This is a Bid Tabulation and Recommendation for Contract Award document from the Michigan Department of Technology, Management & Budget (DTMB), State Facilities Administration, Design & Construction division, dated March 18, 2026. The project involves an Electrical Infrastructure Upgrade at Richard A. Handlon Correctional Facility (MTU 472) in Michigan. The bid opening occurred on May 17, 2026, at 2:00 p.m., with the bid expiration date listed as JGH. Three contractors submitted bids for Bid Package #1 under file number 24413, with bids remaining valid through the specified expiration date. The project is being managed through the DTMB State Facilities Administration office located in Lansing, Michigan.

Three qualified bidders submitted proposals for the electrical infrastructure upgrade project. Amble Electric, LLC of Lakeview, Michigan submitted the lowest base bid of $3,000,000.00, followed by Centennial Electric, LLC of Charlotte, Michigan at $4,410,000.00, and Glen Construction, LLC of Clio, Michigan at $4,607,654.00. All three bidders submitted bid bonds at 5.00% of their respective bid amounts as required. The project has adequate available funds designated for completion. A QDV (Qualified Disabled Veteran) preference was applied to the bidding process, with Amble Electric, LLC noted as qualifying for this preference and being selected for award as the low bidder.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Agency Name

3/18/2026

Bid Tabulation and Recommendation For Contract AwardDMB-412 (R 10/96)

DOC/Richard A. Handlon Correctional Facility (MTU)

Available Funds $

Bid opening date and time 5/17/2026Bid Expiration Date

JGH./ 24413File Number

Director SAB Architect

FUNDS:

Adequate

Revised W.O./M.O.P.

Addendum

Additional Funds $

RECOMMENDATION (Return to Facilities Administration)

REASON FOR PROJECT (Must be filled in)

BID SECURITY

NOT REQUIRED REQUIRED

BIDDERS BASE BIDCert. of Awardability? BID BOND

Bid Package # 1

Scope Handlon C.F. – Electrical Infrastructure Upgrade Index Number

BOND %

Matrix Consulting Engineers

, 2:00 p.m.

Qualified Dis. Veteran?

DMB-402 (RPIMS revision date: 04/08) DTMB State Facilities Administration, Design & Construction

Warehouse Complex, Building 600

P.O. Box 30026

Lansing, Michigan 48909

AWARD:BIDDER:

Low

Second

Third

Amble Electric, LLC $3,000,000.00Bond

P.O. Box 437

Lakeview, MI 48850 MI

5.00%

Centennial Electric, LLC $4,410,000.00Bond

2206 Lansing Road

Charlotte MI 48813

5.00%

Glen Construction, LLC $4,607,654.00Bond

5092 W. Vienna Road, Suite K

Clio MI 48420

5.00%Yes

Page 1 of 1472 24413/ . JGH