BID_FORM-_Reroofing_City_Schools_Phase_1_-_Mitchell-Neilson_and_Reeves-Rogers.pdf
PDF 55 KB Posted
- Solicitation number
- ITB-21-2022
- Issued by
- Rutherford County, Tennessee
About this file
This is a Bid Form for a reroofing project for Murfreesboro City Schools, specifically Phase 1, involving four elementary schools and issued by Johnson + Bailey Architects. The project requires a contractor to complete reroofing work within sixty (60) consecutive calendar days after receiving the Notice to Proceed, with liquidated damages of $300 per calendar day for delays beyond the established completion date. The bid documents outline requirements for executing the contract, including submitting a Standard Form of Agreement, Performance Bond, Insurance Certificate, List of Subcontractors, Schedule of Values, and Builders Risk Insurance.
The bid includes unit price proposals for specific additional work, such as replacing damaged wood roof edge nailers and removing deteriorated gypsum roof deck at Mitchell-Neilson Elementary School and replacing it with metal deck. The bidder must submit a Drug Free Workplace Affidavit, and certify they are not on the state's Iran Divestment Act list. The bid remains valid for forty-five (45) days, during which the contractor must be prepared to execute the agreement if selected. The project is located in Murfreesboro, Tennessee, and is identified by the project number J+B No. 2105-P1, with the bid documents dated December 3, 2021.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| MCS_Reroofing.Phase_1.Specs-12.3.21.pdf | ||
| MCS_Reroofing.Phase_1.Drawings-12.3.21.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID FORM
Reroofing at Four Elementary Schools
Murfreesboro City Schools
Phase 1
J+B No. 2105-P1
DATE SUBMITTED: CONTRACTOR:
TO: City of Murfreesboro 111 West Vine Street Murfreesboro, Tennessee 37130
Gentlemen:
The undersigned, as Bidder, hereby declares that the only person, or persons interested in this Proposal as principal, or principals, is or are named herein and that this Proposal is in all respects fair and in good faith without collusion or fraud.
The Bidder further declares that he has examined the site of the Work and informed himself fully in regard to all conditions thereon and has examined the Drawings, Specifications, and Contractual Documents for the Work and has satisfied himself relative to the Work to be performed.
Time being of the essence, the Bidder proposes and agrees to commence work with an adequate force and equipment on a date to be specified in a written Order of the Architect, and to complete all work within Sixty
(60) consecutive calendar days after Notice to Proceed.
It is understood that the Notice to Proceed with construction will not be issued until the following documents have been delivered to the Owner through the Architect for review and execution:
- Contractor executed Standard Form of Agreement Between Owner and Contractor, AIA Document, A101, 2007 Edition.
- Performance Bond, Material and Labor Payment Bond.
- Insurance Certificate
- List of Subcontractors
- Schedule of Values
- Builders Risk Insurance (purchased for Owner by Contractor)
Whereas the Owner will suffer loss of use if the project is not complete on or before Sixty (60) consecutive calendar days after Notice to Proceed is issued, the Contractor and his Surety shall be liable for and shall pay to the Owner the sum of Three Hundred Dollars ($300.00) as fixed and agreed liquidated damages for each calendar day of delay (in excess of the Contract Completion Date established herein) until the work is substantially complete as defined in AIA Document A201, Subparagraph 9.8.1. Architect shall issue a Certificate of Substantial Completion (AIA Document G704) to verify date work is substantially complete.
The Bidder further agrees that he will not withdraw this Proposal within a period of forty-five (45) consecutive calendar days from and including the date of this Proposal and that, if this Proposal is accepted, he will execute a Contract within said forty-five (45) day period and within five (5) consecutive calendar days after date of written notice of such acceptance. In case of failure on the Bidder's part to perform as agreed above, the monies payable on the Bid Bond accompanying this Proposal shall be paid into the funds of the Owner as liquidated damages for such failure; otherwise, the Bid Bond shall be returned to the Bidder.
The Bidder further proposes and agrees to contract with the Owner on the AIA Standard Form of Agreement between Owner and Contractor for a Lump Sum to furnish for the following sum all necessary materials, equipment, tools, apparatus, means of transportation and labor necessary to complete the construction of the Project in complete accordance with the shown, noted, described, and reasonable intended requirements of Drawings, Specifications, and Contract Documents with the definite understanding that no money will be allowed for extra work except as set forth in the Contractual Documents.
December 3, 2021 © 2021 JOHNSON + BAILEY ARCHITECTS P.C. 2105-P1
The Bidder further agrees that he and each subcontractor employing no less than five (5) employees will execute and submit to the Owner the attached DRUG FREE WORKPLACE AFFIDAVIT. No Contractor or Subcontractor may perform work on this project unless this form is fully executed and submitted prior to the start of the project. The General Contractor shall submit a fully executed, notarized copy of this form with this bid.
By submission of this bid, each bidder and each person signing on behalf of any bidder certifies, and in the case of a joint bid each party thereto certifies as to its own organization, under penalty of perjury, that to the best of its knowledge and belief that each bidder is not on the list created pursuant to T.C.A. §12-12-106 (The Iran Divestment Act - July).
BID DOLLARS
UNIT PRICE PROPOSALS
The following unit price Proposals shall be utilized to compute additional compensation due the Contractor for additional work. Refer to Section 01 22 00 - UNIT PRICES, for definitions. Refer to Section 01 21 29, QUANTITY ALLOWANCES, for quantities to be included in base bid.
1. DOLLARS PER BOARD FOOT ($ ).
For removal of damaged existing wood roof edge nailers, and replacement with new wood nailers.
2. DOLLARS PER BOARD FOOT ($ ).
For removal of deteriorated existing gypsum roof deck at Mitchell-Neilson Elementary School, and replacement with new metal deck as shown on Detail 2/A4.3 and Detail 3/S1.0.
The undersigned states that he has received and taken into consideration
Addenda No. Dated
Addenda No. Dated
Addenda No. Dated
EXECUTION OF AGREEMENT:
The undersigned agrees that if written notice of acceptance of this proposal is mailed, telegraphed, or delivered to him within forty-five (45) days after opening of proposals, he will promptly execute an Agreement with the
Owner in accordance with the Bid Documents.
COMPANY: DATE:
BY: TITLE:
December 3, 2021 © 2021 JOHNSON + BAILEY ARCHITECTS P.C. 2105-P1