This document is a Request for Quotation (RFQ 25-569) for the Central Office Building Women's Restroom renovation project, involving multiple construction contractors. The project involves a single lump sum (1 LS) procurement covering materials, labor, and permitting for restroom improvements. Seven construction companies submitted competitive bids, with costs ranging from $42,000 to $71,953.76 across three primary cost categories: materials, labor, and permitting.
FSV Construction was awarded the contract at a total cost of $42,000, which was the second-lowest bid submitted. The breakdown of their proposal includes $18,000 for materials, $21,000 for labor, and $3,000 for permitting. Bid prices varied significantly among contractors, with H2D Total Construction presenting the highest total cost at $65,400 and Dorothy Builds offering the lowest alternative bid at $48,176. The competitive bidding process demonstrates a range of pricing strategies and cost structures among local construction firms for this specific restroom renovation project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ_25-569_Addendum_3.pdf | ||
| RFQ_25-569_Addendum_2.pdf | ||
| Sign-In_Sheet_7-22-25.pdf | ||
| RFQ_25-569_Addendum_1.pdf | ||
| RFQ_25-569_Central_Office_Building_Women's_Restroom.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ 25-569 Central Office Building Women's Restroom Quantity
H2D Total Construction
Falcon Design& Construction
Jim's Complete Construction FSV Construction
DPS Professional Services
Materials 1 LS $34,000.00 $34,705.44 $17,535.00 $18,000.00 $20,738.00
Labor 1 LS $30,400.00 $35,716.89 $32,070.00 $21,000.00 $23,501.00
Permitting 1 LS $1,000.00 $1,531.43 $3,000.00 $3,000.00 $650.00
Total Cost $65,400.00 $71,953.76 $52,605.00 $42,000.00 $44,889.00
Awarded
Dorothy Builds
Alberto Flores dba Ovation Construction
J.C Stanford & Sons AG Pifer
Materials 1 LS $22,400.00 $17,600.00 $32,703.77 $23,700.00
Labor 1 LS $24,276.00 $46,000.00 $22,299.50 $23,700.00
Permitting 1 LS $1,500.00 $6,000.00 $4,500.00 $2,500.00
Total Cost $48,176.00 $69,600.00 $59,503.27 $49,900.00