BCOES_CERT_RE_FORT PIERCE BEACH RENOURISHMENT.pdf

PDF 106 KB Posted

Attached to
Shore Protection Project Fort Pierce Beach Renourishment 2023 St. Lucie County, Florida
Solicitation number
W912EP23B0003
Issued by

About this file

This memorandum outlines requirements for a shore protection project to renourish Fort Pierce Beach in St. Lucie County, Florida. The project work includes constructing a beach berm along approximately 7,000 feet of shoreline south of Fort Pierce Inlet between Florida Department of Environmental Protection Range Monuments R-34 and T-41. Beach compatible sand will be dredged from Capron Shoal approximately four miles southeast and offloaded inside the South Jetty of Fort Pierce Inlet. In addition to beach renourishment, the project requires endangered species observation, sea turtle non-capture trawl sweeping, turbidity monitoring, beach tilling, and vibration control and monitoring. A pre-bid conference will be held via teleconference on November 18, 2022 at 11:00am EST, with call-in and web details provided. The solicitation number for this opportunity is W912EP23B0003.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CESAJ-RE 6 OCTOBER 2022

MEMORANDUM FOR THE RECORD

SUBJECT: SHORE PROTECTION PROJECT, FORT PIERCE BEACH RENOURISHMENT

2023, ST. LUCIE COUNTY, FLORIDA

Project work consists of constructing a beach berm along approximately 7,000 feet of shoreline immediately south of Fort Pierce Inlet between Florida Department of Environmental Protection (FDEP) Range Monuments R-34 and T-41. The project work is subdivided into a base and one option as shown on the drawings. Beach compatible sand for the project will be dredged from Capron Shoal, located approximately four miles southeast of the project site. Due to the extensive hardbottom areas located offshore of the fill area, offshore pipeline access to the beach site is prohibited. Offloading will be done inside the South Jetty of Fort Pierce Inlet, as shown on the plans. A staging area and beach access to the project fill area is located at the end of Seaway Drive and near the south jetty offloading area. Project work also includes but is not limited to endangered species observation, sea turtle non-capture trawl sweeping, turbidity monitoring, beach tilling, and vibration control and monitoring.

In accordance with the provisions of ER 415-1-11, certification is made that all appropriate biddability, constructability, operability, environmental, and sustainability (BCOES) review comments have been incorporated into the subject bid package or otherwise satisfactorily resolved. Feedback to reviewers for all comments is available on DrChecks.

The lands required for the project were certified by St. Lucie County Erosion District in certifications dated 19 June 2020 and 28 September 1998.

Timothy H. McQuillen Chief, Real Estate Division Date