Boston-A-3.pdf

PDF 358 KB Posted

Attached to
Boston- Cooling Tower Replacements at Haymarket Center
Solicitation number
BD-27-1030-CPO1-CPO1-131243
Issued by
Suffolk County, Massachusetts

About this file

This is Addendum No. 3 to the contract documents for the Boston Cooling Tower Replacements at Haymarket Center project, issued by the Massachusetts Department of Transportation on July 30, 2026. The addendum transmits revisions to the contract documents and supersedes previously filed sub-bid information with updated Final Filed Sub-Bid Results posted on COMMBUYS. The revision includes an updated Plan Sheet M-000 containing HVAC legend, notes, details, and schedules. Sub-bids were opened and read on July 27, 2026 at 2:00 p.m., with general bids scheduled to be opened and read on August 5, 2026 at 2:00 p.m. Prospective bidders are required to acknowledge Addendum No. 3 in their proposal files before submitting their bids. The project scope includes the installation of two new stainless steel cooling towers (Model NC8401NAN1 with 118 CFM, 60 MBH cooling capacity), a new ceiling-mounted air handling unit (BCHE054 with 1,800 CFM capacity), and a new exhaust fan (AX-36-25-0420-VG-4 with 1,560 CFM capacity) for the generator room. All existing HVAC systems, ductwork, piping, and controls shall remain unless otherwise noted, with the contractor responsible for reconnecting piping and controls and providing system startup and commissioning.

The addendum includes detailed technical specifications and design details for equipment installation, including requirements for vibration isolation, internal heater provisions on fan motors, stainless steel construction, water inlet configurations, equalizing line connections, vibration switches, and electric water level controls on cooling towers. The contractor is required to coordinate exact equipment locations with existing field conditions per manufacturer instructions while maintaining recommended clearances, with any discrepancies to be brought to the architect/engineer for clarification. New chilled water supply and return piping (3/4" PVC) must be provided to connect to existing piping, with air handling unit condensate drain routed to the floor drain. The drawings are diagrammatic and indicate approximate equipment locations; the contractor must verify existing conditions in the field and coordinate with the supporting equipment requirements specified by the cooling tower manufacturer. All work shall comply with the sequence of operation specified for the exhaust fan controls and intake damper interlock system.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

July 30, 2026

Proposal No. 616454-134457

ADDENDUM NO. 3

To Prospective Bidders and Others on:

BOSTON

COOLING TOWER REPLACEMENTS AT HAYMARKET CENER

SUB-BIDS OPENED AND READ: JULY 27, 2026 @ 2:00 P.M.

GENERAL BIDS TO BE OPENED AND READ: AUGUST 5, 2026 @ 2:00 P.M.

Transmitting changes to the Contract Documents as follows:

FILED SUB-BID RESULTS AND RESTRICTIONS

The filed sub-bid information for the Project in Addendum No. 2 is superseded by the filed sub-bid information for the Project in the document entitled Final Filed Sub-Bid Results that is posted on

COMMBUYS.”

DRAWING REVISIONS

Revised Plan Sheet M-000

Please take note of the above and acknowledge Addendum No. 3 in your Proposal file before submitting your bid.

HVAC LEGEND

CT

AHU

EF

COOLING TOWER

AIR HANDLING UNIT

EXHUAST FAN

CHWS&R CHILLED WATER SUPPLY AND RETURN

AFF ABOVE FINISHED FLOOR

HP HORSE POWER

DN DOWN

HVAC HEATING, VENTILATING & AIR CONDITIONING

DOV DRAIN-OFF VALVE

CFM CUBIC FEET PER MINUTE

EA EXHAUST AIR

OA OUTDOOR AIR

SA SUPPLY AIR

RA RETURN AIR

EC ELECTRICAL CONTRACTOR

GC GENERAL CONTRACTOR

PC PLUMBING CONTRACTOR

BFP BACKFLOW PREVENTER

CD CONDENSATE DRAIN

ESP EXTERNAL STATIC PRESSURE

TYP. TYPICAL

ROUND AIR DUCT UP

ROUND AIR DUCT DOWN

SUPPLY AIR DUCT UP

SUPPLY AIR DUCT DOWN

RETURN/EXHAUST AIR DUCT UP

RETURN/EXHAUST AIR DUCT DOWN

MOTORIZED DAMPER

MD

CONDENSATE WATER SUPPLY

CONDENSATE WATER RETURN

CONDENSATE DRAIN

CHILLED WATER SUPPLY

CHILLED WATER RETURN

MAKE UP WATER PIPE

THERMOSTAT-ELECTRICT

MW

CHWR

CHWS

CD

CNR

CNS PIPE UP

PIPE DOWN

PIPE TEE DROP

PIPE STUB UP W/FLOW ARROW

PIPE ANCHOR

PIPE GUIDE

GATE VALVE

STRAINER

CONTROL VALVE

DRAIN-OFF VALVE W/UNION

DOV

BUTTERFLY VALVE

GLOBE VALVE

BALL VALVE

FLEXIBLE PIPE

THERMOMETER

PRESSURE GAUGE

AUTOMATIC AIR VENT

BACKDRAFT DAMPER

BD

CNS&R CONDENSATE WATER SUPPLY AND RETURN

CONNECT NEW TO EXISTING

1.

2.

3.

4.

ALL EXISTING HVAC SYSTEMS, DUCTWORK, DIFFUSERS, REGISTERS & GRILLES,

PIPING, CONTROLS ETC. SERVING THE BUILDING SHALL REMAIN UNLESS

OTHERWISE NOTED.

CONTRACTOR SHALL RECONNECT PIPING AND CONTROLS TO THE REINSTALLED

EQUIPMENT AND PROVIDE START-UP FOR ALL EQUIPMENT AND CONFIRM

RECONNECTED EQUIPMENT WORKS WITH EXISTING CONTROL SEQUENCE.

CONTRACTOR SHALL LOCATE ALL NEW EQUIPMENT INCLUDING BUT NOT LIMITED TO

THE COOLING TOWERS, FANCOIL UNITS AND EXHAUST FAN ETC. PER MANUFACTURER'S

INSTRUCTIONS MAINTAINING RECOMMENDED CLEARANCES.

CONTRACTOR SHALL COORDINATE THE EXACT LOCATIONS OF ALL EQUIPMENT,

DUCTWORK, PIPING AND ASSOCIATED ACCESSORIES WITH EXISTING

CONDITIONS IN THE FIELD. DRAWINGS ARE DIAGRAMMATIC AND INDICATE

APPROXIMATE LOCATIONS OF THE APPARATUS. ANY DISCREPANCIES IN THE

FIELD SHALL BE BROUGHT TO THE ATTENTION OF THE ARCHITECT/ENGINEER

FOR CLARIFICATION.

GENERAL NOTES

1.

2.

KEYED NOTES:

NEW AHU SHALL BE CEILING MOUNTED. PROVIDE NEW CHWS&R PIPING TO CONNECT TO EXISTING PIPING AS SHOWN.

PROVIDE OFFSETS AND FITTINGS AS REQUIRED FOR CONNECTION. ROUTE AHU CD PIPING TO FLOOR DRAIN.

MOUNT COOLING TOWER ON THE EXISTING STEEL DUNNAGE WITH NEW VIBRATION ISOLATION. THE EXISTING GALVANIZED STEEL FRAME THAT IS ABOVE THE VIBRATION ISOLATORS SHALL REMAIN AND BE REUSED. CONTRACTOR TO COORDINATE SUPPORTING EQUIPMENT IN ACCORDANCE WITH COOLING TOWER MANUFACTURERS REQUIREMENTS(TYP.2).

MODEL CFM O.A.

SUPPLY FAN

HP ESP MBH

COOLING

V PH HZ

ELECTRICAL

LBS

WEIGHT

REMARKS

NO.

ITEM

AHU-1 BCHE054 1800 0 1.0 - 54 115 1 60 130 -

BASED ON TRANE

AIR HANDLING UNIT SCHEDULE

SERVICE

MECHANICAL ROOM

BASED ON MARLEY STRUCTURE AND CASING SHALL BE SS301L STAINLESS STEEL.

PROVIDE INTERNAL HEATERS ON ALL FAN MOTORS TO PREVENT INTERNAL CONDENSATION.

PROVIDE GEARBOX WITH 5 YEAR OIL CHANGE INTERVALS.

2 3

HZ

REMARKS

WB (°F)

ELECTRICAL

CFM

EWT (°F)

V PH

LWT (°F)GPMMODELNO.

ITEM FAN MOTORS

HP

EAT

CT-1&2 NC8401NAN1 95 85 78 60118 10 460 3 60

COOLING TOWER SCHEDULE

(FT)

PD

10.43

PROVIDE SINGLE WATER INLET ON ALL TOWERS.

PROVIDE EQUALIZING LINE CONNECTIONS BETWEEN CELLS.

PROVIDE VIBRATION SWITCH ON ALL TOWERS.

PROVIDE ELECTRIC WATER LEVEL CONTROL ON ALL TOWERS.7

4 5 6 7

(LBS)

WEIGHT

8,500

(KW)

BASIN HEATER

AX-36-25-0420-VG-4 IN LINE 19 115/1/60 CONTROLLED BY THERMOSTATGENERATOR ROOMEF-1 1/4900 1560.375

WEIGHT

(LBS) V/PH/HZ

BASED ON GREENHECK

SERVICE

EXHAUST FAN SCHEDULE

ITEM

NO.

MODEL TYPE ESP.

IN.

CFM HP RPM REMARKS

THREADED

SUSPENSION

RODS AS

REQUIRED(TYP.)

VIBRATION

ISOLATOR(TYP.)

STEEL CHANNEL SUPPORT

BY HVAC CONTRACTOR

(TYP.)

EXHAUST AIR DUCT

ROOF SUPPORT

STRUCTURE

FLEXIBLE

CONN.(TYP.)

INLINE FAN

EXHAUST AIR DUCT

NO SCALE

INLINE EXHAUST FAN DETAIL

BD

M

12" DEEP PLENUM

FULL SIZE OF

LOUVER

EXISTING HORIZONTAL

SUPPORT

BEAMS ±42" ON

CENTER

EXISTING METAL PANEL.

PITCH DOWN

TO LOUVER

NOTES:

FURNISH AND INSTALL AN INTAKE AIR DUCT

AS HEREINAFTER SPECIFIED. CUTTING AND

PATCHING SHALL BE BY THIS

CONTRACTOR. LOUVER IS EXISTING.

1.

2. SEQUENCE OF OPERATION: THE EXHAUST FAN

CONTROLS SHALL BE WIRED TO INTERLOCK

WITH THE CONTROL DAMPER LOCATED ON THE

INTAKE LOUVER. THE DAMPER SHALL OPEN AND

THIS WILL ALLOW THE EXHAUST FAN TO

OPERATE ON ACTIVATION OF THE

PROVING SWITCH. THE PROVING SWITCH WILL

DETERMINE IF THE DAMPER IS FULLY OPEN.

SOLDER WATER

TIGHT ALL JOINTS

MOTORIZED DAMPER

EXISTING LOUVER

NO SCALE

INTAKE DUCT INSTALLATION DETAIL

AHU NEW AIR

HANDLING

UNIT

NEW CHILLED

WATER

PIPING

3/4" PVC CONDENSATE

DRAIN TO FLOOR DRAIN

SUPPLY AIRRETURN AIR

NEW VIBRATION

ISOLATOR (TYP.)

NEW THREADED SUSPENSION

RODS AS REQUIRED (TYP.)

NEW COOLING COIL

ROOF SUPPORT

STRUCTURE

NO SCALE

AIR HANDLING SYSTEM - DETAIL

2 POSITION

CONTROL VALVE

BALL VALVE

STRAINER WITH DRAIN VALVE

1/2" MESH GALV. SCREEN1/2" MESH GALV. SCREEN

NEW 1" DRAIN VALVE

EXISTING CHWR

NO SCALE

AHU-1 CHWS&R CONNECTION DETAIL

NEW TEE

TO AHU-1

TO CHILLER

EXISTING CHWS

NEW TEE

TO AHU-1

TO CHILLER

NEW 1" CHWR NEW 1" CHWS

Professional Stamp Professional Stamp

Project Name:

MassDOT Project Number: 616454-134457

Project Location:

Project Architect

Drawn By:

Checked By:

AA Project No.:

Scale:

Original Issue Date

Revisions

Plan Name:

Drawing Number:

Project Consultant

STATE FEDERAL AID PROJECT NO. SHEET

NO.

TOTAL

SHEETS

PROJECT FILE NO.

Ten Park Plaza Suite 4160

Boston, MA 02116 857-368-4636 www.mass.gov/massdot

BOSTON

136 BLACKSTONE STREET

219 Concord Avenue Cambridge MA 02138 Tel. 617-441-8500

MA -

616454-134457

As indicated

HVAC LEGEND, NOTES,

DETAILS & SCHEDULES

M000

15 JUNE, 2026 - BID SET

COOLING TOWER

REPLACEMENT AT

HAYMARKET CENTER

136 BLACKSTONE STREET

BOSTON, MA 02109

YC

MHV

0856.35

HVAC LEGEND, NOTES, DETAILS & SCHEDULES

No. Description Date 1 Addendum #3 2026-07-30

ADDENDUM NO. 3
BOSTON
SUB-BIDS OPENED AND READ: JULY 27, 2026 @ 2:00 P.M.
GENERAL BIDS TO BE OPENED AND READ: AUGUST 5, 2026 @ 2:00 P.M.
DRAWING REVISIONS
Revised Plan Sheet M-000

File details come from the government source that posted it. Updated .