About this file

This is a Quality Assurance Checklist for Construction Projects used by the National Park Service (NPS) Regions 6, 7, and 8 to ensure compliance and quality control for construction projects exceeding $25,000. The checklist must be submitted with the Public Relations package for qualifying projects and retained in project files for all others.

The checklist documents completion and verification of 13 mandatory requirements plus additional considerations and final certification. Key requirements include: Compliance Complete (NEPA, Section 106); Investigations for Hazardous Materials and Geotechnical issues; Sustainability Check; Accessibility ABAAS Standards Check; Requirements for Projects exceeding $2 million or $1 million in new construction; Building Code Requirements Check; Fire Protection Requirements and FCO Review; Safety Responsibilities and Requirements; Federal, State, and Local Permits or Public Utility Compliance Interface; Quality Control Review by Acquisition Team and Peer; Final Package for Contracting (Drawings, Specs, IGE Class A); and PHS Review for Civil Water & Wastewater and Food Service Projects. The Acquisition Team includes park user, project manager, contracting officer, contracting officer's representative, compliance staff, and zone or park safety manager. Additional considerations encompass topographical surveys, IT components, preliminary design packages, project delivery method selection, demolition guidance, right-of-way permits, integrated pest management, physical security, and park base funding applications. The form requires sign-offs from responsible individuals and concludes with BCO Certification of Occupancy verification. The specific example documented is the PECO New Siding, Roof and 2 HVAC project (PMIS #315705) at Pecos Park, with completion verified by Steve Crooks on April 12, 2026.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N/A

Building Code Requirements Check

NAME:

DATE:

Click “i” for Supporting Information for Requirements 1-13, and:

14. Other Requirements and Considerations

• Topographical Survey

• IT Components - Software, Hardware, and Networking

• Preliminary Package - Drawings, Specs, IGE Class B

• Design/Bid/Build or Design/Build?

• Non-Historic Real Property Improvements Demolition Guidance

• Right-of-Way Permit

• Integrated Pest Management

• Physical Security and Crime Prevention

• Use of Park Base Funding for Construction

15. BCO Certification of Occupancy

Compliance Complete - NEPA, Section 106, etc.

PROJECT MANAGER/LEAD or RESPONSIBLE

INDIVIDUAL’S APPROVAL

DATE:

Quality Assurance Checklist for Construction Projects NPS Region/DOI 6,7,8 Submit with PR package for construction projects > $25K. Keep completed checklist in project file for all other projects.

NAME:

DATE:

NAME:

Park/Project Title

Project Manager or Lead Name

PMIS # Fund Source Fund Amount PEPC #

Phone Number Contracting Officer Name

N/A

Investigations: Hazardous Materials and Geotechnical

NAME:

DATE:

N/A

Requirements for Projects >$2M or >$1M New Construction

NAME:

DATE:

N/A

Sustainability Check

NAME:

DATE:

N/A

Accessibility ABAAS Standards Check

NAME:

DATE:

Acquisition Team confirms project scope and budget, and agrees on schedule and task assignments. Acquisition Team includes: park user, project manager, contracting officer, contracting officer’s representative, compliance staff, zone or park safety manager, and sometimes others such as fund program manager or park superintendent.

Insert the name of the person who completed or verified requirement.

N/A

Fire Protection Requirements and FCO Review

NAME:

DATE:

Safety Responsibilities and Requirements

NAME:

DATE:

N/A

Federal State Local Permits or Public Utility Comp Interface

NAME:

DATE:

Quality Control Review of Package by Acq Team and Peer

NAME:

DATE:

Final Package for Contracting - Drawings, Specs, IGE Class A

NAME:

DATE:

N/A

PHS Review - Civil Water & Wastewater and Food Service Projects

NAME:

DATE:

REMARKS (ATTACH A SEPARATE PAGE FOR MULTIPLE REMARKS)

November 2025 https://doimspp.sharepoint.com/sites/nps-imr-facility_management/SitePages/QUALITY-ASSURANCE-CHECKLIST.aspx

Name 46:
Name 47:
Check Box 33: Yes
Name 2: 4/15/26
Name 25: Steve Crooks
Name 26: 12apr2026
Name 27:
Name 28: PECO NEW SIDING, ROOF AND 2 HVAC UNITS FOR PARK CURATION BUILDING
Name 29: Steve Crooks
Name 30:
Name 31: 315705
Name 32: CYCLIC
Name 33:
Name 34:
Name 35: 505-208-5078
Name 36:
Name 37:
Check Box 18: Yes
Name 40:
Name 41:
Check Box 20: Yes
Name 42:
Name 43:
Check Box 21: Yes
Name 44:
Name 45:
Check Box 22: Yes
Name 49:
Check Box 24: Yes
Name 50: Jim Huck
Name 51: 4/15/26
Name 52:
Name 53:
Name 54:
Name 55:
Name 56: Steve Crooks
Name 57: 04/12/26
Name 58:
Name 59:
Check Box 31: Yes
Check Box 35: Yes
Title:
Compliance Hover:
Investigations Hover:
Sustainability Hover:
Accessibility Hover:
Requirements Hover:
Building Code Hover:
Fire Protection Hover:
PHS Hover:
Federal Hover:
Quality Hover:
Final Hover:
Pro Man Hover:
Other Hover:
BCO C/O Hover:
Name 48: Jeremy Moss
Safety Hover:

File details come from the government source that posted it. Updated .