The provided document is a Site Plan for the replacement of the East Lift Station at the Gulf Islands National Seashore in Escambia County, Florida. The key details are:
The project consists of demolishing the existing lift station, 50-KW diesel generator, pump control panel, and 200-amp, 240 volt, 3-pole automatic transfer switch. A new lift station with a fiberglass wet well and 15 horsepower pump, an 80-KW propane generator with 250-gallon propane tanks, a pump control panel, and a 200-amp, 240 volt, 3-pole service rated automatic transfer switch will be installed. The bid items include Site Preparation, Site Improvements, Site Mechanical Utilities, and Site Electrical Utilities. The estimated price range for this Firm Fixed Price construction contract is between $500,000 and $1,000,000. An organized site visit is scheduled for May 29, 2024, and the solicitation is being issued as an Invitation for Bids under FAR Part 14 - Sealed Bidding. Bids must include a bid bond, and the contract will be awarded to the responsible bidder whose bid is most advantageous to the Government, considering only price and price-related factors.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROPOSED 6' DIAMETER FIBERGLASS WETWELL
CONTRACTOR TO PROVIDE CONNECTIONS TO
EXISTING UTILITIES INCLUDING TWO (2) GRAVITY
CONNECTIONS AND TWO (2) PRESSURE PIPE
CONNECTIONS
NEW 12'x18' CONCRETE
PAD
SEE SHEET C6 FOR LIFT
STATION LAYOUT FOR
APPROXIMATE PIPED
CONNECTIONS
o o o o o o o o o o o o o o o o o o o o o o o o ooooooooooo
NEW 10' WIDE GRAVEL
ACCESS ROAD
oo o o
NEW 12' WIDE CHAIN
LINK GATE
NEW CONTROL PANEL
TO BE PLACED ON
EXISTING CONCRETE
PAD
NEW 80 KW
GENERATOR TO BE
PLACED ON EXISTING
CONCRETE PAD
NEW CHAIN LINK FENCE
NEW 1'x1' CONCRETE
PAD WITH POTABLE
WATER HOSE BIB
CONNECTING LINES SHOWN FOR REFERENCE.
CONTRACTOR TO FIELD LOCATE GRAVITY AND
PRESSURE PIPES TO DETERMINE CONNECTION
POINTS TO NEW WET WELL.
NEW CONCRETE PAD
FOR 250 GALLON
GENERATOR FUEL
STORAGE TANK
SCALE ASCALE A
SITE PLAN
C4
SCALE OF FEET
NOTES
1. 4" PF FLORIDA DEPARTMENT OF TRANSPORTATION (FDOT) #57 STONE, 60 MIL
GEOFABRIC WEED CONTROL LINER UNDER STONE PLACED AT ALL NON-PAVED
AREAS WITHIN CHAIN LINK FENCE
2. SEE SHEETS C5 & C6 FOR LIFT STATION PLAN AND SECTION DETAILS.
3. SEE ELECTRICAL PLANS FOR ELECTRICAL CONNECTIONS
4. CONTRACTOR SHALL BRING IN SAND FILL AS REQUIRED TO MATCH ORIGINAL
GRADE.
5. CONTRACTOR TO PROVIDE TEMPORARY PUMPING OF SANITARY SEWER TO MAINTAIN
OPERATIONS THROUGHOUT CONSTRUCTION. TEMPORARY PUMPING SHALL BE
SUBMITTED AND APPROVED BY THE CONTRACTING OFFICE PRIOR TO USE.
6. APPROXIMATELY 60' IN 1" PVC MAY BE NEEDED FOR WATER LINE EXTENSION.
DATE:
DESIGNED:
TECH. REVIEW:
SUB SHEET NO.
PMIS/PKG NO.
DRAWING NO.
SHEET
OF
TITLE OF PROJECT
TITLE OF SHEET
A/E FIRM
CROFT &
ASSOCIATES
KENNESAW,
GEORGIA
01/09/2024
Jim Downey
Ken Bates
Lee Hale
303760
XXXXXX
XX
GULF ISLAND NATIONAL SEASHORE
SITE PLAN
REPLACE EAST LIFT STATION
C4
10505
32'-8"
18'-0"
12'-0"
40'-0"
35'-0"