This document is a Request for Proposal (RFP) #2023-11 from the City of Bloomington for Police Department Administration Building Automation System Improvements. The RFP seeks qualified providers to design, install, calibrate, activate, and train staff on an upgraded Building Automation System (BAS) for a multi-level police administration building constructed in 1996. The project offers two options: a complete BAS upgrade utilizing Open Protocol Direct Digital Controls based on the Niagara N4 Framework (Option A), or improvements to the existing Johnson Controls Metasys System (Option B). The project must be completed by April 30, 2023, with potential extension at the City's discretion.
The existing building automation system requires significant upgrades, including repairs or replacements of control components for exhaust fans, boilers, fin tube coils, VAV boxes, and other mechanical systems. The RFP emphasizes the need for an open, interoperable system that supports multi-vendor integration, secure web access, and direct programmability. The City will retain full ownership of all software, graphics, and engineering designs. Respondents will be evaluated on business qualifications (40%), employee qualifications (20%), performance history (30%), and project management experience (10%), with a focus on providers who can deliver a comprehensive, technically advanced building automation solution.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
POLICE DEPARTMENT ADMINISTRATION
BUILDING AUTOMATION SYSTEM
BAS‐1
I. GENERAL BUILDING INFORMATION
The Police Department Administration building is a multi-level structure containing general office space, meeting areas, storage areas, mechanical & electrical rooms and vehicle parking areas. The facility was built in 1996.
II. EXISTING BUILDING AUTOMATION SYSTEM
The existing Building Automation System (BAS) is a Johnson Controls Metasys System which was installed when the facility was initially constructed. A few minor upgrades to the BAS have been performed since the building became operational. Record drawings for the original BAS system are attached.
III. EXISTING CONTROL COMPONENTS
The existing control components include automated dampers, valves, variable frequency drives, thermostats and various sensors, including occupancy, temperature, pressure, etc.
IV. EXISTING HVAC COMPONENTS
The existing primary HVAC components include chillers, a cooling tower, boilers, hot water heating pumps, air handling units and exhaust fans.
V. REQUIRED AUTOMATION
The City of Bloomington is requesting proposals from Qualified Providers to design, install, calibrate, activate and train City staff on an upgraded Building Automation System or improvements to the existing system. The work must be based on the following specification with no exceptions.
A. BAS UPGRADE SCOPE OF WORK (OPTION A)
1. Furnish all labor, materials and equipment necessary for a complete and operating Building Automation System (BAS) upgrade and integration, utilizing Open Protocol Direct Digital Controls only. The intent is to provide a system that is open in protocol throughout the facility and based upon the Niagara N4 Framework.
2. Any proposed system architecture must fully support a multi-vendor environment and be able to integrate third party systems via existing vendor protocols including, as a minimum, LonTalk, BACnet, and Modbus.
3. System architecture shall provide secure Web access using a standard web browser from any computer on the owner’s LAN that has proper credentials and password information.
4. All control devices furnished must be programmable directly from the Niagara N4 Workbench upon completion of this project. The use of configurable or programmable controllers that require additional software tools for post-installation maintenance are not acceptable.
BAS‐2
5. Any control vendor that must provide additional BMS server software shall be unacceptable. Only systems that utilize the Niagara N4 Framework meet the requirements of this RFP.
6. The BAS server shall host all graphic files for the control system. All graphics and navigation schemes for this project shall be custom generated to match the existing mechanical equipment and building layout. Generic “cut and paste” graphics will not be acceptable.
7. OPEN NIC STATEMENTS - All Niagara N4 software licenses shall have the following NiCS: “accept.station.in=*”; “accept.station.out=*”and “accept.wb.in=*”and “accept.wb.out=*”. All open NIC statements shall follow Niagara Open NIC specifications; systems not meeting these fully open standards are not acceptable.
OPEN, INTEROPERABLE, INTEGRATED ARCHITECTURE (OPTION A)
8. Responders must provide a system based on a peer-to-peer networked, stand-alone, distributed control system utilizing industry standard open protocol communication providing the end user with one open, interoperable system.
9. The supplied system software shall employ object-oriented technology (OOT) for representation of all data and control devices within the system. In addition, adherence to industry standards including ANSI/ASHRAE™ Standard 135, BACnet and LonMark to assure interoperability between all system components is required.
10. A hierarchical topology is required to assure reasonable system response times and to manage the flow and sharing of data without unduly burdening the customer’s internal Intranet network. Systems employing a flat single tiered architecture shall not be acceptable. Maximum acceptable response time from any alarm occurrence (at the point of origin) to the point of annunciation shall not exceed 10 seconds for network connected user interfaces. Maximum acceptable response time from any alarm occurrence (at the point of origin) to the point of annunciation shall not exceed 60 seconds for remote or dial-up connected user interfaces.
11. All components and controllers supplied shall be true “peer-to-peer” communicating devices. Components or controllers requiring “polling” by a host to pass data are not acceptable.
B. BAS IMPROVEMENT SCOPE OF WORK (OPTION B)
1. In lieu of providing the BAS upgrade described in the previous sections (OPTION A), an alternate proposal may be submitted. This alternate proposal (OPTIONB) shall accomplish all other requirements included in this request by making improvements to the existing BAS.
2. The proposal shall be clearly identified as BAS IMPROVEMENT
(OPTION B).
BAS‐3
3. All labor, materials and equipment necessary for a complete and operating improvement of the existing BAS shall be included.
C. SOFTWARE OWNERSHIP (OPTIONS A & B)
The City of Bloomington shall have full ownership and full access rights for all network management, operating system server, graphics, engineering designs and programming software required for the ongoing maintenance and operation of the Building Automation System.
D. OTHER INFRASTRUCTURE IMPROVEMENTS (OPTIONS A & B)
1. Some existing sensors or control equipment are damaged or not functional. These items are listed in the attached Table 1. These items need to be repaired or replaced and incorporated into the fully functional BAS for the facility.
2. Some equipment is currently not included in the existing BAS. This equipment is listed in the attached Table 2. The table also identifies equipment that will not be included in the BAS improvements project and equipment that need to be added to the BAS as part of the project.
3. The BAS upgrade or improvements need to include all required fire system interaction or override for compliance with applicable codes.
4. All new electrical circuits must be in existing or new conduit and comply with applicable codes.
5. All new fire alarm circuits must be in existing or new conduit and comply with applicable codes.
VI. SCHEDULE
A. BAS improvements or upgrades shall be scheduled and performed such that minimal disruption to the operation of the facility occurs.
B. Complete implementation of the BAS improvement or upgrade shall be completed no later than April 30, 2023. The completion date may be extended at the sole discretion of City Facility Management staff. The contractor shall request the extension in writing at least 15 days prior to the completion date and provide an explanation why the extension is necessary.
VII. SUBMITTAL REQUIREMENTS
A. Submittals shall include the following sections with relevant documentation.
Additional information can be provided. The City of Bloomington reserves the right to reject any response that is not formatted as described.
1. Cover Letter
2. Table Contents
3. Proposal with Cost Based on Services Requested
4. Executive Overview
5. Company Overview
BAS‐4
6. Company’s Commitment to Process
7. Individual Team Member’s Resumes
8. Sole Source Open Architecture Capabilities
9. Project Management Plan
10. Location of Office and Service Personnel Responsible of the Project
11. References with Similar Scopes of Work
12. Equipment, Maintenance, Training & Support
VIII. EVALUATION CRITERIA
A. Respondents Business Qualifications (40%)
1. Ability to be the first party and sole source provider of the requested Building Automation System improvement or upgrade.
2. Years of Experience in Building Automation System field.
3. Location of Qualified Providers Office, to provide timely service.
4. Ability to provide a sole source Open Architecture Building Automation System, without the use of proprietary software or hardware.
B. Respondents Employee Qualifications (20%)
1. Experience of employees to perform their specified duties.
2. Years of experience providing their specified duties.
3. Location of employees to provide timely service.
C. Performance History (30%)
1. Experience with design, installation, and maintenance, monitoring and training for customers with similar scopes of work.
2. Sole source responsibility for design, installation, and maintenance, monitoring and training for projects with similar scopes of work.
3. References of prior customers with similar scopes of work.
D. Project Management Experience (10%)
1. Ability to provide in-house Project Management services for the desired design, installation, maintenance, monitoring and training of a Building Automation System improvement or upgrade.
2. Methods used to determine cost associated with the desired scope of work.
3. Ability to provide local resources to insure a timely project with desired results.
IX. RIGHTS & RESPONSIBILITIES
The City of Bloomington reserves the right to reject any and all responses received from this RFP. Late responses will not be accepted. The City of Bloomington is not responsible for any cost incurred by any person or company that issues a response to this
RFP.
CONTROL EQUIPMENT LOCATION CURRENT CONDITION DESIRED CONDITION
Exhaust Fans Parking Garage
Controls or Programming not functional.
Fans currently operate 24/7/365. Fans should be controlled by CO sensors.
Boilers Mechanical Room
Originally the 4 Boilers were controlled by a Weil‐Mclean Boiler control and the building automation system only sent an on/off command. The Weil‐Mclean control was scrapped and a basic Johnson
Control system was put in its place. It is not in an electrical box, but sitting on top of abandoned Weil‐Mclean box. Wiring is not code compliant. Outside air temp sensor was ran with non‐plenum thermostat wire and is going up through the existing mechanical room exhaust fan hood and the wire comes out of a vent on the side of the exhaust fan into a LB fitting with the sensor inside. Also, we currently do not have any status and temp sensors going to BAS to notify us when a boiler goes down. It has to be manually assessed in person.
Replace the current controls for all 4 boilers to full automation, with graphics, override controls, etc. All work shall be done in conformance with applicable codes.
Fin Tube Coils Throughout Building
Currently all fin tube radiant heaters are controlled through the nearest VAV box controller. Every fin tube heater in the building does not function automatically with a change in room temperature. It has become standard operation to manually override all fin tube valves through the corresponding VAV in order to turn them off and on. Some VAV box controllers are not operational at all, and staff must manually turn on/off valves to these tubes each spring and fall.
Repair, replace or add VAV box controllers that are not functional. Update programming for VAV and fin tube control based on temperature and schedule.
Rooftop Chiller Roof
There are currently no alarm interlocks into the BAS indicating when the Chiller has gone into alarm. It requires someone to go onto the roof and access the control panel on the Chiller to find out if the system has any faults, alarms or lockouts present.
The new automation system needs to be tied into the chiller control system so the building operator can view chiller alarm status without going to roof on a daily/weekly basis. An indicator of alarm on the BAS system will help in more timely response to a failed component in the system before the entire chiller is down.
VAV's Throughout Building
The individual operation and controls of the VAV boxes are not functioning when changes are made. It's as if the points and programing links in the background were not set up properly so making changes does nothing on several points on many if not all VAV controller user interface BAS pages. It is difficult to control the airflow in heating and cooling seasons with limited functional control of listed features on respective VAV control pages. Also, zone setpoint is out of service on VR‐6 and VR‐
19.
Repair, replace or add VAV box controllers and update programming to address this issue.
VAV's 2nd Floor
VAV boxes are uninsulated and when building humidity is high, condensation would form on the sheet metal causing rusting along with condensation dripping onto the ceiling tile. Many ceiling tile were replaced over the years because of this problem.
Situation has been improved, if not completely corrected, with changes made to the dehumidification programming of the building. Issue should be investigated after all BAS improvements are complete and VAV boxes should be insulated as needed under the alternate bid item.
POLICE DEPARTMENT ADMINISTRATION BUILDING AUTOMATION SYSTEM IMPROVEMENTS
RFP # 2023‐11
TABLE 1 ‐ EXISITNG DAMAGED OR NON‐FUNCTIONAL CONTROL EQUIPMENT
CONTROL EQUIPMENT LOCATION CURRENT CONDITION DESIRED CONDITION
POLICE DEPARTMENT ADMINISTRATION BUILDING AUTOMATION SYSTEM IMPROVEMENTS
RFP # 2023‐11
TABLE 1 ‐ EXISITNG DAMAGED OR NON‐FUNCTIONAL CONTROL EQUIPMENT
BAS Graphics Throughout Building Non graphics based system.
The new system shall be graphics based to assist in the visual understanding of the operation of the entire system by the building operator. Status of operation of components, inlet and outlet temps of piping and air flow devices, etc. broke down by component and floor level for quick reference in the automation system.
OA/Humidity Sensor Mechanical Room & Building Exterior
Original OA/Humidity sensor for the system was previously located in the OA inlet air duct on the South side of the building. This never allowed the system to accurately function as the sun had a significant effect on the sensor causing it to read high during the daytime, and the humidity sensor did not get consistent outside airflow causing it to give unreliable results. Johnson Controls installed a new
OA/Humidity Sensor on the Northeast corner of the building and abandoned the original in duct sensor. We were able to increase energy savings utilizing greater
OA cooling vs. mechanical along with limiting OA air into the building when outside humidity high limiting the need for excessive dehumidification operation. At this time our dehumidification programming was adjusted and has been functioning better than ever.
Maintain current configuration, but replace sensors as needed.
EQUIPMENT LOCATION ISSUE / PROBLEM ADD TO BAS
Future Controls Dispatch Add conduit, wiring and box to control future AC system No
Future Controls Radio Room Add conduit, wiring and box to control future AC system No
Temp Sensor Radio Room
There is a stand‐alone ductless split air conditioning system that is used to cool the radio control room. This system is not a part of the
BAS. At minimum, a temperature sensor shall be installed and monitored on the new BAS and an alarm alert be sent when the room temperature gets above desired temp, indicating the cooling system is not working. This would allow quicker notification/response time for repairs or other arrangements to keep the equipment cool so that it does not overheat and go offline or worse. Yes
Future Controls
LL‐2 elevator rooms, generator room, water service room, all emergency stairwells and lobby entrances with unit heaters
We have had several instances where the heater would stop working and the pipes would freeze and burst in these areas. It would be beneficial, at minimum, to have a temperature sensor in these rooms in order to monitor temperature. An alarm in the BAS when the room temp falls outside of an acceptable range would be an early alert for potential freeze issues. Secondly, a full automation with status of these components could be but on the automation for remote testing of operational function to ensure proper operation in a more proactive manner. Yes
POLICE DEPARTMENT ADMINISTRATION BUILDING AUTOMATION SYSTEM IMPROVEMENTS
RFP # 2023‐11
TABLE 2 ‐ EQUIPMENT CURRENTLY NOT ON BAS