This is a Construction Schedule specification (Section 01 32 16) for a federal construction project managed by PECO PMIS 315705, effective April 14, 2026.
The specification requires the Contractor to prepare and maintain a comprehensive construction schedule using Critical Path Method (CPM) analysis with cost and resource loading. The Contractor must submit a Schedule of Values breaking down lump-sum contract items into component work activities, with total costs equaling the contract price. A Construction Baseline Schedule must be developed and accepted within 180 days of the Notice to Proceed, utilizing either Microsoft Project or Primavera software. The schedule must include all contract dates, phases, milestones, occupancies, holidays, weather considerations, and critical path activities. Individual activities are limited to 14 calendar days maximum, except for non-construction activities such as mobilization, shop drawings, fabrication, and delivery. Long lead procurement items (cycles exceeding 60 days) such as metal siding and HVAC equipment must be shown as separate activities. The Contractor must provide three-week look-ahead schedules before weekly progress meetings and update the baseline schedule monthly, with the status date seven days preceding each progress payment request. Recovery schedules must be submitted when work falls 14 or more calendar days behind the accepted schedule. For contract modifications, changes, delays, or Contractor requests affecting the schedule, time impact analyses using fragnets must be submitted to demonstrate the effect on overall project duration. Time extensions are granted only when equitable time adjustments exceed total available float on affected activities. Distribution of accepted schedules and updates is required to the Contracting Officer, Contracting Officer's Representative, Subcontractors, testing agencies, and other relevant parties, with copies posted in the Contractor's field office.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P6326Q0034_Amd_0003.pdf | ||
| B09_Solicitation_Amendment_3_Questions_and_Answers_0003.pdf | ||
| B09_Solicitation_Amendment_2_attach_1_Experience_Questionaire_0002.xls | XLS spreadsheet | |
| Sol_140P6326Q0034_Amd_0002.pdf | ||
| B09_Solicitation_Amendment_2_Attach_2_Project_Approach_0002.docx | DOCX document | |
| Sol_140P6326Q0034_Amd_0001.pdf | ||
| B08_Solicitation_Attach_1_SPEC_1_0.pdf | ||
| Sol_140P6326Q0034.pdf | ||
| B08_Solicitation_Attach_3_SPEC_1_2_Quality_Assurance_Checklist_-_Copy.pdf | ||
| B08_Solicitation_Attach_4_WD.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PECO PMIS 315705 01 32 18 - 1
14April2026 CONSTRUCTION SCHEDULE
SECTION 01 32 16 – CONSTRUCTION SCHEDULE
PART 1 - GENERAL
1.1 SUMMARY
A. Section consists of Construction Schedule requirements including:
1. Schedule of Values
2. Construction Schedule Requirements.
3. Construction Schedule Updates.
4. Time Impact Analysis.
B. Purpose: The Construction Schedule ensures adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. It shall assist the Contractor and
Contracting Officer (CO) in monitoring the progress of the work, evaluating proposed changes, and processing Contractor's monthly progress payments. It shall include the dates in the contract, phases, milestones, occupancies, holidays, weather consideration, a critical path, and the requirements of this section.
1.2 DEFINITIONS
A. Activity: A discrete part of a project identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: Allocation of the Schedule of Values for completion of an activity as scheduled.
The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.
C. Critical Path Method (CPM): Method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
D. Critical Path: Longest connected chain of interdependent activities through the network schedule that establishes minimum overall Project duration and contains no float.
E. Float: Measure of leeway in starting and completing an activity.
1. Float: Not for the exclusive use or benefit of the Government or Contractor but is jointly owned.
2. Free Float: Amount of time an activity can be delayed without adversely affecting the early start of the successor activity.
PECO PMIS 315705 01 32 18 - 2
3. Total Float: Measure of leeway in starting or completing an activity without adversely affecting planned Project completion date.
F. Resource Loading: Allocation of manpower and equipment necessary for completion of an activity as scheduled.
G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.
1.3 SUBMITTALS
A. Electronic Copies: Schedules and reports submitted shall be in native electronic file formats and/or in PDF format. The intent of the Government is to limit the number of printed reports to those determined by the project team as essential.
B. Schedule of Values: After contract award and before Pre-Construction conference, submit schedule of dollar values based on Contract Price Schedule.
C. Construction Baseline Schedule: After contract award and before Pre-Construction conference, submit the baseline schedule in electronic format (native file and PDF) formatted to show the entire schedule for the entire construction period. Utilize Schedule of Values in preparation of
Construction Baseline Schedule.
D. Critical Path Method (CPM) Reports: Concurrent with CPM schedule, submit in electronic format
(PDF) the following computer-generated reports. For each activity, include activity number, activity description, cost and resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.
1. Activity Report: List of activities sorted by activity number and then early start date, or actual start date if known.
2. Logic Report: List of predecessor and successor tasks for activities sorted in ascending order by activity number and then early start date, or actual start date if known.
3. Total Float Report: List of activities sorted in ascending order of total float.
E. Construction Schedule Updates: Provide as requested by the Contracting Officer.
F. Construction Schedule Revisions and Time Impact Analysis: Provide as requested by the
Contracting Officer. Incorporate a Fragmentary Network (Fragnet) into currently accepted
Construction Schedule that demonstrates how Contractor proposes to incorporate a modification, change, delay, or Contractor request.
1.4 QUALITY ASSURANCE
A. Contractor shall meet with Contracting Officer on day of the preconstruction conference to go over:
1. Discuss constraints, including work stages, area separations partial substantial completions.
2. Review time required for review of submittals and re-submittals.
PECO PMIS 315705 01 32 18 - 3
3. Review requirements for tests and inspections by independent testing and inspecting agencies.
4. Review time required for completion and startup procedures.
5. Review time required for obtaining and activating permits.
6. Review and finalize list of construction activities to establish the baseline schedule.
7. Discuss reporting requirements and protocol for naming and transmitting electronic submittals.
1.5 COORDINATION
A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate Contractors.
B. Coordinate Construction Baseline Schedule with Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.
1. In developing Construction Baseline Schedule, ensure Subcontractor’s work at all tiers, and prime Contractor’s work, is included and coordinated.
2. Secure time commitments for performing critical elements of work from parties involved.
3. Coordinate each construction activity in network with other activities and schedule in proper sequence.
PART 2 - PRODUCTS
2.1 SCHEDULE OF VALUES
A. Breakdown each lump-sum item into component work activities used in the schedule for which progress payments may be requested. Work activities broken out within schedule of values may be integrated into and made a logical part of the construction baseline schedule. Total costs for the component work activities shall equal contract price for that lump-sum item. Contracting
Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump-sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.
B. Do not break down unit price items. Use only the contract price for unit price items.
C. Total cost of all items shall equal the contract price. The Schedule of Values will form the basis for progress payments and the Construction Schedule.
2.2 CONSTRUCTION SCHEDULE REQUIREMENTS
A. Construction Baseline Schedule: Prepare Construction Baseline Schedule using a computerized, cost and resource-based, time-scaled Critical Path Method network analysis diagram for the
Work.
PECO PMIS 315705 01 32 18 - 4
1. Develop and finalize Construction Baseline Schedule so it can be accepted for use no later than one hundred eighty (180) days after date established for the Notice to Proceed.
a. Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing work within applicable completion dates, regardless of Governments acceptance of schedule.
2. Establish procedures for monitoring and updating Construction Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.
B. Construction Baseline Schedule Preparation: Prepare a list of all activities required to complete the Work. Using preliminary Critical Path Method network diagram, prepare a skeleton network to identify probable critical paths.
1. Activities: Indicate estimated duration, sequence requirements, and relationship of each activity in relation to other activities.
2. Critical Path Activities: Identify critical path activities, including those for interim completion dates. Scheduled start and completion dates shall be consistent with Contract milestone dates.
3. Processing: Process data to produce output data on a computer-drawn, time-scaled network. Revise data, reorganize activity sequences, and reproduce as often as necessary to produce the Critical Path Method schedule within the limitations of the Contract Time.
4. Show sequence and interdependence of activities required for completion of work. Ensure work sequences are logical and Construction Baseline Schedule shows a coordinated plan of the work.
5. Include anticipated normal downtime related to weather as non-working time due to seasonal weather conditions in planning and scheduling work influenced by high and low ambient temperatures, wind, or precipitation to ensure completion of work within contract time. Anticipated weather days shall be based on data for local area from a reliable source like the National Oceanic and Atmospheric Administration (NOAA), National Park
Service records, or source acceptable to Contracting Officer.
6. Time Frame: Proposed duration assigned to each activity shall be Contractor's best estimate of time required to complete activity considering the scope and resources planned for activity.
a. An early finish date may be shown but the late finish date shall be same date as last day of contract period. An early completion schedule shall contain:
1) Insert an activity titled "Project Float" as a successor to last activity in early project completion schedule network.
2) Add a milestone titled "Contract End Date" as a successor to the activity
"Project Float".
3) Add duration to the activity "Project Float" as required so the milestone
"Contract End Date" equals the last day of Contract Period.
b. Contract completion date shall not be changed by submission of a schedule that shows an early completion date.
c. Contractor shall limit use of lead or lag durations between schedule activities.
PECO PMIS 315705 01 32 18 - 5
d. Activity Duration: Define so no activity is longer than fourteen (14) calendar days, except for non-construction activities including mobilization, shop drawings and submittals, fabrication and delivery of materials and equipment.
e. Procurement Activities: Include procurement process activities for long lead items and major items, requiring a cycle of more than 60 calendar days, as separate activities in the schedule. Procurement cycle activities can include submittals, approvals, purchasing, fabrication, and delivery.
1) Metal Siding;
2) HVAC equipment;
f. Submittal Review Time: Include review and re-submittal times indicated.
Coordinate submittal review times in Construction Baseline Schedule.
g. Substantial Completion: Allow time for Government administrative procedures necessary for certification of Substantial Completion. (For more information, refer to Specification 01 77 00 "Closeout Procedures.")
C. Joint Review, Revision, and Acceptance:
1. Within seven calendar days of receiving Contractor's proposed Construction Baseline
Schedule, Contracting Officer shall review initial Construction Baseline Schedule.
2. Within seven calendar days after review, Contractor shall revise and resubmit Construction
Baseline Schedule in accordance with comments presented from review.
3. In the event the Contractor fails to define any element of work, activity, or logic, and the
Contracting Officer review does not detect this omission or error, such omission or error, when discovered by Contractor or Contracting Officer, shall be corrected by Contractor within seven calendar days and shall not affect contract period.
4. Upon Contracting Officer’s acceptance of the Construction Baseline Schedule, save the schedule as a baseline and update on a monthly basis. Construction schedule updates will be used to evaluate Contractor's monthly applications for payment based upon information developed at monthly Construction Schedule update meetings.
D. Recovery Schedule: When periodic schedule update indicates Work is fourteen (14) or more calendar days behind current accepted schedule, a separate recovery schedule indicating means by which Contractor intends to regain compliance with the schedule shall also be submitted.
Indicate changes to working hours, working days, crew sizes, and equipment required to achieve compliance, and date by which recovery shall be accomplished.
E. Computer Software: Prepare schedules using a program developed specifically to manage construction schedules.
1. Use Microsoft Project or Primavera.
PECO PMIS 315705 01 32 18 - 6
PART 3 - EXECUTION
3.1 CONSTRUCTION SCHEDULE UPDATES
A. Progress Meeting Updates: Provide a three (3) week look-ahead schedule, derived from the currently accepted schedule, before each weekly progress meeting. Utilize look-ahead schedule to facilitate and take notes on discussions held during progress meeting.
B. Monthly Schedule Updates:
1. General: Update the Construction Schedule on a monthly basis to reflect actual construction progress and activities throughout the entire contract period and until the project reaches the substantial completion milestone. The status date of each schedule update shall be the 7th day preceding the progress payment request date.
2. Procedure: Contractor shall meet with the Contracting Officer each month at either a
Construction Schedule update meeting or during a weekly Progress Meeting to review progress made to date and discuss any changes to the baseline schedule.
a. Review actual progress made during update period; actual and potential delaying activities; impediments to progress; issues related to inclement weather; progress toward established milestones and project float. Discussion shall include a review of work anticipated to be performed in the next month. Revisions to the schedule are be identified for evaluation and acceptance or rejection.
3. As Work progresses, indicate Actual Completion percentage for each activity.
4. Progress Payments: Monthly updating of the currently accepted Construction Schedule shall be an integral part of the process upon which progress payments will be made. If
Contractor fails to provide schedule updates or revisions, a portion of the monthly payment may be retained until corrections have been made.
C. Distribution: Distribute copies of accepted schedule to the Contracting Officer, Contracting
Officers Representative, Subcontractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility. Also post a copy in the
Contractor’s field office.
1. When revisions are made, distribute updated schedules to same parties and post in same locations. Delete parties from distribution when they have completed their assigned portion of the Work.
D. Construction Schedule Revisions:
1. Required Revisions: If, as a result of the monthly schedule update, it appears the currently accepted Construction Schedule no longer represents actual prosecution and progress of the work, Contracting Officer will request, and Contractor shall submit, a revision to the
Construction Schedule. Contractor may also request reasonable revisions to currently accepted Construction Schedule in event the Contractor's planning for the work is revised.
If Contractor desires to make changes, Contractor shall notify Contracting Officer in writing, stating reason for proposed revision. Accepted revisions shall be incorporated into currently accepted Construction Schedule for next monthly schedule update.
2. Procedure: If revision to currently accepted Construction Schedule is contemplated, Contractor or Contracting Officer shall advise the other in writing at least seven calendar days prior to next monthly schedule update meeting, describing revision and reasons for
PECO PMIS 315705 01 32 18 - 7
the revision. Government-requested revisions will be presented in writing to the
Contractor, who shall respond in writing within seven calendar days.
3.2 TIME IMPACT ANALYSIS FOR CONTRACT MODIFICATIONS CHANGES DELAYS
AND CONTRACTOR REQUESTS:
1. Requirements: When contract modifications or changes are initiated, delays experienced, or Contractor desires to revise currently accepted Construction Schedule, Contractor shall submit to Contracting Officer a written time impact analysis illustrating the influence of modification, change, delay, or Contractor request on contract time.
2. Time Extensions: Activity delays, resulting in a late completion date projection, shall not automatically mean an extension of contract time is warranted or due to Contractor. It is possible a modification, change, or delay will not affect existing critical path activities or cause non-critical activities to become critical. A modification, change, or delay may result in absorbing a part of available total float that may exist within an activity chain of the
Schedule, not causing any effect on contract time. Time extensions will be granted in accordance with terms of contract.
3. Extension of contract time will be granted only to the extent the equitable time adjustments to activity or activities affected by modification, change, or delay exceeds total (positive or zero) float available on a particular activity.
4. Procedure: Each time impact analysis shall be submitted within time period stated in a request for proposal, or time period designated under the clauses entitled Changes or
Default. In cases where Contractor does not submit a written request for extension of time and a time impact analysis within the designated time, it is mutually agreed that the particular modification, change, delay, or Contractor request does not require an extension of the contract time. Upon acceptance, time impact analysis shall be incorporated into currently accepted Construction Schedule at next monthly schedule update.
5. Contract Modifications: Prepare time-impact analysis using fragnets to demonstrate effect of proposed change on overall Construction Schedule for each proposed contract modification concurrent with submission.
END OF SECTION 01 32 16