This document is a comprehensive bid specification for the Timberlin Golf Course Sand Bunker Restoration Project located in Berlin, Connecticut, prepared by Golf Design Unlimited, LLC. The project involves a complete renovation of sand bunkers across all 18 holes of the golf course, with two potential scenarios: Scenario A encompasses rebuilding all 51 sand bunkers, and Scenario B focuses on the 30 greenside sand bunkers. The project is scheduled to commence in the Fall of 2025 and must be completed before Memorial Day 2026, with a specific construction timeline requiring work to begin within 7-10 days of the "Notice to Proceed" and be completed within 35 days of starting. The scope includes removing existing sand, installing new drainage, adding capillary concrete liner, reconstructing bunker edges, and reinstalling sand and sod.

The bid specifications outline detailed requirements for materials, construction methods, and contractor qualifications. The contractor must have a minimum of five years of golf course construction experience and must have completed at least 30 sand bunker renovations in the past three years. Materials include specific specifications for drainage pipes, gravel, sod, and bunker sand sourced from Dunning Industries Sand & Gravel. The project will be paid upon completion, with unit pricing for various components such as sod installation, drainage, sand placement, and irrigation head relocation. The bid includes add/alternate options for additional drainage and fairway sod installation, with the owner reserving the right to accept or reject any part of the bid. Pricing will be determined through a detailed bid sheet that itemizes quantities and unit prices for each project component.

View the file

Other files

File Type Posted
Timberlin_Golf_Course_Sand_Bunker_Restoration_Project.pdf PDF
Bid_Form.pdf PDF
Prevailing_Wage_Rates_(Heavy).pdf PDF
Installation_Instructions.pdf PDF
2025-24_Drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Timberlin GC Specifications

Golf Design Unlimited, LLC Page 1

TIMBERLIN GOLF COURSE

Town of Berlin, Connecticut

Site Location: 330 Southington Road. Berlin, CT 06037

Golf Course Drawings, Specifications, Bid Form & Details

SAND BUNKER RESTORATION PROJECT

Prepared by Golf Design Unlimited, LLC

BID # 2025-24

Table of Contents

COVER SHEET

GENERAL REQUIREMENTS AND COVENANTS .............................................................................. 2-3

CONSTRUCTION DRAWINGS .............................................................................................................. 4-21

Item 100 – SILT FENCE

Item 200 – SAND BUNKER CONSTRUCTION ................................................................................... 23-25

Item 300 – SODDING

Item 400 – DRAINAGE ............................................................................................................................ 27-30

Item 500 – LOAD, HAUL & PLACE FILL

Item 600 – EXTRA SHAPING

Item 700 – SAND BUNKER IRRIGATION .......................................................................................... 33-35

Golf Design Unlimited, LLC Page 2

BID FORMS & QUALIFICATIONS ................................................................................................... 36-38

DETAILS ................................................................................................................................................ 39-55

GENERAL REQUIREMENTS AND COVENANTS

1. Definitions

1.1. Wherever "G.C.A." (Golf Course Architect) appears herein, it shall refer to the firm of Golf Design Unlimited, LLC and their authorized representative: Douglas

Smith, ASGCA.

1.2. Wherever "G.C.S." (Golf Course Superintendent – Jerry Salvio) appears herein, it shall refer to the person working in that capacity for Timberlin GC, or its authorized representative(s).

1.3. Wherever "Owner" appears herein, it shall refer to Timberlin GC, and its authorized representative(s) including Mr. Sol Guererro.

1.4. Wherever " Contractor" appears herein, it shall refer to the contractor who is performing the work.

1.5. The term "Plans" refers to all construction drawings within this document and field design sketches and details that the G.C.A. will do during construction, and details authorized by the Owner and pertaining to the work as prepared by the

G.C.A.

1.6. The term "Site" refers to the grounds upon which the work is being constructed.

2. Contractor's and Owners Responsibilities.

2.1. Material - The Contractor shall supply all material needed to rebuild, eliminate or make new sand bunkers. Any drainage material (pipe, sumps, catch basins, stone etc.) All stockpile areas are subject to the approval of the G.C.S. and the Owner.

Supplemental topsoil will be supplied by the owner too.

2.2. The G.C.S. shall provide the Contractor with all known and updated information about the existing irrigation system and where all pipes and heads are located.

2.3. The Owner shall indicate to the Contractor all haul roads and locations for storing any material and/or equipment. Storage for materials will likely be in the

Clubhouse parking lot region. Any damage from an existing haul road by the

Contractor shall be repaired by the Contractor at his own expense. Any new haul roads shall be removed and the area repaired to the state it originally was in. All haul road repairs are at the Contractor’s own expense and subject to the approval of the G.C.A. and the G.C.S.. Locations for haul roads will be clearly stated by

Golf Design Unlimited, LLC Page 3

Gillette Ridge/Cigna at the outset. Please note #5 green and entirety of hole #6 need to be clearly marked for ingress and egress for equipment.

2.4. The Contractor shall be responsible to use proper surveying equipment to check that all drainage installation is pitched at the proper slope and correct invert elevations.

2.5. The Contractor shall provide and have on hand wooden stakes, metal marking flags, white and red fluorescent paint and a paint gun for the G.C.A.'s use during the project.

2.6. The Contractor shall keep in close contact with the G.C.A. and give him a minimum of 48 hours notice when the Architect's services are required for approval as dictated by the Specifications.

2.7. All work shall be included in the items whether mentioned or not mentioned in the specifications.

3. Summary of Project

3.1. Qualifications - for the project the Contractor must meet: The Contractor shall have golf course experience with a minimum of five years. The supervisor for this project must have the same experience.

3.2. This project involves the renovation of sand bunkers on all eighteen holes. There will be a total of fifty-one (51) sand bunkers rebuilt or new. Thirty (30) of the 51 are greenside sand bunkers. Ten sand bunkers will be eliminated and one sand bunker will be made into two as well as two sand bunkers on one hole will be made into one. Most sand bunkers are being restored at their present locations.

Some sand bunkers are being shifted and/or enlarged and will require the Hunter

I-80 heads to be re-used and adjusted. Some sand bunkers will need fill hauled and placed as they are being made smaller in size. Additional drainage is indicated on certain holes (example #8 & #11). There is an add/alternate for additional drainage and fairway sod at the discretion of Timberlin GC and will be authorized only in writing if deemed necessary.

At each existing sand bunker sod will be stripped then sand, bunker blankets (if found) and existing internal drainage will be removed. Sand bunkers will be rebuilt completely with new internal 4” drainage being replaced and capillary concrete will be installed as the new base. The sand bunker designs are meant to work around all existing irrigation. All damage to irrigation equipment is the responsibility of the Contractor to fix. The average size sand bunker will be 1,050 s.f. with 70 l.f. of perforated pipe and two (2) catch basins included in the bunker price along with the capillary concrete and the installation of the sand.

Golf Design Unlimited, LLC Page 4

3.3. The Contractor shall provide all material for the project except the bunker sand, fill and additional topsoil.

3.4. Payment is in full after completion of job. All labor and materials will be at contractor’s expense except the bunker sand – no upfront payments at start of job.

This project is not prevailing wage.

4. Construction Schedule

4.1. This project (SCENARIO A) will be hopefully be substantially completed in one season and will comprise all the sand bunkers. It may possibly be just the greenside sand bunkers depending on available funding (SCENARIO B). The project (EITHER SCENARIO) is to commence in the Fall of 2025 and be completed before Memorial Day 2026.

4.2. The Contractor must start work within seven to ten days of “Notice to Proceed” and complete work within 35 days after start. A construction start date (weather permitting) is October 1, 2025.

Golf Design Unlimited, LLC Page 5

Golf Design Unlimited, LLC Page 6

Golf Design Unlimited, LLC Page 7

Golf Design Unlimited, LLC Page 8

Golf Design Unlimited, LLC Page 9

Golf Design Unlimited, LLC Page 10

Golf Design Unlimited, LLC Page 11

Golf Design Unlimited, LLC Page 12

Timberlin 8 Pro

Final

Golf Design Unlimited, LLC Page 13

Golf Design Unlimited, LLC Page 14

Golf Design Unlimited, LLC Page 15

Golf Design Unlimited, LLC Page 16

Golf Design Unlimited, LLC Page 17

Golf Design Unlimited, LLC Page 18

Golf Design Unlimited, LLC Page 19

Golf Design Unlimited, LLC Page 20

Golf Design Unlimited, LLC Page 21

Golf Design Unlimited, LLC Page 22

Golf Design Unlimited, LLC Page 23

TECHNICAL SPECIFICATIONS

Item 100 - SILT FENCE

DESCRIPTION. The work under this Item consists of the Contractor installing and maintaining silt fence around necessary construction areas as directed in the field by the

G.C.A. The work also includes the removal of the silt fence by the Contractor after the construction areas are stabilized. Please note that the G.C.A. might direct the Contractor to install some additional silt fence not for its purpose of stopping erosion runoff but to fence out an area from golfers.

0. MATERIAL. All material under this Item shall be supplied by the Contractor.

0.1. Silt Fence. Silt fence shall be a woven polypropylene fabric resistant to soil chemicals, mildew, insects and exposure to sunlight. The fabric shall have the following minimum values:

Minimum

Property Test Method Avg. Value

Tensile strength (lbs) ASTM-D-1682 200 WARP

Elongation (%) ASTM-D-1682 2

Burst Strength (psi) Mullen Burst Test 300

Retention Efficiency (%) VTM-51-79 75

Equivalent Opening Size U.S. Sieve No. Equiv. 30/ 50

0.2. Stakes. Shall be either wood or steel as recommended by the silt fence manufacturer.

1. CONSTRUCTION OPERATIONS.

1.1. Installation. Silt fence shall be installed and maintained around all locations as indicated on the Plans and/or as deemed necessary by the G.C.A. Silt fence shall be installed according to the detail and to the manufacturer's recommendations.

1.2. Removal. The Contractor shall remove silt fence upon approval of the Architect and/or the Owner.

2. CLEAN-UP AND APPROVAL. All work, methods of construction and clean-up shall be subject to the approval of the G.C.A.

3. PAYMENT. The Contractor shall be paid by his bid unit price per linear foot and it includes the installation, maintenance, removal of the silt fence and any turf restoration as necessary.

Golf Design Unlimited, LLC Page 24

END OF ITEM 100

ITEM 200 - SAND BUNKER CONSTRUCTION & SAND BUNKER REMOVAL

DESCRIPTION. The work under this Item consists of the contractor and his shaper rebuilding the majority of the sand bunkers and removing some.

The work for rebuilding the sand bunkers includes: removing old bunker sand and stockpiling it at a designated location, removing existing sod around bunker, removing and disposing of the bunker blankets if they are there, the rebuilding of the bunkers at their present locations except in a few cases (hole #16 for example), including placing both 6” “venting” catch basins outside of the bunker, installing capillary concrete base, spreading minimal topsoil around bunker if necessary, supply, hauling and placing sand in bunker (see item 500.1), and spreading and vibratory tamping sand in bunker, and supplying and placing sod around the bunkers (see item 300). Please note most existing drainage basins outside of each sand bunker are working and many of the newly rebuilt bunkers will tie into them. Some will terminate into proposed gravel sumps. Some sand bunkers will be enlarged or shifted and the Hunter I-80 heads will need to be re-used and replaced(Item 700).

1. MATERIAL. All material shall be supplied by the Golf Contractor.

1.1. Fill. All fill necessary for the project will be obtained by the contractor. See item 500.

1.2. Topsoil. Topsoil shall either be topsoil from the site or alternate topsoil supplied by the Owner. The intent of this project is that the native, existing topsoil shall be enough for the projects needs. A minimum of 2-3 cubic yards should be expected per sand bunker as supplemental topsoil.

1.3. Bunker Sand. It is to be “Native Sand” from Dunning Industries Sand & Gravel (105

Brickyard Rd. Farmington, CT) Contact: 860-677-1616

1.4. Capillary Concrete Liner – This item is further detailed in the construction details.

The subgrade must be prepared properly before installation – all bunker drains must work properly and the subgrade be positively pitched, stable under foot, smooth, compacted and free of debris. Sodding around the perimeter should take place prior to installation and be secured. Once poured and properly spread to the consistent 2” depth it must be covered and cured for 24 hours before placing the sand and creating the sand/sod perimeter edge

1.5. Sod. Turf Type Tall Fescue Sod

2. QUALITY ASSURANCE.

2.1. The Shaper shall rough grade and final grade all bunkers to the complete satisfaction of the G.C.A. This grading includes any modifications deemed necessary by the

G.C.A. for drainage and/or aesthetic reasons. The location, size, and shape of each bunker shall be as directed in the field by the G.C.A. and not just based on the

Construction Drawings.

2.2. Should any topographical or geological feature mandate modifications to the location, size, and/or shape of the bunker, the Shaper and Contractor shall comply with these modifications and should not expect any extra payment due to these changes. The Shaper and Contractor should expect minor modifications to take place.

3. CONSTRUCTION OPERATIONS.

3.1. Removing Existing Sod: A minimum two strips of sod per sand bunker will be removed and discarded.

3.2. Removing Bunker Sand: Sand shall be removed from bunkers and be hauled to a designated location on site – Town of Berlin Dump Site.

3.3. Removing Bunker Blanket: All material to be removed and discarded if deemed necessary

3.4. Re-Edging / Shaping:

3.4.1. Using paint and a spray-gun supplied by the Contractor, the G.C.A. shall spray the outline of the existing sand bunker to be re-edged/re-shaped.

3.4.2. The G.C.A. shall provide a sketch of the sand bunker and the proposed sand line inside the bunker.

3.4.3. The Shaper shall re-edge/re-shape the sand bunker according to the sketch of the G.C.A.

3.4.4. The Shaper shall then get approval of the rough grade of the sand bunker by the G.C.A.

3.5. 6” Grates Outside Bunker. The new two drain line riser caps (6”) outside the bunker will be located at either end of the bunker to flush the 4” pipe and provide necessary air into the lines. The Contractor will ensure the opening into the catch basin is covered until final grade is established.

3.6. Edging Bunker – this work consists of the Contractor removing six (6”) inches of material with a hand spade along the G.C.A.’s spray line.

3.7. Finish Work Inside Sand Bunker. - Before any sand is placed inside the bunker, the

Contractor shall ensure the bottom of the bunker is smooth and allows for proper drainage.

3.8. Topsoil Replacement. The Contractor shall place and compact topsoil around the bunker to ensure a compacted depth of six inches (6"). The Shaper shall final grade the topsoil surrounding the bunker construction.

3.9. Sodding. To take place before the capillary concrete is installed. The sod will be pulled back (rolled back) along the edges to allow for the capillary concrete edges to be placed and ultimately overlap the capillary concrete by approximately 4” then the sand placed on the 4” overlap. See Item 300.

3.10. Capillary Concrete Liner. This item is further explained in the construction details.

The subgrade must be prepared properly before installation – all bunker drains must work properly and the subgrade positively pitched, stable under foot, smooth, compacted and free of debris. Sodding around the perimeter should take place prior to installation and be secured except for the edge (perimeter) of the sand bunker.

Once poured and properly spread to the consistent 2” depth it must be covered and cured for 24 hours before re-placing sod edges (overlap) and sand.

3.11. Sand Placement. The Contractor shall take great care in hauling sand so as not to damage the underground drain-pipe and/or capillary concrete. The Contractor shall place the sand in the bunkers in sufficient quantity to cover the interior of each bunker to a settled depth of four (4) inches.

3.12. Spreading and Tamping Sand. The Contractor shall spread the sand and vibratory tamp the sand to a uniform depth of four inches (4"). The Contractor may be required to remove or add sand in order to achieve this required depth. When the sand is shoveled down the Contractor must be vibratory tamping the sand at the exact same time.

4. CLEANUP AND APPROVAL. All work methods of construction and clean-up shall be subject to the approval of the G.C.A.

5. BASIS OF PAYMENT SUMMARY.

200.1 Rebuild/New Sand Bunker - paid per bunker

200.2 Remove Sand Bunker – paid per removed bunker

Item 300 – SODDING

1. DESCRIPTION. The Golf Contractor shall strip and/or haul away the turf from areas before the Shaper starts his work, the Golf Contractor shall prepare the ground surface, apply fertilizers and any necessary additives to all areas (around sand bunkers) being sodded, and lay sod and rolling it as indicated and directed in the field by the G.C.A. and/or the G.C.S.

2. EQUIPMENT:

2.1. Sand-Pro, or an approved equal, shall be required to fertilize all surfaces.

2.2. "Cyclone" rotary spreader, or approved equal.

3. MATERIALS. The Golf Contractor shall supply all sod and fertilizer.

3.1. Fertilizers. A starter fertilizer with a ratio of 19-26-5 or an approved starter fertilizer.

3.2. Sod:

3.2.1. Rough Sod. All rough sod shall be a turf type tall fescue sod from East Coast

Sod or approved equal, mowed at no more than two (2") inches and shall be approved by the G.C.A. and G.C.S. It should be cut and delivered within twenty-four (24) hours. It shall be free from noxious weeds and grasses. It shall a soil layer no less than one-half inch (1/2") and no more than three-quarters of an inch (3/4") in thickness, shall have enough moisture to allow for proper rolling and handling. It is assumed the sod shall be cut eighteen inches (18") wide and be rolled in six foot (6') lengths. Any variation of this standard roll must be approved by the G.C.A. or G.C.S. prior to delivery of the sod to the site.

3.2.2. Plywood. All plywood shall be good quality plywood a minimum of 1/2" thick and shall be free of warping or tearing.

4. CONSTRUCTION OPERATIONS. Fertilizing, laying & rolling sod:

4.1. Fertilizing. The areas to be sodded will be fertilized with starter fertilizer at the manufacturer's recommended rate. The fertilizer shall be applied using a "cyclone" type spreader unless otherwise directed by the G.C.A. and/ or the G.C.S. The fertilizer shall be hand raked into the top three inches (3") of the soil. Tees or greens that are sodded are to be fertilized according to the directions in their appropriate

Items. All tee surfaces shall only be prepared for seed or sod with the use of a sand -pro or approved equal there shall be no hand raking of the final grade.

4.2. Sodding around Sand Bunkers. The Golf Contractor shall ensure that the sod is laid at a sharp 90-degree angle into the sand bunker (where the wood-edging would have gone) according to the Detail.

4.3. Watering. All sodded areas shall be lightly irrigated after completion of placement of sod by the Golf Contractor then rolled (note this is to be the same day).

5. CLEANUP AND APPROVAL. All work, methods of construction and clean-up shall be subject to the approval of the G.C.A.

6. BASIS OF PAYMENT. Unit bid price per square foot of sod as indicated below. Includes supplying sod, preparing soil bed, installing sod and rolling.

300.1 Turf Type Tall Fescue Sod - for rough – paid per s.f.

300.2 Bentgrass Sod for Fairways – paid per s.f.

Item 400 - DRAINAGE

1. DESCRIPTION. Under this Item, the Golf Contractor shall perform all operations necessary for installing drainage pipe outside the sand bunkers with both perforated and non-perforated drain pipe as indicated in the plans or as directed by the G.C.S. in the field. Note all drainage pipe is to be smooth wall interior. All catch basins will be made by the Contractor using either smooth wall interior pipe (see detail). All drain lines and catch basins shall have wire in them to help locate them in the future.

2. QUALITY ASSURANCE. The Contractor shall supply and use surveying equipment to verify the pipe has proper fall before beginning any backfill operations. The Contractor shall ensure that the minimum slope (1/ 2%) is consistent throughout the drainage system and that no backups occur. The Contractor shall be responsible to repair any malfunctioning drainage.

3. MATERIALS. All material used in this work shall be supplied by the Golf Contractor and approved by the G.C.S.

3.1. Fill. All fill necessary for the project will be obtained from areas on the site.

3.2. Additional Topsoil. If required, shall be obtained and hauled to needed areas at the Contractor's expense.

3.3. Pea Gravel. Gravel for all drainage trenches with perforated drain-pipe shall be 1/4" to 1/2" stone, washed, clean, free of soil and debris, and approved by the G.C.A.

3.4. Sump with Gravel. Gravel for 4’ x 4’ x 4’ sumps shall be an angular washed stone 3/4", clean, free of soil and debris, and must be approved by the G.C.A.

or Engineer.

3.5. Perforated Drainage Pipe and Tees. Drainage pipe shall be four inch (4"), rigid, smooth wall internal plastic pipe (N-12), as manufactured by Advanced Drainage Systems, Inc., or an approved equal

3.6. Non-perforated Drainage Pipe and Tees. Drainage pipe shall be four (4"), non-perforated, rigid, smooth wall internal plastic pipe (N-12), as manufactured by ADS Inc., or an approved equal.

3.7. Wire. 14-gauge tracer wire will be placed in all drainage trenches and attached to the top of all drain lines, vents, and catch basins so that drainage can be easily located with a metal detector.

3.8. Catch Basins. The Golf Contractor shall make all the catch basins using N-12 smooth wall interior pipe. There shall be two sizes the smaller one shall be made of 8" smooth wall interior pipe (N-12) with a Ten inch (10"), plastic grate.

The larger catch basins shall made of 12" N-12 pipe with an 12"grate. All grates shall be green or black in color. Please note that the grate shall fit onto the N- 12 pipe snuggly.

3.9. Grates - Twelve inch (12") grates shall be heavy duty green plastic manufactured by Polylok, and manufactured to easily but snugly on top of N-12 pipe, or approved equal. These grates are not part of the two “venting” grates required at every sand bunker.

3.10. Pest Control Gates. Pest control devices to be installed at the end of drain lines at ponds or ditches shall be the appropriate size for the drain pipe and shall be "Rat Guards" as manufactured by Agri Drain Corporation of Adair, Iowa, or an approved equal.

Golf Design Unlimited, LLC Page 31

4. CONSTRUCTION OPERATIONS:

4.1. Excavation. The trenches for all new drain-pipe installation shall be the required depth and minimum width necessary for proper installation.

The minimum fall shall be one- half percent (0.5%) and shall be verified by the Contractor with proper surveying equipment.

4.2. Perforated Drainage Installation. The perforated drain pipe shall be installed beneath the subgrade as indicated on the details and/ or as indicated in the field by the G.C.S. according to the detail and in the accordance with the manufacturer's recommendations, and in accordance with ASTM D 2321.

4.2.1. The pea gravel shall be placed in the trench to a minimum of depth of two inches (2") before the drain pipe is installed

4.2.2. The drain-pipe shall have a uniform slope of no less than 0.5%.

4.2.3. All pipe shall be vented with 12" catch basins with necessary risers wherever drainage lines meet, at all areas as indicated on the Plans, and/or as directed by the G.C.A. or Engineer. The Golf Contractor shall install catch basins a minimum of 150 feet apart on long runs of pipe.

4.2.4. Catch basins and their grates shall be set flush with the finished grade after seeding or sodding. If required, the Golf Contractor shall grade as much as 10 feet around the catch basin to ensure a natural appearance to the installation.

4.2.5. All drain lines shall be lined with 14-gauge wire so as to be located with a metal detector.

4.2.6. Once the drain-pipe is in place, pea gravel will be placed a minimum of 6" from the final grade. Backfilling shall be compacted in three lifts to ensure the trench does not settle. The trench will be topped of with topsoil.

4.3. Non-Perforated Drain Installation. The Contractor shall install non-perforated drain pipe in fairways and rough for subsurface drainage as indicated on the Plans or as directed in the field and in the accordance with the manufacturer's installation recommendations, and in accordance with ASTM D 2321.

4.3.1. The drain pipe shall have a uniform slope of no less than 0.5%.

4.3.2. All pipe shall be vented with 10" catch basins wherever drainage lines meet, at all areas as indicated on the Plans, and/or as directed by the G.C.S. The Contractor shall install catch basins a minimum of 150 feet apart on long runs of pipe.

4.3.3. Catch basins shall be set flush with the finished grade after seeding or sodding. If required, the Golf Contractor shall grade as much as 10 feet around the catch basin to ensure a natural appearance to the installation.

Golf Design Unlimited, LLC Page 32

4.3.4. All drain lines and catch basins shall be lined with 14-gauge wire so as to be located with a metal detector.

4.3.5. Once the drain pipe is in place, the trench will be topped-off with 6" of topsoil.

4.4. Catch Basins - The Golf Contractor shall make the catch basin using 8” or 12" smooth wall interior pipe as indicated in the construction detail.

4.5. Drainage Termination Points:

4.5.1. If terminating in a drainage ditch, the last twenty feet (20') of pipe before termination of the drain line must be non-perforated. The Golf Contractor shall install pest control gates inside the pipe to prevent animals from entering the drain line.

5. WARRANTY: Workmanship under this Item shall be guaranteed by the Golf Contractor for one year after completion. Any settlement in trenches within 1 year of the final completion date shall be repaired by the Contractor at no charge.

6. PAYMENT. All work trenching, supplying & placing gravel, placing pipe, backfilling), methods of construction and clean-up shall be subject to the approval of the G.C.A. or G.C.S. and paid per lineal foot or each unit as follows:

400.1 - 4” Solid Pipe - paid per l.f.

400.2 - 4” Perforated Pipe - paid per l.f.

400.3 - 12" Catch Basin - per catch basin

400.4 - Gravel Sump 4’ x 4’ x 4’ – per sump

Golf Design Unlimited, LLC Page 33

ITEM 500 - LOADING AND/OR HAULING & PLACING MATERIAL

DESCRIPTION. Under this Item, the Golf Contractor shall: haul fill material to needed areas;

haul and place approved sand to the bunkers & haul and load topsoil (existing or supplied) to all areas that need extra topsoil. Fill material will come from the site and will not be hauled in from off the site unless the Owner chooses to pay extra to bring it in from off site. All haul roads will be repaired by the Golf Contractor according to directions of the superintendent and

G.C.A., and there shall be no charge for the repair of the haul roads.

EQUIPMENT: The Golf Contractor shall use proper equipment for getting around a golf course and not damaging it. All equipment is subject to the approval of the G.C.A. and the superintendent.

MATERIALS. All construction materials shall be supplied by the Owner and approved by the G.C.A.:

Topsoil - If the Owner needs to supply topsoil it shall be clean topsoil, and must be approved.

Fill - The fill material brought to, or from, the site shall be clean fill with not rock, or concrete larger than six (6") inches in size, and shall not make up more that 10% of the fill.

There shall not be any asphalt in the fill or any other toxic material.

CONSTRUCTION METHODS: The Golf Contractor shall use only approved equipment to transport construction materials. All materials shall be placed as close as possible to the various construction items for use by the Golf Course Shaper or by the

Golf Contractor’s own crew. All ruts the trucks make shall be repaired by the Golf

Contractor at no additional expense. This will include fertilizing and seeding or sodding if the G.C.A. so directs.

CLEAN UP AND APPROVAL. All work, methods of construction and clean-up shall be subject to the approval of the G.C.A.

PAYMENTS : Payments shall be made on a unit price basis (cubic yards) for each of the following items.

500.1 Load, Haul & Place Bunker Sand - paid per ton

500.2 Load, Haul & Place Topsoil – paid per c.y.

500.3 Generate, Load, Haul & Place Fill - paid per cy

END OF ITEM 500

Golf Design Unlimited, LLC Page 34

Item 600 – EXTRA SHAPING

1. DESCRIPTION. . This item describes extra shaping for areas beyond the expected shaping of all the sand bunkers. To be paid for 'extra shaping' it must be approved before hand by the G.C.A. Under this Item, the Golf Contractor shall prepare areas for the Shaper to do his work. The work also includes any other features deemed necessary by the G.C.A. not covered in another Item.

2. EQUIPMENT:

2.1. A bulldozer (D-4, or D-5) shall be required for all major shaping operations. A back-hoe with a swivel-bucket or a bobcat may also be used.

3. MATERIALS. All materials if needed shall be supplied by the Golf Contractor.

3.1. Fill. All fill necessary for the project will be obtained from areas on the site by the Contractor.

3.2. Topsoil. The Shaper shall strip & stockpile all existing topsoil for re-use and re-spread later. If additional topsoil is needed it shall be a good quality loam, free from lumps, and stones or debris larger than one inch in diameter of any kind as supplied, and stockpiled in a parking lot.

4. PRELIMINARY WORK. The G.C.A. shall work with the Shaper and answer any questions they may have on the existing irrigation system. The Contractor shall be responsible to disconnect irrigation lines and install any gate valves necessary at any of the construction sites prior to all construction operations.

5. MOUND AND BERM SHAPING:

5.1. Fill Material Placement and Rough Grading. The Golf Contractor shall haul any necessary fill material quantities to the site as directed by the G.C.A. according to Item 500. All fill material shall be placed in layers not to 12 inches and each layer will be compacted by a rolling dozer with the blade up before the next fill layer is laid upon it. The acceptable tolerance of workmanship is plus or minus two inches (+ or - 2").

5.2. Final Shaping. The Shaper shall final grade all mounds and berms to the complete satisfaction of the G.C.A.

6. CLEAN-UP AND APPROVAL. All work, methods of construction, and clean-up by the Golf Contractor shall be subject to the approval of the G.C.A.

7. PAYMENT - The Golf Contractor shall be paid for his extra shaping work on a per hour basis and fractions thereof. Please note that the shaping of greens, sand bunkers and tees, and retention basin are under those specific specifications and shaping is included in those prices. Important - all shaping to be done under this Item and invoiced under this Item must be discussed and approved by the G.C.A. ahead of time in writing.

Item 600. Extra Shaping - paid for per hour

Golf Design Unlimited, LLC Page 35

END OF ITEM 600

Item 700 – IRRIGATION

1. DESCRIPTION. The work under this Item consists of the Contractor re-using existing sprinkler heads (I-80 Hunters) around sand bunkers. The Contractor shall provide all labor and technical supervision to install and fully test additions and modifications to the existing golf course automatic irrigation system to the complete approval and satisfaction of the Golf Architect and the

Superintendent. All work shall be of the highest quality and workmanship. The Contractor shall guaranty his work for a period of one (1) year, and shall repair any damage caused to the new installations and/or connections to the original irrigation system when the system is started up the following spring. The Contractor shall supply a "GPS-As Built" of the renovation.

2. OWNER'S AND GOLF ARCHITECT'S RESPONSIBILITIES.

2.1. GCS has an as-built irrigation Plan for reference. It is located at the maintenance building.

3. CONTRACTOR’S RESPONSIBILITIES.

3.1. Security. Adequate security of materials on site shall be provided by the Owner at all times at his expense. During the life of this contract, the Contractor shall be solely responsible for the replacement of any irrigation materials or supplies which are stored on the site, and are stolen or vandalized prior to installation.

3.2. Damage to Other Work and Vegetation. If, in the opinion of the Superintendent and/or the Golf

Architect, a malfunction or other failure renders the irrigation system or a portion of the system inoperable, and this results in erosion or other damage to the golf course during the construction period, the cost of corrective work necessary to repair, replant, or otherwise return the damaged area to an acceptable condition shall be borne by the Contractor. The Contractor shall exercise special caution to tree, shrubs, and their roots.

3.3. Existing Sprinkler Heads. The Contractor shall remove existing sprinkler heads and re-use them on the holes slated for re-build/enlarge or new.

4. CONTRACTOR SUPPLIES ALL MATERIALS The Contractor shall re-use all Hunter irrigation heads and other parts etc.. The Contractor shall supply all additional pipe. Where possible the

Contractor shall connect pipe to existing gate valves. All material listed below shall also include the note “or approved equal”.

4.1. General. All new materials installed shall be in perfect condition and shall meet the requirements of the existing system.

4.2. Sprinkler Heads, Electric Valves and Quick-coupling Valves. All material shall be manufactured by Hunter to match or approved equal and must be approved by the G.C.A.

Golf Design Unlimited, LLC Page 36

4.3. Wire. All wire shall be UL listed, polyethylene coated shall be of sufficient size and type to match existing wire. All splices shall be waterproof.

4.4. Valve Boxes. Access to all main line, green, and tee isolation valves shall be provided by

Ametek, or an approved equal.

4.5. Gate Valves. All main line isolation valves larger than 2.5” shall be iron body, bronze mounted units which meet AWWA specification C5090, as manufactured by Waterous or other U.S.

manufacturer as approved by the Golf Architect. They shall be resilient wedge valves with a working pressure rating for cold water of at least 200 psi. The valves shall have push-on ends specifically designed for use with PVC pipe. The valves shall be equipped with non-rising stems and 2” square cast iron operating nuts. Two (2) T-handle valve wrenches shall be supplied for valve operation. 2.5” and smaller isolation and drain valves shall be screwed bonnet, bronze body, solid-wedge type gate valves with threaded ends, non-rising stems, and shall be rated for a normal operating pressure (cold water) of at least 200 psi. They shall be Kitz Model #27, or an approved equal.

5. CONSTRUCTION DETAILS.

5.1. Installation. Install pipe, wire, valves, sprinklers, and all other appurtenances in strict accordance with the manufacturer’s recommended procedures, standard industry practices, these specifications, and the direction of the Golf Architect and/or the Superintendent.

5.2. Excavation. Trench for pipe shall be wide enough to allow for proper tamping around the pipe in accordance with the manufacturer’s recommendations. The trench shall be deep enough to allow for a minimum of 18” cover over the top of all the pipe. The bottom of the trench shall be clean and smooth, with all rock, loose soil, and organic matter removed. The Contractor shall insure that there are no conditions in the trench that could damage the pipe or the wire. Any deviations from the above must be approved by the Superintendent and/or the Golf Architect.

5.3. Rock Removal. If subsurface conditions along with the proposed trench line are such that excavating equipment of the type and size correctly suited to this installation cannot properly excavate the trench and blasting is required, the Contractor shall notify the Golf Architect immediately to make adjustments for the pipe installation.

5.4. Deleterious Material. Excavated material which consists of rock larger than 1” in diameter or other material unsuitable for backfill (as defined by the pipe manufacturer’s instructions) shall be classified as deleterious material. The Contractor shall remove this material and haul it to an on-site dump locations designated by the Superintendent. In back-filling excavations where deleterious material has been removed, the Contractor shall install select backfill. Note there will be maximum ceiling payment for any large rock removal (deleterious material). It is the

Irrigation Contractor's responsibility to understand the existing soil conditions.

5.5. Valves. Isolation valves shall be installed plumb and level, and anchored in accordance with the pipe manufacturer’s recommendation. Isolation valves shall be afforded access through a valve box.

5.6. Wire and Wire Splicing. Do not yank, stretch, or pull wires during installation. Provide a minimum of one foot of slack, in an expansion loop, in each 100 feet of wire. Lay wire on a firm even bed in the trench, which shall support the entire length. At splice locations, provide sufficient slack to allow the splice to be raised a minimum of 24 inches above grade for

Golf Design Unlimited, LLC Page 37 inspection. Do not lay wire above, or on top of the pipe, except when wire and pipe are being plowed simultaneously. When power and pulse wire runs do not follow the pipe, lay them in a straight line which shall be carefully located on the as-built plan. Minimum 2.5” pipe shall be used as wire conduit for bridge crossings. Power and pulse wires shall be as specified in the wire specifications. Splice all wires to requirements of local minimum regulations or to the following recommendations, whichever is more restrictive: Make all splices by baring a minimum of three-quarters of an inch of copper conductor, twisting the leads together, and soldering them with a non-acid core solder, wire nuts are acceptable in lieu of soldering. Make the splice completely waterproof by using connector kits in strict accordance with the manufacturer’s recommendations.

5.7. Sprinkler Heads. Install sprinkler heads plumb and to grade. Elevation of the sprinkler heads is critical and the Contractor shall exercise care to set them exactly to grade.

5.8. Quick-Coupling Valves. Install quick-coupling valves to finish grade and on live pipe as indicated on the Plans.

5.9. Valve Boxes. One valve box shall be used for each valve location. Elevation of the sprinkler valve boxes is critical and the Contractor shall exercise care to set them exactly to grade and on dry level ground wherever possible. Do not locate valve boxes in tee surfaces, or in the approaches, collars, or putting surfaces of the greens. Avoid locating them in low spots that will collect drainage.

5.10. Backfill. After pipe and wires have been laid and thrust blocks have been set, trenches shall be backfilled using rock-free excavated material. Pipe shall be hand backfilled and tamped to 4" above pipe. Trenches shall be tamped at three levels to eliminate future settling, and to bring the settled trench line flush with the surrounding grade, after topsoil has been replaced.

5.11. Turf - Irrigation changed in existing turf areas must first have the sod carefully removed and then replaced so the area is uniform in slope and easy to mow. All of this work is subject to the approval of the G.C.

6. GUARANTY. The Contractor shall be responsible to repair any leaks.

7. CLEAN UP AND APPROVAL. All work, methods of construction and clean-up shall be subject to the approval of the G.C.S. and G.C.A.

8. BASIS OF PAYMENT. Work includes all labor, and technical supervision to re-install, and test the new irrigation (please note the contractor is responsible to supply all additional piping, wire, gate valves, valve boxes all necessary items (note there will be no extra charge for any items necessary for a sprinkler head to work) according to plans, plus supply. The Contractor shall be [paid by the

G.C.A. counting each type of sprinkler head and multiplying by the unit price.

700.0 - Re-use Irrigation at Tees – Hunter I-80’s (includes all work ie, trenching, pipe, wire) . paid per head

END OF ITEM 700

Golf Design Unlimited, LLC Page 38

Contractor's Name ____________________________________________________________________

TIMBERLIN GOLF COURSE

SAND BUNKER RESTORATION PROJECT

CONTRACTOR BID SHEET

The undersigned proposes to construct the following items according to the Plans, Specifications, Construction Details and Field Design of Golf Design Unlimited. The Contractor shall furnish all material and shall provide all labor, approved equipment, and services and shall include all and any sales tax if applicable, overhead and profit and complete all work for the Unit Prices below.

Timberlin GC reserves the right to reject or accept any part of or all of any bid. The bid will be

PREVAILING WAGE.

SCENARIO ‘A’ – All 18 Holes

Estimated Unit Estimated

Item Item Description Quantity Price Bid Total

100.0 - Silt Fence 300 l.f. _________ ___________

200.1 – Rebuild/New Sand Bunker 51 each _________ ___________

(1,070 s.f. avg. with average 70 l.f. perforated drainage inside and two 6” vents included)

200.2 – Remove Sand Bunker 10 each _________ ___________

300.1 – Sodding (Tall Turf Type Fescue for Rough) 120,000 s.f. _________ ___________

300.2 – Sodding (Bentgrass for Fairways) 1,000 s.f. _________ ___________

400.1 – 4” Non-perforated Drainage (from sand bunker) 1,515 l.f. _________ ___________

400.2 – 4” Perforated Drainage (outside of sand bunkers) 200 l.f. _________ ___________

400.3 – 12” Catch Basins 5 each _________ ___________

400.4 – Gravel Sump (4’ x 4’ x 4’) 17 each _________ ___________

500.1 – Load, Haul & Place Bunker Sand (54,000 s.f.) 1,400 ton _________ ___________

500.2 – Load, Haul & Place Topsoil (supplied by owner) 50 c.y. _________ ___________

500.3 – Load, Haul & Place Fill (supplied by owner) 50 c.y. _________ ___________

600.0 – Extra Shaping 3 hours _________ ___________

700.0 – Sand Bunker Irrigation (Hunter I-80’s) 55 heads _________ ___________

(paid per head re-used and moved including pipe)

Golf Design Unlimited, LLC Page 39

Total Scenario ‘A’ $_____________________________ (Above written in numbers)

(Above written in words) continued

SCENARIO ‘B’ – Greenside Sand Bunkers Only

100.0 - Silt Fence 200 l.f. _________ ___________

200.1 – Rebuild/New Sand Bunker 30 each _________ ___________

(1,065 s.f. avg. with avg. 70’ perforated drainage inside and two 6” vents included)

200.2 – Remove Sand Bunker 3 each _________ ___________

300.1 – Sodding (Tall Turf Type Fescue for Rough) 70,000 s.f. _________ ___________

300.2 – Sodding (Bentgrass for Fairways) 1,000 s.f. _________ ___________

400.1 – 4” Non-perforated Drainage (from sand bunker) 890 l.f. _________ ___________

400.2 – 4” Perforated Drainage (outside of sand bunkers) 100 l.f. _________ ___________

400.3 – 12” Catch Basins 5 each _________ ___________

400.4 – Gravel Sump (4’ x 4’ x 4’) 10 each _________ ___________

500.1 – Load, Haul & Place Bunker Sand (33,000 s.f.) 855 ton _________ ___________

500.2 – Load, Haul & Place Topsoil (supplied by owner) 50 c.y. _________ ___________

500.3 – Load, Haul & Place Fill (supplied by owner) 50 c.y. _________ ___________

600.0 – Extra Shaping 3 hours _________ ___________

700.0 – Sand Bunker Irrigation (Hunter I-80’s) 25 heads _________ ___________

(paid per head re-used and moved including pipe)

Total Scenario ‘B’ $_____________________________ (Above written in numbers)

Golf Design Unlimited, LLC Page 40

(Above written in words)

Add/Alternates

Add1.0 4” Solid Drainage Pipe 50 l.f. _________ ___________

Add2.0 4” Perforated Drainage Pipe 700 l.f. _________ ___________

Add3.0 12” Catch Basins 15 each _________ ___________

Add4.0 Gravel Sump (4’ x 4’ x 4’) 1 each _________ ___________

Add5.0 Install Fairway Sod (#3, 11, 16, 18) 53,000 s.f. _________ ___________

QUALIFICATION REQUIREMENTS FOR CONTRACTOR

Qualifications for the project the Contractor must meet: the Contractor shall have golf course construction experience with a minimum of five years. The Contractor must have completed start to finish construction of 30 (thirty) sand bunkers in the past 3 (three) years. The Contractor MUST have experience installing Capillary Concrete liners in sand bunkers. The supervisor for this project must have the same experience. Make sure to fill out form concerning qualifications and submit with bid and do not include more info.

Contractor (submitting bid) _____________________________________________________

Please list golf courses where you have installed drainage and rebuilt sand bunkers:

Golf Course:_____________________________________________

Address:________________________________________________

Golf Course Architect:_____________________________________________

Contact at Course:_________________________________________

Golf Course:_____________________________________________

Address:________________________________________________

Golf Course Architect:_____________________________________________

Golf Design Unlimited, LLC Page 41

Contact at Course:_________________________________________

The Contractor shall also list any important sub-contractors he will be using.

Sub-Contractor _____________________________________ phone ______________for _______________

Golf Design Unlimited, LLC Page 42

Golf Design Unlimited, LLC Page 43

6" N-12 Pipe

NEW & REBUILD SAND BUNKER DETAIL

with Capillary Concrete Liner (No Scale)

Min. 5'

Sod

Subsoil

Endcap

Subsoil Peagravel

Plastic Green Grate (6" Min.)

Sand (as above)

4" Perforated Drain Tile

6" Topsoil

4" Non-Perforated or Perforated Pipe to Drainage Sump, Ditch or Pond.

6" Topsoil

View of 8" N-12 Pipe w/ Grate

4" Tamped Sand

SEE

ENLARGEMENT

ABOVE

4" Perforated Drain Tile

6" - 12"

2"

12"

Subsoil

Sodded Slope

6" Topsoil 2" Capillary Concrete

2" Sand into Trench 4" Pea Gravel above Tile

SECTION 'A-A'

BUNKER PERIMETER

SODDED

(SEE SPECIFICATIONS)

Sod at 90 degree angle

Sod-- Minimum 2 Strips or Whole Area

Sand Capillary Concrete

(Under Sod & Under Sand)

0.5% Min. Fall

BB

A

A 6" Catch Basin 4' to 5' away from bunker edge

DRAIN TILE

PLAN VIEW

SECTION 'B-B'

Golf Design Unlimited, LLC Page 44

Golf Design Unlimited, LLC Page 45

Golf Design Unlimited, LLC Page 46

Golf Design Unlimited, LLC Page 47

Golf Design Unlimited, LLC Page 48

Golf Design Unlimited, LLC Page 49

The Bunker Edge

To maintain the nature of the product, every effort should be made to prevent soil contamination of

Capillary Concrete during installation, curing, and prior to sand installation. Two methods to safeguard your installation from contamination:

1. Grassing around the perimeter of the bunker prior to Capillary Concrete installation: With this method, it is recommended that turf grass around the perimeter of the bunker should be secured to the soil by roots or staples before the installation of Capillary Concrete. After installation and curing and a water test has been performed to ensure drainage function, sand can be installed in the bunker. For newly sodded bunkers, where additional irrigation is required for rooting and establishment, we recommend that a thicker layer of sand (approx. 8-10 inches high x 10 inches wide) be installed on inside perimeter of the bunker against new sod. This is done to allow the sand to act as a filter layer to catch any soil runoff during irrigation cycles on the newly placed sod. Once the sod is established and irrigation cycles are reduced, any contaminated sand around the perimeter should be removed. Bunker sand can be leveled and normal bunker maintenance practices can begin.

2. Capillary Concrete installation prior to sod placement: In situations where grass cannot be installed prior to the installation of Capillary Concrete, extreme care must be used to prevent soil contamination.

Sand should be installed immediately after curing and the water test. As in method 1), a thicker perimeter layer of sand should be installed to reduce soil contamination prior to sod placement. After establishment, any contaminated sand around the perimeter can be removed.

Golf Design Unlimited, LLC Page 50

Planning and Construction of The Bunker Edge The edge detail often gives the bunker shape its distinctive style. Capillary Concrete has the unique ability to be formed to fit any Architects design goals.

Preserving the desired style or motif and reducing ongoing maintenance is critical to the success of any bunker restoration/renovation plan.

1. Existing bunker and sod renovation The strength of Capillary Concrete allows the opportunity to protect the inside wall of the bunker better than any other product. Cap- illary Concrete has the ability to be shaped almost vertically at installation to get the least possible amount of soil in contact with the bunker sand. In this photo the subgrade under the existing turf has been excavated 3-4 inches and a layer of Capillary Concrete has been placed under the sod to help protect the edge from collapse and contamination. Sand is pulled up the face to hide the Capillary Concrete edge.

2. New sod layer around the perimeter In this case, either the existing soil and grass, or sod is utilized as the edge of the bunker. The 2-inch (50mm) layer of Capillary Concrete meets the edge of the bunker.

Rolling the sod over the face to cover the soil is an option.

Bunker Sand Testing

Capillary Concrete has an open structure that allows water to freely drain through it at more than 100 inches per hour. Once sand is placed on top of the product, the new water drainage limit will be the Ksat

(saturated hydraulic conductivity) of the sand that covers the Capillary Concrete product. After gravitational water has freely drained from the sand, a certain amount of water will always be retained in the sand against the force of gravity. This is known as capillary water and the amount can be determined with a Soil Moisture Release Test by an accredited test lab. Every different bunker sand has its own unique amount of capillary water retention based on the amount of moisture present in the sand. If the

Capillary Wash Box is installed, the sand can be modified and finer particles in the sand at the base of the bunker can be removed. Never use a sand that is not an approved USGA sand. For more information on selecting the perfect bunker sand we recommend this information from the USGA:

https://www.usga.org/ content/usga/home-page/course-care/green-section-record/58/11/a-guide-to-selecting-the-right-bunker-sand-for-your-course-. html#returnable.

Pre-Construction Checklist

Golf Design Unlimited, LLC Page 51

1. Heavy-duty vehicle to haul mix from the ready-mix truck to the bunker.