The document provided is a Price Schedule Template for a federal contract opportunity related to the replacement of the East Lift Station at the Fort Pickens area of the Gulf Islands National Seashore in Escambia County, Florida.
The solicitation number is 140P5224B0001, and the project is titled "REPLACE FORT PICKENS EAST LIFT STATION". The work consists of demolishing the existing lift station, 50-KW diesel generator, pump control panel, and automatic transfer switch, and installing a new lift station with a fiberglass wet well and 15 HP pump, an 80-KW propane generator with 250-gallon propane tanks, a pump control panel, and a 200-amp, 240 volt, 3-pole service rated automatic transfer switch. The estimated price range for the project is between $500,000 and $1,000,000. Bid items include Site Preparation, Site Improvements, Site Mechanical Utilities, and Site Electrical Utilities. A site visit is scheduled for May 29, 2024, and the cut-off for inquiries or RFIs is June 10, 2024. The solicitation is issued as an Invitation for Bids (IFB) under FAR Part 14 - Sealed Bidding and FAR Part 36 - Construction Contracts procedures. A bid bond is required, and the contract will be awarded to the responsible bidder whose bid is most advantageous to the government, considering only price and price-related factors.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFI__1_-_9_CLARIFICATIONS_0003.zip | ZIP file | |
| Site_Visit_Sign-In_Sheet_0003.pdf | ||
| Sol_140P5224B0001_Amd_0003.pdf | ||
| C4_SHEET_5_OF_11_REVISION_FP-2024-EAST-Lift_Station_Revised_Site_Plan_0003.pdf | ||
| Sol_140P5224B0001_Amd_0002.pdf | ||
| Sol_140P5224B0001_Amd_0001.pdf | ||
| Site_Visit_Agenda.pdf | ||
| Engineer_s_Estimated_Quantity.pdf | ||
| Atch_4_-_BID_BOND__SF24-16e.pdf | ||
| ReadThisFirst.pdf | ||
| Atch_3_-_WAGE_DETERMINATION_FL20240112.pdf | ||
| B08_Atch_2_-_SPECS_-FP-East_LS-FINAL_Contract_Documents.pdf | ||
| Sol_140P5224B0001.pdf | ||
| Atch_1_-_PLANS_DWG__635_192070_Final_Construction_Documents.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price Schedule Template
| Contract Price Schedule | |||||
| National Park Service (NPS) - Denver Service Center (DSC) | 3-13-18 | |||||
| Solicitation Number: | 140P5224B0001 | ||||
| PARK - PMIS: | GUIS 303760 | ||||
| (Project Management Information System) | |||||
| Developed Area: | FORT PICKENS AREA - RANGER STATION/CMPG REGISTRATION OFFICE | ||||
| Project Title: | REPLACE EAST LIFT STATION | ||||
| Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents. Enter pricing for all line items. | |||||
| Failure to do so may render the offer unacceptable. On lump-sum line items, provide the total price only. For all unit-priced | |||||
| line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related | |||||
| item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts | |||||
| govern. Round totals and extended prices to whole dollars. | |||||
| Contract Line Item Number (CLIN) | Contract Line Item (CLI) Title | Quantity | Unit of Measure | Unit Price | Total Price |
| 1A | G10 Site Preparation | 1 | LUMP SUM | $0.00 | |
| 1B | G20 Site Improvements | 1 | LUMP SUM | $0.00 | |
| 1C | G30 Site Mechanical Utilities | 1 | LUMP SUM | $0.00 | |
| 1D | G40 Site Electrical Utilities | 1 | LUMP SUM | $0.00 | |
| TOTAL BASE PRICE (Contract Line Item Number 1A through 1D) --------------------------------------------------------------------------------- | $0.00 |
Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump-sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.