
| Prevailing Wage Rates - MCS Middle School Additions & Renovations.pdf | ||
| AVB Health Safety Program v30 08.29.2023.pdf | ||
| MCS BP3 MS Add & Ren - Addendum 1 - For Release.pdf | ||
| 2. AVB 01 0000 Subcontractor Gen Req - BP3 MCS MS Addit & Renov.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task Name Duration Start Finish
1 Project Administration 180 days Wed 6/3/26 Tue 2/9/27
2 CDs Received from TP 1 day Wed 6/3/26 Wed 6/3/26
3 State Plan Review - BCC and BFS 3 mons Thu 6/4/26 Wed 8/26/26
4 AVB Bid Doc Prep 7 days Thu 6/4/26 Fri 6/12/26
5 Bid Package Published 1 day Mon 6/15/26 Mon 6/15/26
6 Bidding 20 days Tue 6/16/26 Mon 7/13/26
7 Addenda with Pre-Bid RFIs 0 days Mon 6/29/26 Mon 6/29/26
8 Bid Opening 1 day Tue 7/14/26 Tue 7/14/26
9 Post Bid Interviews 15 days Wed 7/15/26 Tue 8/4/26
10 GMP Sent to District 1 day Wed 8/5/26 Wed 8/5/26
11 Board of Education GMP Approval 1 day Mon 8/10/26 Mon 8/10/26
12 Notices of Intent & Subcontracting 15 days Wed 8/5/26 Tue 8/25/26
13 Long Lead Time Submittals 130 days Wed 8/12/26 Tue 2/9/27
14 Concrete Rebar & Mix Designs 10 days Wed 8/12/26 Tue 8/25/26
15 Concrete Rebar & Mix Design Approval 5 days Wed 8/26/26 Tue 9/1/26
16 Concrete Rebar Procurement 10 days Wed 9/2/26 Tue 9/15/26
17 Masonry Rebar 10 days Wed 8/12/26 Tue 8/25/26
18 Masonry Rebar Approval 5 days Wed 8/26/26 Tue 9/1/26
19 Masonry Rebar Procurement 10 days Wed 9/2/26 Tue 9/15/26
20 Steel Lintels & Embeds 10 days Wed 8/12/26 Tue 8/25/26
21 Steel Lintels & Embeds Approval 5 days Wed 8/26/26 Tue 9/1/26
22 Steel Lintels & Embeds Fabrication 10 days Wed 9/2/26 Tue 9/15/26
23 Steel Joists & Deck 20 days Wed 8/12/26 Tue 9/8/26
24 Steel Joists & Deck Approval 10 days Wed 9/9/26 Tue 9/22/26
25 Steel Joists & Deck Procurement 6 wks Wed 9/23/26 Tue 11/3/26
26 Electrical Gear 15 days Wed 8/12/26 Tue 9/1/26
27 Electrical Gear Approval 10 days Wed 9/2/26 Tue 9/15/26
28 Electrical Gear Procurement 16 wks Wed 9/16/26 Tue 1/5/27
29 Mechanical Equipment 10 days Wed 8/12/26 Tue 8/25/26
30 Mechanical Equipment Approval 10 days Wed 8/26/26 Tue 9/8/26
31 Mechanical Equipment Procurement 10 wks Wed 9/9/26 Tue 11/17/26
32 Casework 20 days Wed 8/12/26 Tue 9/8/26
33 Casework Approval 10 days Wed 9/9/26 Tue 9/22/26
34 Casework Fabrication 20 wks Wed 9/23/26 Tue 2/9/27
35 Doors & Hardware 15 days Wed 8/12/26 Tue 9/1/26
36 Doors & Hardware Approval 10 days Wed 9/2/26 Tue 9/15/26
37 Doors & Hardware Procurement 16 wks Wed 9/16/26 Tue 1/5/27
39 MCS School Schedule 465 days Mon 8/24/26 Mon 6/5/28
40 Start of School Year 2026 0 days Mon 8/24/26 Mon 8/24/26
41 Winter Break 2026 10 days Mon 12/21/26Fri 1/1/27
42 Spring Break 2027 6 days Fri 4/2/27 Fri 4/9/27
43 Start of Summer Break 2027 0 days Mon 6/7/27 Mon 6/7/27
44 Start of School Year 2027 0 days Mon 8/23/27 Mon 8/23/27
45 Winter Break 2027 10 days Mon 12/20/27Fri 12/31/27
46 Spring Break 2028 6 days Fri 3/31/28 Fri 4/7/28
47 Start of Summer 2028 0 days Mon 6/5/28 Mon 6/5/28
49 PHASE 1 - MIDDLE SCHOOL OFFICE 256 days Mon 8/31/26 Mon 8/23/27
50 1A - Office Addition 190 days Mon 8/31/26 Fri 5/21/27
51 Mobilization - Safety & Barriers 5 days Mon 8/31/26 Fri 9/4/26
52 Strip Topsoil & Excavate Footings 5 days Mon 9/7/26 Fri 9/11/26
53 Form & Pour Footings & Foundaton Walls 15 days Wed 9/16/26 Tue 10/6/26
54 Backfill Foundations 3 days Wed 10/7/26 Fri 10/9/26
55 Underground Rough-ins 15 days Mon 10/12/26Fri 10/30/26
56 Slab-on-Grade Prep 1 day Mon 11/2/26 Mon 11/2/26
57 Slab-on-Grade 3 days Tue 11/3/26 Thu 11/5/26
58 Lintel & Embed Delivery 1 day Wed 9/16/26 Wed 9/16/26
59 Bearing Masonry 15 days Fri 11/6/26 Thu 11/26/26
60 Structural Steel - Joists & Deck 10 days Fri 11/27/26 Thu 12/10/26
61 Temp Enclosure Windows 3 days Fri 12/11/26 Tue 12/15/26
62 Exterior Brick 20 days Fri 12/11/26 Thu 1/7/27
63 Exterior Windows 10 days Fri 1/8/27 Thu 1/21/27
64 Storm Piping 5 days Fri 12/11/26 Thu 12/17/26
65 Roofing 10 days Fri 12/11/26 Thu 12/24/26
66 Steel Stud Framing 15 days Fri 12/11/26 Thu 12/31/26
67 Door Frames 10 days Fri 12/11/26 Thu 12/24/26
68 MEP Rough-Ins 25 days Fri 12/18/26 Thu 1/21/27
69 In Wall Inspections 1 day Fri 1/8/27 Fri 1/8/27
70 Insulation 3 days Mon 1/11/27 Wed 1/13/27
71 Hang & Finish Drywall 20 days Mon 1/11/27 Fri 2/5/27
72 Prime & Paint 15 days Mon 2/8/27 Fri 2/26/27
73 Ceiling Grid & Cut Pads 10 days Mon 2/22/27 Fri 3/5/27
74 MEP Finishes 20 days Mon 3/1/27 Fri 3/26/27
75 Casework 10 days Mon 3/1/27 Fri 3/12/27
76 Flooring 15 days Mon 3/15/27 Fri 4/2/27
77 Doors & Hardware 10 days Mon 4/5/27 Fri 4/16/27
78 Final Clean 5 days Mon 4/19/27 Fri 4/23/27
79 Punchlist 10 days Mon 4/26/27 Fri 5/7/27
80 Furniture Move-In 10 days Mon 5/10/27 Fri 5/21/27
81 1B - Renovation of Existing Student Services 81 days Mon 3/29/27 Mon 7/19/27
82 Relocate Deans & Counselor Offices (MCS) 5 days Mon 3/29/27 Fri 4/2/27
83 Barriers & Temp Rated Partitions (SPRING BREAK) 5 days Wed 3/31/27 Tue 4/6/27
84 Selective Demolition 10 days Wed 4/7/27 Tue 4/20/27
85 Brick/Block Tooth-in at Firewall to Offices 5 days Wed 4/21/27 Tue 4/27/27
86 Continuation of Sanitary & Slab Pour Back 5 days Wed 4/21/27 Tue 4/27/27
87 Steel Stud Framing 10 days Wed 4/28/27 Tue 5/11/27
88 Door Frames 4 days Wed 4/28/27 Mon 5/3/27
89 MEP Rough-Ins 20 days Wed 4/28/27 Tue 5/25/27
90 In Wall Inspections 3 days Wed 5/12/27 Fri 5/14/27
Bid Package Published
Bidding
Addenda with Pre-Bid RFIs 6/29
Bid Opening
Post Bid Interviews
GMP Sent to District
Board of Education GMP Approval
Notices of Intent & Subcontracting
Concrete Rebar & Mix Designs
Concrete Rebar & Mix Design Approval
Concrete Rebar Procurement
Masonry Rebar
Masonry Rebar Approval
Masonry Rebar Procurement
Steel Lintels & Embeds
Steel Lintels & Embeds Approval
Steel Lintels & Embeds Fabrication
Steel Joists & Deck
Steel Joists & Deck Approval
Steel Joists & Deck Procurement
Electrical Gear
Electrical Gear Approval
Electrical Gear Procurement
Mechanical Equipment
Mechanical Equipment Approval
Mechanical Equipment Procurement
Casework
Casework Approval
Casework Fabrication
Doors & Hardware
Doors & Hardware Approval
Doors & Hardware Procurement
Start of School Year 2026 8/24
Winter Break 2026
Spring Break 2027
Start of Summer Break 2027 6/7
Start of School Year 2027 8/23
Winter Break 2027
Spring Break 2028
Start of Summer 2028 6/5
Mobilization - Safety & Barriers
Strip Topsoil & Excavate Footings
Form & Pour Footings & Foundaton Walls
Backfill Foundations
Underground Rough-ins
Slab-on-Grade Prep
Slab-on-Grade
Lintel & Embed Delivery
Bearing Masonry
Structural Steel - Joists & Deck
Temp Enclosure Windows
Exterior Brick
Exterior Windows
Storm Piping
Roofing
Steel Stud Framing
Door Frames
MEP Rough-Ins
In Wall Inspections
Insulation
Hang & Finish Drywall
Prime & Paint
Ceiling Grid & Cut Pads
MEP Finishes
Casework
Flooring
Doors & Hardware
Final Clean
Punchlist
Furniture Move-In
Relocate Deans & Counselor Offices (MCS)
Barriers & Temp Rated Partitions (SPRING BREAK)
Selective Demolition
Brick/Block Tooth-in at Firewall to Offices
Continuation of Sanitary & Slab Pour Back
Steel Stud Framing
Door Frames
MEP Rough-Ins
In Wall Inspections
7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
Jun '26 Jul '26 Aug '26 Sep '26 Oct '26 Nov '26 Dec '26 Jan '27 Feb '27 Mar '27 Apr '27 May '27 Jun '27 Jul '27 Aug '27 Sep '27 Oct '27 Nov '27 Dec '27 Jan '28 Feb '28 Mar '28 Apr '28 May '28 Jun '28
MCS 2024 Bond
BP3 - Middle School Office Addition, Cafeteria Renovation, and MEP Upgrades
Bidding Schedule
MCS BP3 Middle School Bidding Schedule 6.10.2026 Page 1 Wed 6/10/26
91 Insulation 3 days Mon 5/17/27 Wed 5/19/27
92 Hang & Finish Drywall 12 days Thu 5/20/27 Fri 6/4/27
93 Remove Temp Barriers (Start of Summer) 3 days Mon 6/7/27 Wed 6/9/27
94 Prime & Paint 8 days Mon 6/7/27 Wed 6/16/27
95 Ceiling Grid & Cut Pads 5 days Thu 6/17/27 Wed 6/23/27
96 MEP Finishes 10 days Thu 6/17/27 Wed 6/30/27
97 Casework 5 days Thu 6/24/27 Wed 6/30/27
98 Flooring (Include Lobby) 8 days Thu 7/1/27 Mon 7/12/27
99 Doors & Hardware 5 days Tue 7/13/27 Mon 7/19/27
100 1C - Vestibule Entry & Canopy 39 days Mon 6/7/27 Thu 7/29/27
101 Demo Existing Vestibule 3 days Mon 6/7/27 Wed 6/9/27
102 Form & Pour Foundations 5 days Thu 6/10/27 Wed 6/16/27
103 Backfill & Prep for SOG & Sidewalk 3 days Thu 6/17/27 Mon 6/21/27
104 Slab-on-Grade Pour 2 days Tue 6/22/27 Wed 6/23/27
105 Sidewalk Pour 3 days Thu 6/24/27 Mon 6/28/27
106 Bearing Masonry 5 days Thu 6/24/27 Wed 6/30/27
107 Structural Steel - Joists & Deck 5 days Thu 7/1/27 Wed 7/7/27
108 Exterior Brick 6 days Thu 7/8/27 Thu 7/15/27
109 Exterior Windows & Door Systems 8 days Fri 7/16/27 Tue 7/27/27
110 Canopy Roofing 5 days Fri 7/16/27 Thu 7/22/27
111 Canopy Metal Panel 10 days Fri 7/16/27 Thu 7/29/27
112 MEP Systems Start-up & Testing 10 days Thu 7/1/27 Wed 7/14/27
113 Final Inspections 5 days Thu 7/15/27 Wed 7/21/27
114 Final Cleaning 5 days Tue 7/20/27 Mon 7/26/27
115 Punchlist 10 days Tue 7/27/27 Mon 8/9/27
116 Furniture Installation (MCS & Veridus) 10 days Tue 8/10/27 Mon 8/23/27
117 Middle School Staff Move-in 0 days Mon 8/23/27 Mon 8/23/27
119 PHASE 2 - Staff Support Area (Former Den) & Security Doors 54 days Mon 6/7/27 Thu 8/19/27
120 Selective Demo 2 days Mon 6/7/27 Tue 6/8/27
121 Underground Sanitary & Slab Pour Back 3 days Wed 6/9/27 Fri 6/11/27
122 Door Frames & Block Tooth-in 5 days Wed 6/9/27 Tue 6/15/27
123 Steel Stud Framing 3 days Wed 6/16/27 Fri 6/18/27
124 MEP Rough-ins 10 days Wed 6/16/27 Tue 6/29/27
125 In Wall Inspection 1 day Wed 6/23/27 Wed 6/23/27
126 Insulation 1 day Thu 6/24/27 Thu 6/24/27
127 Hang & Finish Drywall 8 days Fri 6/25/27 Tue 7/6/27
128 Prime & Paint 5 days Wed 7/7/27 Tue 7/13/27
129 Ceiling Grid & Cut Pads 4 days Wed 7/14/27 Mon 7/19/27
130 MEP Finishes 4 days Tue 7/20/27 Fri 7/23/27
131 Casework 3 days Tue 7/20/27 Thu 7/22/27
132 Flooring 5 days Fri 7/23/27 Thu 7/29/27
133 Doors & Hardware 3 days Fri 7/30/27 Tue 8/3/27
134 Final Cleaning 2 days Wed 8/4/27 Thu 8/5/27
135 Final Inspection 2 days Wed 8/4/27 Thu 8/5/27
136 Punchlist 5 days Fri 8/6/27 Thu 8/12/27
137 Turnover 0 days Thu 8/12/27 Thu 8/12/27
138 Furniture Installation (MCS & Veridus) 5 days Fri 8/13/27 Thu 8/19/27
140 PHASE 3 - CHILLER, MDP/Tx, Fire Alarm 158 days Wed 1/6/27 Fri 8/13/27
141 MDP & Tx Change 123 days Wed 1/6/27 Fri 6/25/27
142 Set New MDP Gear Tubs 10 days Wed 1/6/27 Tue 1/19/27
143 Feeds from Exist MSP to MDP 20 days Wed 1/20/27 Tue 2/16/27
144 Feeds from MDP to New Tx 15 days Wed 2/17/27 Tue 3/9/27
145 Utility Feeds New Tx from Source 5 days Fri 4/2/27 Thu 4/8/27
146 Set New Tx (with AEP Utility) 5 days Fri 4/9/27 Thu 4/15/27
147 Make MDP Terminations 15 days Fri 4/16/27 Thu 5/6/27
148 Temporary Generator Rental 15 days Mon 6/7/27 Fri 6/25/27
149 MDP/Tx Change Over 15 days Mon 6/7/27 Fri 6/25/27
150 Chiller Replacement 85 days Mon 4/5/27 Fri 7/30/27
151 Disconnect Elementary Chiller to be Moved 10 days Mon 4/5/27 Fri 4/16/27
152 Disconnect Existing Middle School Chiller 10 days Mon 6/7/27 Fri 6/18/27
153 Remove Existing Chiller 5 days Mon 6/21/27 Fri 6/25/27
154 Place Relocated Chiller (from Elem) 5 days Mon 6/28/27 Fri 7/2/27
155 Make Chiller Connection (Piping & Controls) 15 days Mon 7/5/27 Fri 7/23/27
156 Chiller Testing 5 days Mon 7/26/27 Fri 7/30/27
157 Fire Alarm Replacement 50 days Mon 6/7/27 Fri 8/13/27
158 *New Panel Installed During Phase 1A Scope* 0 days Mon 6/7/27 Mon 6/7/27
159 Existing System Demo (Fire Riser to Remain) 15 days Mon 6/7/27 Fri 6/25/27
160 Device Replacement Throughout Corridors & Classrooms 30 days Mon 6/7/27 Fri 7/16/27
161 Testing & TroubleShooting 10 days Mon 7/19/27 Fri 7/30/27
162 Inspections 10 days Mon 8/2/27 Fri 8/13/27
164 PHASE 4 - CAFETERIA, KITCHEN, AND SERVERY 215 days Mon 6/7/27 Fri 3/31/28
165 Selective Demo 15 days Mon 6/7/27 Fri 6/25/27
166 MEP Demo 15 days Mon 6/7/27 Fri 6/25/27
167 Temp Exterior Enclosures 5 days Mon 6/7/27 Fri 6/11/27
168 Sawcut for Footings 5 days Mon 6/21/27 Fri 6/25/27
169 Interior Footings & Slab Pour Back 10 days Mon 6/28/27 Fri 7/9/27
170 Corridor CMU Walls 10 days Mon 7/12/27 Fri 7/23/27
171 In-Wall Rough-ins 15 days Mon 7/12/27 Fri 7/30/27
172 Corridor Side Paint 10 days Mon 7/26/27 Fri 8/6/27
173 Corridor Ceiling Grids & Pads 10 days Mon 8/2/27 Fri 8/13/27
174 Corridor Flooring & Base 10 days Mon 8/9/27 Fri 8/20/27
175 Temp Enclosures/Rated Barriers for Start of School Year 5 days Mon 8/23/27 Fri 8/27/27
176 Exterior CMU Walls & Brick 12 days Mon 7/26/27 Tue 8/10/27
177 Exterior Windows & Doors 10 days Wed 8/11/27 Tue 8/24/27
178 Sawcut for Underground Rough-Ins 10 days Mon 8/30/27 Fri 9/10/27
179 Underground Rough-Ins 20 days Mon 9/13/27 Fri 10/8/27
180 Slab Pour Back 5 days Mon 10/11/27Fri 10/15/27
Insulation
Hang & Finish Drywall
Remove Temp Barriers (Start of Summer)
Prime & Paint
Ceiling Grid & Cut Pads
MEP Finishes
Casework
Flooring (Include Lobby)
Doors & Hardware
Demo Existing Vestibule
Form & Pour Foundations
Backfill & Prep for SOG & Sidewalk
Slab-on-Grade Pour
Sidewalk Pour
Bearing Masonry
Structural Steel - Joists & Deck
Exterior Brick
Exterior Windows & Door Systems
Canopy Roofing
Canopy Metal Panel
MEP Systems Start-up & Testing
Final Inspections
Final Cleaning
Punchlist
Furniture Installation (MCS & Veridus)
Middle School Staff Move-in 8/23
Selective Demo
Underground Sanitary & Slab Pour Back
Door Frames & Block Tooth-in
Steel Stud Framing
MEP Rough-ins
In Wall Inspection
Insulation
Hang & Finish Drywall
Prime & Paint
Ceiling Grid & Cut Pads
MEP Finishes
Casework
Flooring
Doors & Hardware
Final Cleaning
Final Inspection
Punchlist
Turnover 8/12
Furniture Installation (MCS & Veridus)
Set New MDP Gear Tubs
Feeds from Exist MSP to MDP
Feeds from MDP to New Tx
Utility Feeds New Tx from Source
Set New Tx (with AEP Utility)
Make MDP Terminations
Temporary Generator Rental
MDP/Tx Change Over
Disconnect Elementary Chiller to be Moved
Disconnect Existing Middle School Chiller
Remove Existing Chiller
Place Relocated Chiller (from Elem)
Make Chiller Connection (Piping & Controls)
Chiller Testing
*New Panel Installed During Phase 1A Scope* 6/7
Existing System Demo (Fire Riser to Remain)
Device Replacement Throughout Corridors & Classrooms
Testing & TroubleShooting
Inspections
Selective Demo
MEP Demo
Temp Exterior Enclosures
Sawcut for Footings
Interior Footings & Slab Pour Back
Corridor CMU Walls
In-Wall Rough-ins
Corridor Side Paint
Corridor Ceiling Grids & Pads
Corridor Flooring & Base
Temp Enclosures/Rated Barriers for Start of School Year
Exterior CMU Walls & Brick
Exterior Windows & Doors
Sawcut for Underground Rough-Ins
Underground Rough-Ins
Slab Pour Back
7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
Jun '26 Jul '26 Aug '26 Sep '26 Oct '26 Nov '26 Dec '26 Jan '27 Feb '27 Mar '27 Apr '27 May '27 Jun '27 Jul '27 Aug '27 Sep '27 Oct '27 Nov '27 Dec '27 Jan '28 Feb '28 Mar '28 Apr '28 May '28 Jun '28
MCS 2024 Bond
BP3 - Middle School Office Addition, Cafeteria Renovation, and MEP Upgrades
MCS BP3 Middle School Bidding Schedule 6.10.2026 Page 2 Wed 6/10/26
181 Kitchen & Servery CMU Walls 20 days Mon 10/18/27Fri 11/12/27
182 In Wall Rough-ins - Kitchen Servery 20 days Mon 10/18/27Fri 11/12/27
183 MEP Overhead Rough-ins 105 days Mon 6/28/27 Fri 11/19/27
184 Prime & Paint 15 days Mon 11/22/27Fri 12/10/27
185 Kitchen & Servery Ceilings 10 days Mon 11/29/27Fri 12/10/27
186 Epoxy Flooring 20 days Mon 12/13/27Fri 1/7/28
187 Kitchen Equipment Installation 25 days Mon 1/10/28 Fri 2/11/28
188 Cafeteria Ceilings 15 days Mon 12/13/27Fri 12/31/27
189 LVT Flooring 10 days Mon 1/3/28 Fri 1/14/28
190 Doors & Hardware 10 days Mon 1/17/28 Fri 1/28/28
191 MEP Finishes 25 days Mon 12/13/27Fri 1/14/28
192 MEP Start-up 10 days Mon 1/17/28 Fri 1/28/28
193 Kitchen Equipment Start-up 10 days Mon 2/14/28 Fri 2/25/28
194 Final Inspections 10 days Mon 2/28/28 Fri 3/10/28
195 Final Cleaning 5 days Mon 2/28/28 Fri 3/3/28
196 Punchlist 15 days Mon 3/6/28 Fri 3/24/28
197 Furniture Move-In (MCS & Veridus) 5 days Mon 3/27/28 Fri 3/31/28
198 Turnover 0 days Fri 3/31/28 Fri 3/31/28
Kitchen & Servery CMU Walls
In Wall Rough-ins - Kitchen Servery
MEP Overhead Rough-ins
Prime & Paint
Kitchen & Servery Ceilings
Epoxy Flooring
Kitchen Equipment Installation
Cafeteria Ceilings
LVT Flooring
Doors & Hardware
MEP Finishes
MEP Start-up
Kitchen Equipment Start-up
Final Inspections
Final Cleaning
Punchlist
Furniture Move-In (MCS & Veridus)
Turnover 3/31
7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
Jun '26 Jul '26 Aug '26 Sep '26 Oct '26 Nov '26 Dec '26 Jan '27 Feb '27 Mar '27 Apr '27 May '27 Jun '27 Jul '27 Aug '27 Sep '27 Oct '27 Nov '27 Dec '27 Jan '28 Feb '28 Mar '28 Apr '28 May '28 Jun '28
MCS 2024 Bond
BP3 - Middle School Office Addition, Cafeteria Renovation, and MEP Upgrades
MCS BP3 Middle School Bidding Schedule 6.10.2026 Page 3 Wed 6/10/26